758 W 113TH ST 90044
Certificate Information: 758 W 113TH ST 90044
- Application / Permit
- 24010-10000-03680
- Plan Check / Job No.
- B24LA20765
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: New detached ADU per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g). Design per licensed engineer.
- Permit Issued
- Issued on 10/2/2024
- Issuing Office
- Current Status
- CofO Issued on 5/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/6/2024 | CAROLEAN BASMA |
| Corrections Issued | 9/7/2024 | CAROLEAN BASMA |
| Applicant returned to address corrections | 9/27/2024 | CAROLEAN BASMA |
| Plan Check Approved | 10/2/2024 | CAROLEAN BASMA |
| Issued | 10/2/2024 | APPLICANT |
| CofO in Progress | 5/20/2025 | ANSON MAGLASANG |
| Permit Finaled | 5/20/2025 | ANSON MAGLASANG |
| CofO Issued | 5/20/2025 | ANSON MAGLASANG |
| Permit Finaled | 5/20/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 9/22/2024 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 9/22/2024 | ADRIAN SANCHEZ |
| Construction near power lines | Cleared | 9/24/2024 | ENRIQUE ACOSTA |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2024 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 9/25/2024 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Ha My Design, Inc; Lic. No.: 999603-B | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/9/2024 | Corrections Issued | BEN MOLSTAD |
| Underground Mechanical | 10/9/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Footing/Foundation/Slab | 10/11/2024 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 10/17/2024 | Corrections Issued | BEN MOLSTAD |
| Excavation/Setback/Form/Re-Bar | 10/18/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Footing/Foundation/Slab | 10/21/2024 | Corrections Issued | BEN MOLSTAD |
| Excavation/Setback/Form/Re-Bar | 10/23/2024 | Approved | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2024 | Partial Approval | BEN MOLSTAD |
| Wood Frame | 11/4/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 11/8/2024 | Corrections Issued | BEN MOLSTAD |
| HVAC-Rough | 11/8/2024 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 11/8/2024 | Corrections Issued | BEN MOLSTAD |
| Wood Frame | 11/8/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 11/12/2024 | Corrections Issued | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2024 | Partial Inspection | BEN MOLSTAD |
| HVAC-Rough | 11/12/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 11/12/2024 | Approved | BEN MOLSTAD |
| Wood Frame | 11/12/2024 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 12/23/2024 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 12/23/2024 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 12/23/2024 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 12/23/2024 | Partial Approval | JOSEPH MCGARRY |
| MERV13>=Rough | 12/23/2024 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 12/23/2024 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 1/8/2025 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 1/8/2025 | Corrections Issued | BEN MOLSTAD |
| BUILDING-Rough-Frame | 1/13/2025 | Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 1/13/2025 | Approved | BEN MOLSTAD |
| Insulation | 1/13/2025 | Approved | BEN MOLSTAD |
| Wood Frame | 1/13/2025 | Approved | BEN MOLSTAD |
| Drywall Nailing | 1/21/2025 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 1/21/2025 | Approved | BEN MOLSTAD |
| Shower Pan | 1/21/2025 | Approved | BEN MOLSTAD |
| Sewer | 4/8/2025 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 4/8/2025 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Final | 4/23/2025 | Corrections Issued | BEN MOLSTAD |
| Final | 4/23/2025 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 4/23/2025 | Approved | BEN MOLSTAD |
| Green Building Final | 4/23/2025 | Not Ready for Inspection | BEN MOLSTAD |
| MERV13>=Final | 4/23/2025 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 4/23/2025 | SGSOV Not Ready | BEN MOLSTAD |
| Service/Power Release | 4/23/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Smoke Detectors | 4/23/2025 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 5/1/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 5/1/2025 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 5/1/2025 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Final | 5/1/2025 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Final | 5/1/2025 | Corrections Issued | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 5/1/2025 | SGSOV Not Ready | BEN MOLSTAD |
| Service/Power Release | 5/1/2025 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 5/2/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 5/2/2025 | Corrections Issued | BEN MOLSTAD |
| HVAC-Final | 5/2/2025 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 5/2/2025 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 5/15/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 5/15/2025 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 5/15/2025 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Final | 5/15/2025 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Final | 5/15/2025 | Not Ready for Inspection | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 5/15/2025 | SGSOV Not Ready | BEN MOLSTAD |
| Service/Power Release | 5/15/2025 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 5/20/2025 | Approved | ANSON MAGLASANG |
| Final | 5/20/2025 | OK to Issue CofO | ANSON MAGLASANG |
| Green Building Final | 5/20/2025 | Approved | ANSON MAGLASANG |
| HVAC-Final | 5/20/2025 | Approved | ANSON MAGLASANG |
| PLUMBING-Final | 5/20/2025 | Approved | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 5/20/2025 | SGSOV Approved | ANSON MAGLASANG |
| Service/Power Release | 5/20/2025 | Approved | ANSON MAGLASANG |