4528 E MONT EAGLE PL 90041
Certificate Information: 4528 E MONT EAGLE PL 90041
- Application / Permit
- 24010-10000-03790
- Plan Check / Job No.
- B24LA21685
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePLAN. NFPA 13D FIRE SPRINKLER REQUIRED. MAJOR REMODEL AND NEW 1ST AND 2ND FLOOR ADDITION TO (E) SINGLE FAMILY DWELLING WITH ATTACHED CARPORT
- Permit Issued
- Issued on 10/10/2025
- Issuing Office
- Current Status
- Issued on 10/10/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2024 | KEVIN MORALES |
| Corrections Issued | 9/17/2024 | KEVIN MORALES |
| Quality Review Completed | 9/18/2024 | EUGENE BARBEAU |
| Applicant returned to address corrections | 1/3/2025 | KEVIN MORALES |
| Plan Check Approved | 1/29/2025 | KEVIN MORALES |
| Plan Check Approved | 4/17/2025 | KEVIN MORALES |
| Issued | 10/10/2025 | APPLICANT |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 9/17/2024 | KEVIN MORALES |
| Grading Pre-Inspection | Cleared | 9/17/2024 | KEVIN MORALES |
| BHO/Hillside ordinance | Cleared | 9/19/2024 | JUSTIN BICOL |
| BHO/Hillside ordinance | Cleared | 9/19/2024 | JUSTIN BICOL |
| BHO/Hillside ordinance | Cleared | 9/19/2024 | JUSTIN BICOL |
| BHO/Hillside ordinance | Cleared | 9/19/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 9/19/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 9/19/2024 | JUSTIN BICOL |
| Hydrant and Access approval | Cleared | 1/8/2025 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2026 |
Inspection Request History
| Pre-Inspection | 11/7/2025 | Partial Inspection | NICHOLAS LOPEZ |
| PLUMBING-Rough | 11/10/2025 | Partial Approval | NICHOLAS LOPEZ |
| Underground Mechanical | 11/10/2025 | Partial Approval | NICHOLAS LOPEZ |
| Excavation/Setback/Form/Re-Bar | 11/25/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 11/25/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Excavation/Setback/Form/Re-Bar | 11/26/2025 | Approved | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 11/26/2025 | Approved | NICHOLAS LOPEZ |