4039 S MICHAEL AVE 90066

Certificate Information: 4039 S MICHAEL AVE 90066

Application / Permit
24010-10000-03898
Plan Check / Job No.
B24LA22651
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SINGLE FAMILY DWELLING. FIRE SPRINKLER 13D THROUGH OUT.
Permit Issued
Issued on 1/6/2025
Issuing Office
Metro
Current Status
CofO Issued on 9/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/13/2024 APPLICANT
Assigned to Plan Check Engineer 9/26/2024 DANIEL YIP
Corrections Issued 10/3/2024 DANIEL YIP
Quality Review Completed 10/9/2024 KEN GILL
Building Plans Picked Up 10/10/2024 APPLICANT
Plan Check Approved 12/24/2024 DANIEL YIP
Issued 1/6/2025 APPLICANT
Permit Finaled 9/9/2025 RICHARD STEINBACH
CofO Issued 9/9/2025 RICHARD STEINBACH
Permit Finaled 9/9/2025 RICHARD STEINBACH

Permit Application Clearance Information

Low Impact Development (LID) Cleared 10/24/2024 SARAH YOUSSEF
Specific Plan Cleared 11/6/2024 JOSHUA JONES
Eng Process Fee Ord 176,300 Cleared 11/22/2024 VLADIMIR ARUTYUNYAN
Roof/Waste drainage to street Cleared 11/22/2024 VLADIMIR ARUTYUNYAN
Sewer availability Cleared 11/22/2024 VLADIMIR ARUTYUNYAN
Hydrant and Access approval Cleared 12/19/2024 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/24/2025 Approved JESUS PINEDA
Sewer 1/24/2025 Approved JESUS PINEDA
Underground Mechanical 1/24/2025 Partial Approval JESUS PINEDA
Footing/Foundation/Slab 2/10/2025 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 2/19/2025 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 2/24/2025 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 4/4/2025 Partial Approval MICHAEL ALLEN
HVAC-Rough 4/4/2025 Approved MICHAEL ALLEN
PLUMBING-Rough 4/9/2025 Approved MICHAEL ALLEN
ELECTRICAL-Rough 4/14/2025 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 4/17/2025 Not Ready for Inspection MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 4/21/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 4/25/2025 Partial Approval JAYLIN GRAVITTE
BUILDING-Rough-Frame 4/29/2025 Approved MICHAEL ALLEN
Green Building Rough 4/29/2025 Approved MICHAEL ALLEN
Shower Pan 4/29/2025 Approved MICHAEL ALLEN
Verify Sprinkler Sign Off 4/29/2025 Approved MICHAEL ALLEN
Insulation 5/2/2025 Approved JAYLIN GRAVITTE
Interior/Exterior Lathing 5/2/2025 Approved JAYLIN GRAVITTE
Drywall Nailing 5/8/2025 Approved JAYLIN GRAVITTE
ELECTRICAL-Final 8/26/2025 Corrections Issued WILBER ROSALES
HVAC-Final 8/26/2025 Corrections Issued WILBER ROSALES
PLUMBING-Final 8/28/2025 Approved WILBER ROSALES
ELECTRICAL-Final 9/4/2025 Approved WILBER ROSALES
Final 9/4/2025 Conditional Approval WILBER ROSALES
Green Building Final 9/4/2025 Approved WILBER ROSALES
HVAC-Final 9/4/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 9/4/2025 SGSOV Not Required WILBER ROSALES
Service/Power Release 9/4/2025 Approved WILBER ROSALES
Smoke Detectors 9/4/2025 Approved WILBER ROSALES
Verify Sprinkler Sign Off 9/4/2025 Approved WILBER ROSALES