1648 S ABBOT KINNEY BLVD 90291

Certificate Information: 1648 S ABBOT KINNEY BLVD 90291

Application / Permit
24010-10000-03833
Plan Check / Job No.
B24LA22063
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
EPLAN***PROPOSED RETAIL BUILDING
Permit Issued
Issued on 5/22/2025
Issuing Office
Current Status
Issued on 5/22/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/11/2024 APPLICANT
Assigned to Plan Check Engineer 9/12/2024 SINA KHOSRAVI
Corrections Issued 9/16/2024 SINA KHOSRAVI
Assigned to Zoning Architect 9/19/2024 BENNY WONG
Quality Review Completed 10/1/2024 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 1/17/2025 SINA KHOSRAVI
Applicant returned to address corrections 5/2/2025 SINA KHOSRAVI
Plan Check Approved 5/22/2025 SINA KHOSRAVI
Issued 5/22/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/18/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 9/18/2024 DARIN LAM
Sewer availability Cleared 9/18/2024 DARIN LAM
Roof/Waste drainage to street Cleared 10/8/2024 DARIN LAM
Green Code Cleared 10/23/2024 Jesse Arellano
Flood clearance Cleared 10/28/2024 RAYMOND LAM
Specific Plan Cleared 12/10/2024 JOSHUA JONES
Specific Plan Cleared 12/13/2024 JOSHUA JONES
Highway dedication Cleared 1/2/2025 KIMBERLY HERNANDEZ
Hydrant and Access approval Cleared 1/2/2025 JOHN CONNEALLY
Encroachment in public way Cleared 1/22/2025 SAUL GARCIA
Bicycle Parking Cleared 1/27/2025 DARIN LAM
DAS Clearance Cleared 1/30/2025 Jesse Arellano
Coastal Zone Cleared 4/9/2025 DAVID URITA
Miscellaneous Cleared 4/9/2025 DAVID URITA
Miscellaneous Cleared 4/9/2025 DAVID URITA
Miscellaneous Cleared 4/9/2025 DAVID URITA
Miscellaneous Cleared 4/9/2025 DAVID URITA
Specific Plan Cleared 4/9/2025 DAVID URITA
Zoning Plan Check Cleared 4/23/2025 BENNY WONG

Contact Information

Contractor Owner-Builder       ,
Engineer Sandoval,, Martin; Lic. No.: NA56905       ,

Inspector Information

PAUL DAVIDSON, (310) 914-3914 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Final 7/28/2026   
Smoke Detectors 7/28/2026   
SGSOV-Seismic Gas S/O Valve 7/28/2026   
Green Building Final 7/28/2026   

Inspection Request History

Pre-Inspection 6/11/2025 Approved PAUL DAVIDSON
Footing/Foundation/Slab 8/8/2025 Partial Approval DANIEL VARNUM
METHANE-Barrier 8/8/2025 Partial Inspection DANIEL VARNUM
METHANE-Subgrade 8/8/2025 Partial Inspection DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 10/27/2025 Partial Approval DANIEL VARNUM
Green Building Rough 10/27/2025 Not Ready for Inspection DANIEL VARNUM
METHANE-Rough 10/27/2025 Not Ready for Inspection DANIEL VARNUM
Verify Sprinkler Sign Off 10/27/2025 Not Ready for Inspection DANIEL VARNUM
Wood Frame 10/27/2025 Not Ready for Inspection DANIEL VARNUM
Drywall Nailing 12/15/2025 Partial Approval PAUL DAVIDSON
Footing/Foundation/Slab 12/15/2025 Partial Approval PAUL DAVIDSON
METHANE-Barrier 12/15/2025 Not Ready for Inspection PAUL DAVIDSON
METHANE-Subgrade 12/15/2025 Not Ready for Inspection PAUL DAVIDSON
Floor/Roof Diaphrgm/Shear Wall 3/12/2026 Partial Approval PAUL DAVIDSON
Footing/Foundation/Slab 3/12/2026 Partial Approval PAUL DAVIDSON
METHANE-Barrier 3/12/2026 Approved PAUL DAVIDSON
METHANE-Subgrade 3/12/2026 Approved PAUL DAVIDSON
Green Building Rough 4/15/2026 Approved PAUL DAVIDSON
METHANE-Rough 4/15/2026 Approved PAUL DAVIDSON
Verify Sprinkler Sign Off 4/15/2026 Not Ready for Inspection PAUL DAVIDSON
Wood Frame 4/15/2026 Partial Approval PAUL DAVIDSON
Insulation 4/23/2026 Not Ready for Inspection PAUL DAVIDSON
Interior/Exterior Lathing 4/23/2026 Not Ready for Inspection PAUL DAVIDSON
Insulation 4/27/2026 Approved PAUL DAVIDSON
Interior/Exterior Lathing 4/27/2026 Approved PAUL DAVIDSON
Wood Frame 4/27/2026 Partial Approval PAUL DAVIDSON
Drywall Nailing 5/7/2026 Not Ready for Inspection PAUL DAVIDSON
Drywall Nailing 5/15/2026 Approved DANIEL VARNUM
Final 6/23/2026 Not Ready for Inspection PAUL DAVIDSON
Footing/Foundation/Slab 6/23/2026 Approved PAUL DAVIDSON
Pre-Inspection 6/23/2026 Approved PAUL DAVIDSON
Reinforced Concrete Frame 6/23/2026 Approved PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 6/23/2026 SGSOV Not Ready PAUL DAVIDSON
Smoke Detectors 6/23/2026 Not Ready for Inspection PAUL DAVIDSON
Verify Sprinkler Sign Off 6/23/2026 Approved PAUL DAVIDSON
Wood Frame 6/23/2026 Approved PAUL DAVIDSON
Final 7/20/2026 Not Ready for Inspection PAUL DAVIDSON
Smoke Detectors 7/20/2026 Not Ready for Inspection PAUL DAVIDSON