4431 N GARDEN HOMES AVE 90032
Certificate Information: 4431 N GARDEN HOMES AVE 90032
- Application / Permit
- 24010-10000-03912
- Plan Check / Job No.
- B24LA22824
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN.* New detached 2-story ADU at rear of property per LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 4/18/2025
- Issuing Office
- Current Status
- CofO Issued on 2/27/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2024 | HUAN LE |
| Corrections Issued | 12/5/2024 | HUAN LE |
| Quality Review Completed | 12/6/2024 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 2/21/2025 | HUAN LE |
| Applicant returned to address corrections | 2/28/2025 | HUAN LE |
| Plan Check Approved | 4/16/2025 | HUAN LE |
| Issued | 4/18/2025 | APPLICANT |
| CofO in Progress | 2/27/2026 | LILIANA PORTILLO |
| Permit Finaled | 2/27/2026 | DEROLD HAUFF |
| CofO Issued | 2/27/2026 | DEROLD HAUFF |
| Permit Finaled | 2/27/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/31/2025 | CHRISTINA BRACO |
| Roof/Waste drainage to street | Cleared | 1/31/2025 | CHRISTINA BRACO |
| Grading Pre-Inspection | Cleared | 2/1/2025 | MICHAEL TEMPLE |
| Miscellaneous | Cleared | 2/3/2025 | ALBERT TAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2025 | CHRISTINA BRACO |
| Sewer availability | Cleared | 2/4/2025 | CHRISTINA BRACO |
| GPI Written Notices | Cleared | 2/21/2025 | HUAN LE |
| Construction near power lines | Cleared | 4/7/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: NA4808 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/17/2025 | Corrections Issued | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 6/23/2025 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 6/23/2025 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 6/26/2025 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2025 | Partial Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 9/15/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2025 | Partial Approval | LILIANA PORTILLO |
| HVAC-Rough | 9/15/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 9/15/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/9/2025 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 10/9/2025 | Corrections Issued | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 10/9/2025 | Approved | LILIANA PORTILLO |
| Deputy Wood Construction | 10/14/2025 | Conditional Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/17/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/17/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Rough | 10/17/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 10/17/2025 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/24/2025 | Conditional Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/24/2025 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 10/24/2025 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 10/28/2025 | Approved | GEM DE OCAMPO |
| Insulation | 10/30/2025 | Corrections Issued | LILIANA PORTILLO |
| Drywall Nailing | 11/3/2025 | Partial Approval | LILIANA PORTILLO |
| Insulation | 11/3/2025 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 11/10/2025 | Approved | LILIANA PORTILLO |
| Green Building Rough | 11/10/2025 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 1/30/2026 | Approved | LILIANA PORTILLO |
| Final | 1/30/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Footing/Foundation/Slab | 1/30/2026 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 1/30/2026 | SGSOV Not Required | LILIANA PORTILLO |
| Service/Power Release | 1/30/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 1/30/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Underground Mechanical | 1/30/2026 | Approved | LILIANA PORTILLO |
| Final | 2/9/2026 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 2/9/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Service/Power Release | 2/9/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 2/9/2026 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 2/17/2026 | Approved | DAVID WILLIAMS |
| Final | 2/17/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Green Building Final | 2/17/2026 | Approved | DAVID WILLIAMS |
| Service/Power Release | 2/17/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| ELECTRICAL-Final | 2/20/2026 | Approved | LILIANA PORTILLO |
| Final | 2/20/2026 | Conditional Approval | LILIANA PORTILLO |
| HVAC-Final | 2/20/2026 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 2/20/2026 | Approved | LILIANA PORTILLO |
| Service/Power Release | 2/20/2026 | Approved | LILIANA PORTILLO |
| Final | 2/26/2026 | OK to Issue CofO | LILIANA PORTILLO |