758 W 113TH ST 90044

Certificate Information: 758 W 113TH ST 90044

Application / Permit
24010-10000-03680
Plan Check / Job No.
B24LA20765
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: New detached ADU per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g). Design per licensed engineer.
Permit Issued
Issued on 10/2/2024
Issuing Office
Current Status
CofO Issued on 5/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/3/2024 APPLICANT
Assigned to Plan Check Engineer 9/6/2024 CAROLEAN BASMA
Corrections Issued 9/7/2024 CAROLEAN BASMA
Applicant returned to address corrections 9/27/2024 CAROLEAN BASMA
Plan Check Approved 10/2/2024 CAROLEAN BASMA
Issued 10/2/2024 APPLICANT
CofO in Progress 5/20/2025 ANSON MAGLASANG
Permit Finaled 5/20/2025 ANSON MAGLASANG
CofO Issued 5/20/2025 ANSON MAGLASANG
Permit Finaled 5/20/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 9/22/2024 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 9/22/2024 ADRIAN SANCHEZ
Construction near power lines Cleared 9/24/2024 ENRIQUE ACOSTA
Eng Process Fee Ord 176,300 Cleared 9/25/2024 ADRIAN SANCHEZ
Sewer availability Cleared 9/25/2024 ADRIAN SANCHEZ

Contact Information

Contractor Ha My Design, Inc; Lic. No.: 999603-B       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/9/2024 Corrections Issued BEN MOLSTAD
Underground Mechanical 10/9/2024 Not Ready for Inspection BEN MOLSTAD
Footing/Foundation/Slab 10/11/2024 Corrections Issued BEN MOLSTAD
Footing/Foundation/Slab 10/17/2024 Corrections Issued BEN MOLSTAD
Excavation/Setback/Form/Re-Bar 10/18/2024 Not Ready for Inspection BEN MOLSTAD
Footing/Foundation/Slab 10/21/2024 Corrections Issued BEN MOLSTAD
Excavation/Setback/Form/Re-Bar 10/23/2024 Approved BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 11/4/2024 Partial Approval BEN MOLSTAD
Wood Frame 11/4/2024 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 11/8/2024 Corrections Issued BEN MOLSTAD
HVAC-Rough 11/8/2024 Corrections Issued BEN MOLSTAD
PLUMBING-Rough 11/8/2024 Corrections Issued BEN MOLSTAD
Wood Frame 11/8/2024 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 11/12/2024 Corrections Issued BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 11/12/2024 Partial Inspection BEN MOLSTAD
HVAC-Rough 11/12/2024 Approved BEN MOLSTAD
PLUMBING-Rough 11/12/2024 Approved BEN MOLSTAD
Wood Frame 11/12/2024 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 12/23/2024 Corrections Issued JOSEPH MCGARRY
ELECTRICAL-Rough 12/23/2024 Partial Approval JOSEPH MCGARRY
Green Building Rough 12/23/2024 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 12/23/2024 Partial Approval JOSEPH MCGARRY
MERV13>=Rough 12/23/2024 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 12/23/2024 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 1/8/2025 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 1/8/2025 Corrections Issued BEN MOLSTAD
BUILDING-Rough-Frame 1/13/2025 Approved BEN MOLSTAD
ELECTRICAL-Rough 1/13/2025 Approved BEN MOLSTAD
Insulation 1/13/2025 Approved BEN MOLSTAD
Wood Frame 1/13/2025 Approved BEN MOLSTAD
Drywall Nailing 1/21/2025 Approved BEN MOLSTAD
Interior/Exterior Lathing 1/21/2025 Approved BEN MOLSTAD
Shower Pan 1/21/2025 Approved BEN MOLSTAD
Sewer 4/8/2025 Approved JOSEPH MCGARRY
Underground Mechanical 4/8/2025 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Final 4/23/2025 Corrections Issued BEN MOLSTAD
Final 4/23/2025 Corrections Issued BEN MOLSTAD
Footing/Foundation/Slab 4/23/2025 Approved BEN MOLSTAD
Green Building Final 4/23/2025 Not Ready for Inspection BEN MOLSTAD
MERV13>=Final 4/23/2025 Approved BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 4/23/2025 SGSOV Not Ready BEN MOLSTAD
Service/Power Release 4/23/2025 Not Ready for Inspection BEN MOLSTAD
Smoke Detectors 4/23/2025 Approved BEN MOLSTAD
ELECTRICAL-Final 5/1/2025 Not Ready for Inspection BEN MOLSTAD
Final 5/1/2025 Corrections Issued BEN MOLSTAD
Green Building Final 5/1/2025 Not Ready for Inspection BEN MOLSTAD
HVAC-Final 5/1/2025 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Final 5/1/2025 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 5/1/2025 SGSOV Not Ready BEN MOLSTAD
Service/Power Release 5/1/2025 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Final 5/2/2025 Not Ready for Inspection BEN MOLSTAD
Final 5/2/2025 Corrections Issued BEN MOLSTAD
HVAC-Final 5/2/2025 Approved BEN MOLSTAD
PLUMBING-Final 5/2/2025 Approved BEN MOLSTAD
ELECTRICAL-Final 5/15/2025 Not Ready for Inspection BEN MOLSTAD
Final 5/15/2025 Corrections Issued BEN MOLSTAD
Green Building Final 5/15/2025 Not Ready for Inspection BEN MOLSTAD
HVAC-Final 5/15/2025 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Final 5/15/2025 Not Ready for Inspection BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 5/15/2025 SGSOV Not Ready BEN MOLSTAD
Service/Power Release 5/15/2025 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Final 5/20/2025 Approved ANSON MAGLASANG
Final 5/20/2025 OK to Issue CofO ANSON MAGLASANG
Green Building Final 5/20/2025 Approved ANSON MAGLASANG
HVAC-Final 5/20/2025 Approved ANSON MAGLASANG
PLUMBING-Final 5/20/2025 Approved ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 5/20/2025 SGSOV Approved ANSON MAGLASANG
Service/Power Release 5/20/2025 Approved ANSON MAGLASANG