6860 N AURA AVE 91335
Certificate Information: 6860 N AURA AVE 91335
- Application / Permit
- 24010-10000-03783
- Plan Check / Job No.
- B24LA21602
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING AT REAR OF LOT PER SB9 TWO-UNIT DEVELOPMENT GCS 65852.21 NFPA 13D
- Permit Issued
- Issued on 2/18/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2024 | VIVIAN LAO |
| Corrections Issued | 9/26/2024 | VIVIAN LAO |
| Quality Review Completed | 9/27/2024 | KEN GILL |
| Building Plans Picked Up | 10/7/2024 | APPLICANT |
| Applicant returned to address corrections | 11/20/2024 | VIVIAN LAO |
| Applicant returned to address corrections | 12/17/2024 | VIVIAN LAO |
| Plan Check Approved | 2/18/2025 | VIVIAN LAO |
| Issued | 2/18/2025 | APPLICANT |
| CofO in Progress | 10/8/2025 | ARUTYUN MADATYAN |
| Permit Finaled | 10/9/2025 | JOHN JANSON |
| CofO Issued | 10/9/2025 | JOHN JANSON |
| Permit Finaled | 10/9/2025 | JOHN JANSON |
Permit Application Clearance Information
| Senate Bill 9 | Cleared | 11/4/2024 | NATHAN ROMINE |
| ZI | Cleared | 11/4/2024 | NATHAN ROMINE |
| Address approval | Cleared | 11/8/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/12/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/12/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 1/8/2025 | EDGAR PASCUA |
| Low Impact Development (LID) | Cleared | 1/13/2025 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 1/15/2025 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 1/29/2025 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zolfaghari,, Saeed; Lic. No.: C86761 | 6201 BEE AVE AGOURA HILLS, CA 91301 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 3/5/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| Underground Mechanical | 3/5/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 3/10/2025 | Partial Approval | ARUTYUN MADATYAN |
| Sewer | 3/10/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Deputy Drilled-In Anchors | 3/17/2025 | Approved | ARUTYUN MADATYAN |
| Excavation/Setback/Form/Re-Bar | 3/17/2025 | Approved | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 3/17/2025 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2025 | Partial Approval | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 5/12/2025 | Partial Approval | ARUTYUN MADATYAN |
| PLUMBING-Rough | 5/13/2025 | Corrections Issued | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 5/16/2025 | Approved | JUAN ALVARADO |
| HVAC-Rough | 5/16/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Rough | 5/16/2025 | Approved | JUAN ALVARADO |
| BUILDING-Rough-Frame | 5/20/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 5/20/2025 | Approved | ARUTYUN MADATYAN |
| Verify Sprinkler Sign Off | 5/20/2025 | Approved | ARUTYUN MADATYAN |
| Insulation | 5/28/2025 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 6/4/2025 | Approved | ARUTYUN MADATYAN |
| Shower Pan | 6/5/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 6/10/2025 | Partial Approval | ARUTYUN MADATYAN |
| Sewer | 7/25/2025 | Not Ready for Inspection | HENRY KIM |
| Sewer | 8/6/2025 | Approved | GEVORK IPCHYAN |
| Underground Mechanical | 8/6/2025 | Approved | GEVORK IPCHYAN |
| Underground Mechanical | 8/11/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 10/2/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| Final | 10/2/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 10/2/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Final | 10/2/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 10/2/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 10/2/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| Service/Power Release | 10/2/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 10/2/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 10/7/2025 | Approved | ARUTYUN MADATYAN |
| Final | 10/7/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 10/7/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 10/7/2025 | Approved | ARUTYUN MADATYAN |
| Service/Power Release | 10/7/2025 | Approved | ARUTYUN MADATYAN |