1737 W 81ST ST 90047

Certificate Information: 1737 W 81ST ST 90047

Application / Permit
24010-10000-03677
Plan Check / Job No.
B24LA20734
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED NEW ONE STORY ADU (439 SF) AT REAR OF LOT PER STATE LAW.
Permit Issued
Issued on 10/18/2024
Issuing Office
Metro
Current Status
CofO Issued on 4/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/30/2024 APPLICANT
Assigned to Plan Check Engineer 9/4/2024 LUKE GONZALES
Corrections Issued 9/6/2024 LUKE GONZALES
Building Plans Picked Up 9/12/2024 APPLICANT
Plan Check Approved 10/18/2024 DANIEL SMILEY
Issued 10/18/2024 APPLICANT
CofO in Progress 4/10/2025 WAYNE REGESTER
Permit Finaled 4/13/2025 DEROLD HAUFF
CofO Issued 4/13/2025 DEROLD HAUFF
Permit Finaled 4/13/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/23/2024 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 9/23/2024 JESSICA OPINION
Sewer availability Cleared 9/23/2024 JESSICA OPINION
Roof/Waste drainage to street Cleared 9/28/2024 JESSICA OPINION

Contact Information

Contractor Napoles Builders Inc; Lic. No.: 1013480-B 294 EAST 47TH PLACE      LOS ANGELES, CA 90011
Engineer Tzeng,, Charles Chau-Jyi; Lic. No.: C34005 PO BOX 5044      PASADENA, CA 91117

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/8/2024 Not Ready for Inspection AMIR NAZARIAN
Underground Mechanical 11/8/2024 Not Ready for Inspection AMIR NAZARIAN
Excavation/Setback/Form/Re-Bar 11/14/2024 Approved JOHN QUINTANILLA
Footing/Foundation/Slab 11/14/2024 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 12/6/2024 Not Ready for Inspection LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 12/6/2024 Approved LUIS CASTRO
Green Building Rough 12/6/2024 Approved LUIS CASTRO
HVAC-Rough 12/6/2024 Not Ready for Inspection LUIS CASTRO
PLUMBING-Rough 12/6/2024 Not Ready for Inspection LUIS CASTRO
Verify Sprinkler Sign Off 12/6/2024 Approved LUIS CASTRO
BUILDING-Rough-Frame 12/16/2024 Corrections Issued AMIR NAZARIAN
ELECTRICAL-Rough 12/16/2024 Corrections Issued AMIR NAZARIAN
HVAC-Rough 12/16/2024 Corrections Issued AMIR NAZARIAN
PLUMBING-Rough 12/16/2024 Approved AMIR NAZARIAN
BUILDING-Rough-Frame 12/26/2024 Partial Approval AMIR NAZARIAN
ELECTRICAL-Rough 12/26/2024 Conditional Approval AMIR NAZARIAN
HVAC-Rough 12/26/2024 Approved AMIR NAZARIAN
Interior/Exterior Lathing 12/27/2024 Conditional Approval AMIR NAZARIAN
Insulation 1/2/2025 Conditional Approval AMIR NAZARIAN
Drywall Nailing 1/6/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Rough 1/29/2025 Approved JOSE MACIAS
PLUMBING-Rough 2/20/2025 Corrections Issued NICHOLAS LOPEZ
Sewer 2/20/2025 Approved NICHOLAS LOPEZ
Underground Mechanical 2/24/2025 Not Ready for Inspection LUIS CASTRO
PLUMBING-Rough 2/25/2025 Partial Inspection MICHAEL LEWIS
Underground Mechanical 2/27/2025 Approved JOSE MACIAS
BUILDING-Rough-Frame 3/21/2025 Not Ready for Inspection JOSE MACIAS
Final 3/21/2025 Corrections Issued BARRY HACHE
Green Building Final 3/21/2025 Approved BARRY HACHE
SGSOV-Seismic Gas S/O Valve 3/21/2025 SGSOV Not Required BARRY HACHE
Service/Power Release 3/21/2025 Not Ready for Inspection BARRY HACHE
Smoke Detectors 3/21/2025 Approved BARRY HACHE
BUILDING-Rough-Frame 3/28/2025 Approved BARRY HACHE
Final 3/28/2025 Not Ready for Inspection BARRY HACHE
Service/Power Release 3/28/2025 Not Ready for Inspection BARRY HACHE
Final 4/2/2025 Not Ready for Inspection WAYNE REGESTER
Service/Power Release 4/2/2025 Partial Inspection WAYNE REGESTER
Final 4/8/2025 OK to Issue CofO WAYNE REGESTER
Service/Power Release 4/8/2025 Approved WAYNE REGESTER