1752 W 35TH ST 90018

Certificate Information: 1752 W 35TH ST 90018

Application / Permit
24010-10000-03933
Plan Check / Job No.
B24LA23128
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
(N) Detached garage and storage. Work per WFPP design.
Permit Issued
Issued on 12/12/2024
Issuing Office
Metro
Current Status
CofO Issued on 10/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/17/2024 APPLICANT
Assigned to Plan Check Engineer 9/19/2024 EDWIN MARTINEZ
Corrections Issued 9/24/2024 EDWIN MARTINEZ
Building Plans Picked Up 9/26/2024 APPLICANT
Applicant returned to address corrections 11/20/2024 ALEXANDER JOO
Plan Check Approved 12/12/2024 SAMUEL GONZALEZ
Issued 12/12/2024 APPLICANT
CofO in Progress 10/15/2025 MICHAEL LEWIS
Permit Finaled 10/17/2025 DEROLD HAUFF
CofO Issued 10/17/2025 DEROLD HAUFF
Permit Finaled 10/17/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/3/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 12/9/2024 JUSTIN BICOL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/9/2025 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 7/9/2025 Partial Approval SABAS ALONSO
METHANE-Barrier 7/9/2025 Not Ready for Inspection SABAS ALONSO
METHANE-Subgrade 7/9/2025 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 7/11/2025 Approved SABAS ALONSO
Pre-Inspection 8/4/2025 Partial Inspection SABAS ALONSO
BUILDING-Rough-Frame 8/22/2025 Not Ready for Inspection BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 8/22/2025 Approved BRENDAN MORELLI
Green Building Rough 8/22/2025 Not Ready for Inspection BRENDAN MORELLI
BUILDING-Rough-Frame 9/3/2025 Approved LUIS CASTRO
Green Building Rough 9/3/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 9/3/2025 Approved LUIS CASTRO
Insulation 9/5/2025 Approved SABAS ALONSO
Drywall Nailing 9/11/2025 Approved SABAS ALONSO
ELECTRICAL-Final 10/1/2025 Not Ready for Inspection SABAS ALONSO
Final 10/1/2025 Corrections Issued SABAS ALONSO
Green Building Final 10/1/2025 Not Ready for Inspection SABAS ALONSO
HVAC-Final 10/1/2025 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 10/1/2025 SGSOV Approved SABAS ALONSO
Service/Power Release 10/1/2025 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 10/1/2025 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 10/3/2025 Not Ready for Inspection BARRY HACHE
Smoke Detectors 10/3/2025 Corrections Issued BARRY HACHE
ELECTRICAL-Final 10/7/2025 Approved SABAS ALONSO
Final 10/7/2025 OK to Issue CofO SABAS ALONSO
Green Building Final 10/7/2025 Approved SABAS ALONSO
Service/Power Release 10/7/2025 Approved SABAS ALONSO
Smoke Detectors 10/7/2025 Approved SABAS ALONSO