3700 W SENECA AVE 90039
Certificate Information: 3700 W SENECA AVE 90039
- Application / Permit
- 24010-10000-03936
- Plan Check / Job No.
- B24LA23136
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New Detached Accessory Dwelling Unit
- Permit Issued
- Issued on 11/12/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/20/2024 | NGHI SU |
| Corrections Issued | 9/25/2024 | NGHI SU |
| Building Plans Picked Up | 9/26/2024 | APPLICANT |
| Plan Check Approved | 10/8/2024 | JOSEPH RAFOLS |
| Issued | 11/12/2024 | APPLICANT |
| CofO in Progress | 4/21/2025 | LILIANA PORTILLO |
| Permit Finaled | 4/23/2025 | DEROLD HAUFF |
| CofO Issued | 4/23/2025 | DEROLD HAUFF |
| Permit Finaled | 4/23/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 9/30/2024 | RUBEN VASQUEZ |
| Address approval | Cleared | 10/3/2024 | JESSICA OPINION |
| Street Frontage | Cleared | 10/3/2024 | JESSICA OPINION |
| Roof/Waste drainage to street | Cleared | 10/7/2024 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 10/8/2024 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 10/8/2024 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Legacy Builders & Remodeling Inc; Lic. No.: 1046784-B | 9507 DORK ST PICO RIVERA, CA 90660 |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/18/2024 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 11/22/2024 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2024 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 12/9/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Sewer | 12/9/2024 | Approved | THOMAS LOGRASSO |
| Underground Mechanical | 12/13/2024 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 12/17/2024 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 12/17/2024 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 12/17/2024 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 12/17/2024 | Conditional Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 12/20/2024 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 12/20/2024 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 12/23/2024 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 12/23/2024 | Approved | THOMAS LOGRASSO |
| Insulation | 12/23/2024 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 12/27/2024 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 1/16/2025 | Approved | CHARLES BOGHOSKHAN |
| Shower Pan | 1/16/2025 | Approved | CHARLES BOGHOSKHAN |
| BUILDING-Rough-Frame | 2/28/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 2/28/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Final | 2/28/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 2/28/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Final | 2/28/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 2/28/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Final | 2/28/2025 | Corrections Issued | NICHOLAS LOPEZ |
| PLUMBING-Final | 2/28/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/28/2025 | SGSOV No Gas | NICHOLAS LOPEZ |
| Service/Power Release | 2/28/2025 | Not Required | NICHOLAS LOPEZ |
| Smoke Detectors | 2/28/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 4/18/2025 | Approved | LILIANA PORTILLO |
| Final | 4/18/2025 | OK to Issue CofO | LILIANA PORTILLO |
| HVAC-Final | 4/18/2025 | Approved | LILIANA PORTILLO |