9863 S SEPULVEDA BLVD 90045

Certificate Information: 9863 S SEPULVEDA BLVD 90045

Application / Permit
24010-10000-03597
Plan Check / Job No.
B24LA19965
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
**ePlan**LAX** LAWA ATMP Roadway Project - New Pedestrian Bridge
Permit Issued
Issued on 3/17/2026
Issuing Office
South Los Angeles
Current Status
Issued on 3/17/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/28/2024 APPLICANT
Assigned to Plan Check Engineer 8/28/2024 FARSHAD ALIMOHAMADI
Corrections Issued 9/4/2024 FARSHAD ALIMOHAMADI
Quality Review Completed 9/4/2024 LIPING TENG
Applicant returned to address corrections 3/4/2025 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 5/28/2025 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 6/2/2025 FARSHAD ALIMOHAMADI
Plan Check Approved 3/9/2026 FARSHAD ALIMOHAMADI
No Progress 3/9/2026 FARSHAD ALIMOHAMADI
Plan Check Approved 3/9/2026 FARSHAD ALIMOHAMADI
Issued 3/17/2026 APPLICANT

Permit Application Clearance Information

ZA Case Cleared 10/8/2024 DALIA MOKAYED
ZA Case Cleared 10/8/2024 DALIA MOKAYED
Miscellaneous Cleared 2/13/2025 NATHAN ROMINE
ZA Case Cleared 2/13/2025 NATHAN ROMINE
ZA Case Cleared 2/13/2025 NATHAN ROMINE
Address approval Cleared 3/13/2025 MAHELET GEBEYHU
Project Permit Cleared 3/24/2025 CHRISTOPHER MARTINEZ
Specific Plan Cleared 4/1/2025 RICHARD WOO
Eng Process Fee Ord 176,300 Cleared 4/8/2025 MAHELET GEBEYHU
Highway dedication Cleared 5/9/2025 MAHELET GEBEYHU
City owned building/parcel Cleared 10/8/2025 MASON NG
DAS Clearance Cleared 10/29/2025 FARSHAD ALIMOHAMADI
Encroachment in public way Cleared 12/12/2025 MAHELET GEBEYHU
Miscellaneous Cleared 12/18/2025 SAMUEL AHN
Green Code Cleared 2/17/2026 FARSHAD ALIMOHAMADI
Hydrant and Access approval Cleared 2/24/2026 JOHN CONNEALLY
Low Impact Development (LID) Cleared 2/24/2026 AMMAR ELTAWIL
"Q" conditions Cleared 2/26/2026 DANIEL CORONADO
Community Plan Implem. Overlay Cleared 2/26/2026 DANIEL CORONADO
Miscellaneous Cleared 2/26/2026 DANIEL CORONADO
Building over 36-ft Cleared 3/2/2026 CALOSHA APPROVED
Roof/Waste drainage to street Cleared 3/3/2026 MAHELET GEBEYHU
Work Adjacent to Public Way Cleared 3/3/2026 SAMUEL AHN

Contact Information

Architect Murdoch,, Paul Allan; Lic. No.: C19061 1250 S. LUCERNE BLVD      LOS ANGELES, CA 90019
Contractor Skanska Usa Civil West California District Inc; Lic. No.: 140069-A 1995 AGUA MANSA RD      RIVERSIDE, CA 92509
Engineer Morton,, Jesse Edward; Lic. No.: C86535 210 S BERKELEY AVE      PASADENA, CA 91107
Engineer Ortiz,, Oscar Fermin; Lic. No.: S7057 4513 IROQUOIS AVE      LAKEWOOD, CA 90713

Inspector Information

NICK LAROCCA, (213) 473-2153 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 3/27/2026 Partial Inspection NICK LAROCCA
Piling/Pier/Caisson 3/28/2026 Off-Hour Fees Due
Piling/Pier/Caisson 3/30/2026 Partial Approval NICK LAROCCA
Piling/Pier/Caisson 4/6/2026 Partial Approval NICK LAROCCA
Pre-Inspection 4/13/2026 Approved NICK LAROCCA
Piling/Pier/Caisson 4/15/2026 Partial Approval NICK LAROCCA
Piling/Pier/Caisson 4/16/2026 Partial Approval NICK LAROCCA
Piling/Pier/Caisson 4/17/2026 Partial Approval NICK LAROCCA
Footing/Foundation/Slab 4/21/2026 Off-Hour Fees Due
Piling/Pier/Caisson 4/21/2026 Partial Approval NICK LAROCCA
Piling/Pier/Caisson 4/22/2026 Partial Approval NICK LAROCCA
Piling/Pier/Caisson 4/28/2026 Partial Inspection NICK LAROCCA
Piling/Pier/Caisson 4/29/2026 Partial Inspection NICK LAROCCA
Piling/Pier/Caisson 5/1/2026 Approved VASIL MIHALEV
Piling/Pier/Caisson 5/1/2026 Off-Hour Fees Due
Piling/Pier/Caisson 5/15/2026 Partial Approval NICK LAROCCA
Pre-Inspection 5/18/2026 Approved NICK LAROCCA
Piling/Pier/Caisson 5/19/2026 Partial Approval NICK LAROCCA
Piling/Pier/Caisson 5/21/2026 Partial Approval NICK LAROCCA
Piling/Pier/Caisson 5/26/2026 Partial Approval NICK LAROCCA
Piling/Pier/Caisson 5/28/2026 Pending Review
Piling/Pier/Caisson 6/1/2026 Pending Review
Piling/Pier/Caisson 6/2/2026 Pending Review
Piling/Pier/Caisson 6/3/2026 Pending Review
Piling/Pier/Caisson 6/4/2026 Pending Review
Piling/Pier/Caisson 6/5/2026 Pending Review
Piling/Pier/Caisson 6/8/2026 Pending Review
Pre-Inspection 6/8/2026 Approved NICK LAROCCA
Excavation/Setback/Form/Re-Bar 6/9/2026 Partial Inspection NICK LAROCCA
Piling/Pier/Caisson 6/9/2026 Pending Review
Piling/Pier/Caisson 6/10/2026 Partial Inspection NICK LAROCCA
Piling/Pier/Caisson 6/10/2026 Pending Review
Piling/Pier/Caisson 6/11/2026 Not Ready for Inspection NICK LAROCCA
Pre-Inspection 6/11/2026 Pending Review
Piling/Pier/Caisson 6/13/2026 Pending Review
Piling/Pier/Caisson 6/15/2026 Pending Review
Piling/Pier/Caisson 6/24/2026 Partial Inspection NICK LAROCCA
Piling/Pier/Caisson 6/26/2026 Partial Approval NICK LAROCCA
Excavation/Setback/Form/Re-Bar 7/1/2026 Not Ready for Inspection NICK LAROCCA
Reinforced Concrete Frame 7/8/2026 Not Ready for Inspection DAVID TSAU
Piling/Pier/Caisson 7/9/2026 Partial Approval DAVID TSAU
Reinforced Concrete Frame 7/9/2026 Partial Approval DAVID TSAU
Footing/Foundation/Slab 7/14/2026 Partial Approval NICK LAROCCA
Excavation/Setback/Form/Re-Bar 7/16/2026 Partial Inspection NICK LAROCCA
Reinforced Concrete Frame 7/21/2026 Partial Inspection NICK LAROCCA
Pre-Inspection 7/22/2026 Approved NICK LAROCCA