1841-1843 W LOWE ST 90039
Certificate Information: 1841-1843 W LOWE ST 90039
- Application / Permit
- 24010-10000-03795
- Plan Check / Job No.
- B24LA21775
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. New 2-Story 2-units ADUs per PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g)
- Permit Issued
- Issued on 12/12/2024
- Issuing Office
- Current Status
- CofO Issued on 9/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2024 | KHEDER ALRAZAA |
| Corrections Issued | 9/24/2024 | KHEDER ALRAZAA |
| Quality Review Completed | 9/26/2024 | GARO TELMI |
| Plan Check Approved | 11/14/2024 | KHEDER ALRAZAA |
| Issued | 12/12/2024 | APPLICANT |
| CofO in Progress | 9/15/2025 | HAMIK HARTOUNIAN |
| Permit Finaled | 9/18/2025 | DEROLD HAUFF |
| CofO Issued | 9/18/2025 | DEROLD HAUFF |
| Permit Finaled | 9/18/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 10/8/2024 | DALIA MOKAYED |
| Address approval | Cleared | 10/9/2024 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 10/11/2024 | CHRISTINA BRACO |
| Sewer availability | Cleared | 10/11/2024 | CHRISTINA BRACO |
| Roof/Waste drainage to street | Cleared | 10/23/2024 | CELINA MORENO |
Contact Information
| Contractor | Bek & Bek Inc; Lic. No.: 1056403-B | , |
| Contractor | So-Cal Construction & Electric; Lic. No.: 1056403-B | , |
| Engineer | Keshishian,, Anthony; Lic. No.: C89551 | 2654 RISA D GLENDALE, CA 91208 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/17/2025 | Partial Inspection | WILLIAM SIERRA |
| PLUMBING-Rough | 2/10/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 2/21/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Grounding or Bonding | 2/21/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 2/25/2025 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 2/25/2025 | Approved | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 3/3/2025 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2025 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2025 | Approved | JOSH MEISTER |
| ELECTRICAL-Rough | 3/28/2025 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2025 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 3/28/2025 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/2/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 4/2/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| MERV13>=Rough | 4/2/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 4/2/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 4/9/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Special/Order Compliance | 4/9/2025 | Partial Inspection | OSVALDO PARAMO |
| Pre-Inspection | 4/21/2025 | Partial Inspection | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 4/22/2025 | Conditional Approval | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 4/30/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 4/30/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| MERV13>=Rough | 4/30/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 4/30/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 5/19/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 5/19/2025 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 5/19/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| MERV13>=Rough | 5/19/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 5/19/2025 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 5/19/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 5/22/2025 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 5/22/2025 | Approved | BRENDAN MORELLI |
| MERV13>=Rough | 5/22/2025 | Approved | BRENDAN MORELLI |
| Verify Sprinkler Sign Off | 5/22/2025 | Approved | BRENDAN MORELLI |
| Insulation | 5/23/2025 | Approved | BRENDAN MORELLI |
| Shower Pan | 5/23/2025 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 5/30/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 5/30/2025 | Partial Approval | ALEX COLIN |
| ELECTRICAL-Final | 9/11/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 9/11/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |
| HVAC-Final | 9/11/2025 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Final | 9/11/2025 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 9/11/2025 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 9/11/2025 | SGSOV No Gas | HAMIK HARTOUNIAN |
| Service/Power Release | 9/11/2025 | Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 9/11/2025 | Approved | HAMIK HARTOUNIAN |