188 S COMMONWEALTH AVE 90004

Certificate Information: 188 S COMMONWEALTH AVE 90004

Application / Permit
24010-10000-03822
Plan Check / Job No.
B24LA22008
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: new 2-story ADU with garage per LAMC 12.22 A.33(c)-(d). Provided parking spaces are for the ADU.
Permit Issued
Issued on 5/27/2025
Issuing Office
Current Status
Issued on 5/27/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/17/2024 APPLICANT
Assigned to Plan Check Engineer 9/26/2024 ARSALAN SHABESTARI
Corrections Issued 10/8/2024 ARSALAN SHABESTARI
Quality Review Completed 10/17/2024 YOUNG KIM
Applicant returned to address corrections 1/3/2025 ARSALAN SHABESTARI
Applicant returned to address corrections 2/10/2025 ARSALAN SHABESTARI
Plan Check Approved 5/21/2025 ARSALAN SHABESTARI
Issued 5/27/2025 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 10/21/2024 ENRIQUE ACOSTA
Address approval Cleared 10/28/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 11/6/2024 WALLIE JONG
Sewer availability Cleared 11/6/2024 WALLIE JONG
Roof/Waste drainage to street Cleared 11/13/2024 WALLIE JONG
Specific Plan Cleared 12/11/2024 YAMILLET BRIZUELA
GPI Written Notices Cleared 5/21/2025 ARSALAN SHABESTARI
Grading Pre-Inspection Cleared 5/21/2025 ARSALAN SHABESTARI

Contact Information

Contractor N A N D C O Llc; Lic. No.: 1044615-B       ,
Contractor Nandco Construction; Lic. No.: 1044615-B       ,
Engineer Standley,, Craig Erick; Lic. No.: NA87675       ,

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Subgrade 8/26/2025 Not Ready for Inspection LUIS CCAMACHO
METHANE-Barrier 9/3/2025 Approved LUIS CCAMACHO
Excavation/Setback/Form/Re-Bar 9/17/2025 Not Ready for Inspection JOEY BUCHANAN
Footing/Foundation/Slab 9/17/2025 Not Ready for Inspection JOEY BUCHANAN
METHANE-Subgrade 9/17/2025 Not Ready for Inspection JOEY BUCHANAN
Footing/Foundation/Slab 9/19/2025 Approved WILLIAM SIERRA
METHANE-Subgrade 9/19/2025 Approved WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 10/16/2025 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/20/2025 Partial Approval WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 10/30/2025 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 12/16/2025 Partial Inspection WILLIAM SIERRA
Green Building Rough 12/16/2025 Approved WILLIAM SIERRA
Interior/Exterior Lathing 12/16/2025 Partial Approval WILLIAM SIERRA
METHANE-Rough 12/16/2025 Corrections Issued WILLIAM SIERRA
Verify Sprinkler Sign Off 12/16/2025 Approved WILLIAM SIERRA
Wood Frame 12/16/2025 Corrections Issued WILLIAM SIERRA
Deputy Drilled-In Anchors 1/7/2026 Approved WILLIAM SIERRA
Deputy Wood Construction 1/7/2026 Approved WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 1/7/2026 Approved WILLIAM SIERRA
Insulation 1/7/2026 Approved WILLIAM SIERRA
METHANE-Rough 1/7/2026 Approved WILLIAM SIERRA
Wood Frame 1/7/2026 Approved WILLIAM SIERRA
Drywall Nailing 1/12/2026 Approved WILLIAM SIERRA