4039 S MICHAEL AVE 90066
Certificate Information: 4039 S MICHAEL AVE 90066
- Application / Permit
- 24010-10000-03898
- Plan Check / Job No.
- B24LA22651
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SINGLE FAMILY DWELLING. FIRE SPRINKLER 13D THROUGH OUT.
- Permit Issued
- Issued on 1/6/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2024 | DANIEL YIP |
| Corrections Issued | 10/3/2024 | DANIEL YIP |
| Quality Review Completed | 10/9/2024 | KEN GILL |
| Building Plans Picked Up | 10/10/2024 | APPLICANT |
| Plan Check Approved | 12/24/2024 | DANIEL YIP |
| Issued | 1/6/2025 | APPLICANT |
| Permit Finaled | 9/9/2025 | RICHARD STEINBACH |
| CofO Issued | 9/9/2025 | RICHARD STEINBACH |
| Permit Finaled | 9/9/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 10/24/2024 | SARAH YOUSSEF |
| Specific Plan | Cleared | 11/6/2024 | JOSHUA JONES |
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2024 | VLADIMIR ARUTYUNYAN |
| Roof/Waste drainage to street | Cleared | 11/22/2024 | VLADIMIR ARUTYUNYAN |
| Sewer availability | Cleared | 11/22/2024 | VLADIMIR ARUTYUNYAN |
| Hydrant and Access approval | Cleared | 12/19/2024 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/24/2025 | Approved | JESUS PINEDA |
| Sewer | 1/24/2025 | Approved | JESUS PINEDA |
| Underground Mechanical | 1/24/2025 | Partial Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 2/10/2025 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2025 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2025 | Partial Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2025 | Partial Approval | MICHAEL ALLEN |
| HVAC-Rough | 4/4/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 4/9/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Rough | 4/14/2025 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2025 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 4/25/2025 | Partial Approval | JAYLIN GRAVITTE |
| BUILDING-Rough-Frame | 4/29/2025 | Approved | MICHAEL ALLEN |
| Green Building Rough | 4/29/2025 | Approved | MICHAEL ALLEN |
| Shower Pan | 4/29/2025 | Approved | MICHAEL ALLEN |
| Verify Sprinkler Sign Off | 4/29/2025 | Approved | MICHAEL ALLEN |
| Insulation | 5/2/2025 | Approved | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 5/2/2025 | Approved | JAYLIN GRAVITTE |
| Drywall Nailing | 5/8/2025 | Approved | JAYLIN GRAVITTE |
| ELECTRICAL-Final | 8/26/2025 | Corrections Issued | WILBER ROSALES |
| HVAC-Final | 8/26/2025 | Corrections Issued | WILBER ROSALES |
| PLUMBING-Final | 8/28/2025 | Approved | WILBER ROSALES |
| ELECTRICAL-Final | 9/4/2025 | Approved | WILBER ROSALES |
| Final | 9/4/2025 | Conditional Approval | WILBER ROSALES |
| Green Building Final | 9/4/2025 | Approved | WILBER ROSALES |
| HVAC-Final | 9/4/2025 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 9/4/2025 | SGSOV Not Required | WILBER ROSALES |
| Service/Power Release | 9/4/2025 | Approved | WILBER ROSALES |
| Smoke Detectors | 9/4/2025 | Approved | WILBER ROSALES |
| Verify Sprinkler Sign Off | 9/4/2025 | Approved | WILBER ROSALES |