6860 N AURA AVE 91335

Certificate Information: 6860 N AURA AVE 91335

Application / Permit
24010-10000-03783
Plan Check / Job No.
B24LA21602
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILY DWELLING AT REAR OF LOT PER SB9 TWO-UNIT DEVELOPMENT GCS 65852.21 NFPA 13D
Permit Issued
Issued on 2/18/2025
Issuing Office
Metro
Current Status
CofO Issued on 10/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2024 APPLICANT
Assigned to Plan Check Engineer 9/19/2024 VIVIAN LAO
Corrections Issued 9/26/2024 VIVIAN LAO
Quality Review Completed 9/27/2024 KEN GILL
Building Plans Picked Up 10/7/2024 APPLICANT
Applicant returned to address corrections 11/20/2024 VIVIAN LAO
Applicant returned to address corrections 12/17/2024 VIVIAN LAO
Plan Check Approved 2/18/2025 VIVIAN LAO
Issued 2/18/2025 APPLICANT
CofO in Progress 10/8/2025 ARUTYUN MADATYAN
Permit Finaled 10/9/2025 JOHN JANSON
CofO Issued 10/9/2025 JOHN JANSON
Permit Finaled 10/9/2025 JOHN JANSON

Permit Application Clearance Information

Senate Bill 9 Cleared 11/4/2024 NATHAN ROMINE
ZI Cleared 11/4/2024 NATHAN ROMINE
Address approval Cleared 11/8/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/12/2024 CARLOS AGUILERA
Sewer availability Cleared 11/12/2024 CARLOS AGUILERA
Construction near power lines Cleared 1/8/2025 EDGAR PASCUA
Low Impact Development (LID) Cleared 1/13/2025 ERNEST TSE
Roof/Waste drainage to street Cleared 1/15/2025 CARLOS AGUILERA
Hydrant and Access approval Cleared 1/29/2025 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,
Engineer Zolfaghari,, Saeed; Lic. No.: C86761 6201 BEE AVE      AGOURA HILLS, CA 91301

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 3/5/2025 No Access for Inspection ARUTYUN MADATYAN
Underground Mechanical 3/5/2025 No Access for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 3/10/2025 Partial Approval ARUTYUN MADATYAN
Sewer 3/10/2025 Not Ready for Inspection ARUTYUN MADATYAN
Deputy Drilled-In Anchors 3/17/2025 Approved ARUTYUN MADATYAN
Excavation/Setback/Form/Re-Bar 3/17/2025 Approved ARUTYUN MADATYAN
Footing/Foundation/Slab 3/17/2025 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 4/4/2025 Partial Approval ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 4/23/2025 Corrections Issued ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 4/28/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 5/12/2025 Partial Approval ARUTYUN MADATYAN
PLUMBING-Rough 5/13/2025 Corrections Issued ARUTYUN MADATYAN
ELECTRICAL-Rough 5/16/2025 Approved JUAN ALVARADO
HVAC-Rough 5/16/2025 Approved JUAN ALVARADO
PLUMBING-Rough 5/16/2025 Approved JUAN ALVARADO
BUILDING-Rough-Frame 5/20/2025 Approved ARUTYUN MADATYAN
Green Building Rough 5/20/2025 Approved ARUTYUN MADATYAN
Verify Sprinkler Sign Off 5/20/2025 Approved ARUTYUN MADATYAN
Insulation 5/28/2025 Approved ARUTYUN MADATYAN
Drywall Nailing 6/4/2025 Approved ARUTYUN MADATYAN
Shower Pan 6/5/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 6/10/2025 Partial Approval ARUTYUN MADATYAN
Sewer 7/25/2025 Not Ready for Inspection HENRY KIM
Sewer 8/6/2025 Approved GEVORK IPCHYAN
Underground Mechanical 8/6/2025 Approved GEVORK IPCHYAN
Underground Mechanical 8/11/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 10/2/2025 No Access for Inspection ARUTYUN MADATYAN
Final 10/2/2025 Corrections Issued ARUTYUN MADATYAN
Green Building Final 10/2/2025 Approved ARUTYUN MADATYAN
HVAC-Final 10/2/2025 Approved ARUTYUN MADATYAN
PLUMBING-Final 10/2/2025 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 10/2/2025 SGSOV Approved ARUTYUN MADATYAN
Service/Power Release 10/2/2025 Not Ready for Inspection ARUTYUN MADATYAN
Smoke Detectors 10/2/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 10/7/2025 Approved ARUTYUN MADATYAN
Final 10/7/2025 OK to Issue CofO ARUTYUN MADATYAN
HVAC-Final 10/7/2025 Approved ARUTYUN MADATYAN
PLUMBING-Final 10/7/2025 Approved ARUTYUN MADATYAN
Service/Power Release 10/7/2025 Approved ARUTYUN MADATYAN