4706 S CENTINELA AVE 90230

Certificate Information: 4706 S CENTINELA AVE 90230

Application / Permit
24010-10000-03774
Plan Check / Job No.
B24LA21579
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 7 STORY 73 UNITS (63 LI + 9 MI + 1 MGR) AFFORDABLE HOUSING APARTMENT TO INCLUDE 5 STORY TYPE IIIA APARTMENT OVER 2 STORY TYPE IA APARTMENT, USING 12.22.A.25 INCENTIVES CALOSHA PERMIT TO BE OBTAINED PRIOR TO CONSTRUCTION.
Permit Issued
Issued on 11/24/2025
Issuing Office
Metro
Current Status
Issued on 11/24/2025
Certificate of Occupancy
292653 - Pending More Information
292653 - Pending More Information

Permit Application Status History

Submitted 9/9/2024 APPLICANT
Assigned to Plan Check Engineer 9/12/2024 MANUEL MONTUFAR
Assigned to Zoning Architect 9/12/2024 RONALD GREENE
Corrections Issued 9/19/2024 MANUEL MONTUFAR
Quality Review Completed 9/23/2024 EUGENE BARBEAU
Plan Check Approved 11/18/2025 KEVIN MORALES
Issued 11/24/2025 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 1/13/2025 RIDWAN HARDY
Address approval Cleared 1/29/2025 KIMBERLY HERNANDEZ
Low Impact Development (LID) Cleared 2/5/2025 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 2/20/2025 KIMBERLY HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 2/26/2025 KIMBERLY HERNANDEZ
Highway dedication Cleared 4/24/2025 KIMBERLY HERNANDEZ
Miscellaneous Cleared 4/24/2025 KIMBERLY HERNANDEZ
Miscellaneous Cleared 4/24/2025 KIMBERLY HERNANDEZ
Miscellaneous Cleared 4/24/2025 KIMBERLY HERNANDEZ
Green Code Cleared 6/13/2025 MANUEL MONTUFAR
Trees in Parkway Cleared 6/23/2025 MIGUEL ORNELAS
Permit Cleared 7/18/2025 LIAM ODONOVAN
Hydrant and Access approval Cleared 9/5/2025 LAVEON RIDER
Specific Plan Cleared 9/5/2025 RICHARD WOO
Fire Marshal Fire Life Safety Cleared 9/24/2025 FIRE DEPARTMENT
Density Bonus Cleared 10/7/2025 KENNETH LE
Density Bonus Cleared 10/7/2025 KENNETH LE
Density Bonus Cleared 10/7/2025 KENNETH LE
SB8 RUD Cleared 10/7/2025 KENNETH LE
Tenant Habitability Plan Cleared 10/9/2025 KORNEL LELEA
Miscellaneous Cleared 10/21/2025 DANIEL CORONADO
Miscellaneous Cleared 10/21/2025 DANIEL CORONADO
Miscellaneous Cleared 10/21/2025 DANIEL CORONADO
Miscellaneous Cleared 10/21/2025 DANIEL CORONADO
Miscellaneous Cleared 10/21/2025 DANIEL CORONADO
ZI Cleared 10/21/2025 DANIEL CORONADO
Sewer availability Cleared 10/22/2025 CHRISTINE REUSCH
Zoning Plan Check Cleared 11/7/2025 Ronald Greene
DAS Clearance Cleared 11/10/2025 MANUEL MONTUFAR

Contact Information

Contractor Steiner Douglas Construction Inc; Lic. No.: 916002-B       ,

Inspector Information

VASIL MIHALEV, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/11/2025 Conditional Approval VASIL MIHALEV
Excavation/Setback/Form/Re-Bar 12/15/2025 Partial Approval VASIL MIHALEV
Pre-Inspection 12/15/2025 Approved VASIL MIHALEV
Footing/Foundation/Slab 12/29/2025 Approved VASIL MIHALEV
Green Building Rough 12/30/2025 Not Ready for Inspection VASIL MIHALEV
Reinforced Concrete Frame 12/30/2025 Not Ready for Inspection VASIL MIHALEV
Verify Sprinkler Sign Off 12/30/2025 Not Ready for Inspection VASIL MIHALEV
Green Building Rough 1/13/2026 Not Ready for Inspection VASIL MIHALEV
Reinforced Concrete Frame 1/13/2026 Partial Inspection VASIL MIHALEV
Verify Sprinkler Sign Off 1/13/2026 Not Ready for Inspection VASIL MIHALEV
Structural Steel Frame 1/14/2026 Not Ready for Inspection VASIL MIHALEV
Green Building Rough 2/11/2026 Not Ready for Inspection VASIL MIHALEV
Reinforced Concrete Frame 2/11/2026 Partial Approval VASIL MIHALEV
Verify Sprinkler Sign Off 2/11/2026 Not Ready for Inspection VASIL MIHALEV
Green Building Rough 2/27/2026 Not Ready for Inspection DERRICK SPENCER
Reinforced Concrete Frame 2/27/2026 Partial Approval DERRICK SPENCER
Verify Sprinkler Sign Off 2/27/2026 Approved DERRICK SPENCER
Wood Frame 2/27/2026 Partial Approval DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 3/20/2026 Partial Approval DERRICK SPENCER
Wood Frame 4/8/2026 Partial Approval DERRICK SPENCER
Deputy Wood Construction 4/17/2026 Approved DERRICK SPENCER
Wood Frame 4/17/2026 Partial Approval DERRICK SPENCER
Wood Frame 4/22/2026 Partial Approval DERRICK SPENCER
Wood Frame 5/5/2026 Partial Approval DERRICK SPENCER
Wood Frame 5/15/2026 Partial Approval FARHAD DADBIN
Light Gage Steel Frame 6/1/2026 Partial Approval DERRICK SPENCER
Wood Frame 6/1/2026 Partial Approval DERRICK SPENCER
Deputy Wood Construction 6/2/2026 Approved DERRICK SPENCER