188 S COMMONWEALTH AVE 90004
Certificate Information: 188 S COMMONWEALTH AVE 90004
- Application / Permit
- 24010-10000-03822
- Plan Check / Job No.
- B24LA22008
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: new 2-story ADU with garage per LAMC 12.22 A.33(c)-(d). Provided parking spaces are for the ADU.
- Permit Issued
- Issued on 5/27/2025
- Issuing Office
- Current Status
- Issued on 5/27/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2024 | ARSALAN SHABESTARI |
| Corrections Issued | 10/8/2024 | ARSALAN SHABESTARI |
| Quality Review Completed | 10/17/2024 | YOUNG KIM |
| Applicant returned to address corrections | 1/3/2025 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 2/10/2025 | ARSALAN SHABESTARI |
| Plan Check Approved | 5/21/2025 | ARSALAN SHABESTARI |
| Issued | 5/27/2025 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/21/2024 | ENRIQUE ACOSTA |
| Address approval | Cleared | 10/28/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 11/6/2024 | WALLIE JONG |
| Sewer availability | Cleared | 11/6/2024 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 11/13/2024 | WALLIE JONG |
| Specific Plan | Cleared | 12/11/2024 | YAMILLET BRIZUELA |
| GPI Written Notices | Cleared | 5/21/2025 | ARSALAN SHABESTARI |
| Grading Pre-Inspection | Cleared | 5/21/2025 | ARSALAN SHABESTARI |
Contact Information
| Contractor | N A N D C O Llc; Lic. No.: 1044615-B | , |
| Contractor | Nandco Construction; Lic. No.: 1044615-B | , |
| Engineer | Standley,, Craig Erick; Lic. No.: NA87675 | , |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 8/26/2025 | Not Ready for Inspection | LUIS CCAMACHO |
| METHANE-Barrier | 9/3/2025 | Approved | LUIS CCAMACHO |
| Excavation/Setback/Form/Re-Bar | 9/17/2025 | Not Ready for Inspection | JOEY BUCHANAN |
| Footing/Foundation/Slab | 9/17/2025 | Not Ready for Inspection | JOEY BUCHANAN |
| METHANE-Subgrade | 9/17/2025 | Not Ready for Inspection | JOEY BUCHANAN |
| Footing/Foundation/Slab | 9/19/2025 | Approved | WILLIAM SIERRA |
| METHANE-Subgrade | 9/19/2025 | Approved | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2025 | Partial Approval | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2025 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2025 | Partial Inspection | WILLIAM SIERRA |
| Green Building Rough | 12/16/2025 | Approved | WILLIAM SIERRA |
| Interior/Exterior Lathing | 12/16/2025 | Partial Approval | WILLIAM SIERRA |
| METHANE-Rough | 12/16/2025 | Corrections Issued | WILLIAM SIERRA |
| Verify Sprinkler Sign Off | 12/16/2025 | Approved | WILLIAM SIERRA |
| Wood Frame | 12/16/2025 | Corrections Issued | WILLIAM SIERRA |
| Deputy Drilled-In Anchors | 1/7/2026 | Approved | WILLIAM SIERRA |
| Deputy Wood Construction | 1/7/2026 | Approved | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2026 | Approved | WILLIAM SIERRA |
| Insulation | 1/7/2026 | Approved | WILLIAM SIERRA |
| METHANE-Rough | 1/7/2026 | Approved | WILLIAM SIERRA |
| Wood Frame | 1/7/2026 | Approved | WILLIAM SIERRA |
| Drywall Nailing | 1/12/2026 | Approved | WILLIAM SIERRA |