5518 N BUSHNELL WAY 90042

Certificate Information: 5518 N BUSHNELL WAY 90042

Application / Permit
24010-10000-03591
Plan Check / Job No.
B24LA19848
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. New Detached Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 4/17/2025
Issuing Office
Current Status
CofO Issued on 11/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/27/2024 APPLICANT
Assigned to Plan Check Engineer 8/30/2024 AMY GUEVARRA
Corrections Issued 9/5/2024 AMY GUEVARRA
Applicant returned to address corrections 2/20/2025 AMY GUEVARRA
Applicant returned to address corrections 3/24/2025 AMY GUEVARRA
Plan Check Approved 4/4/2025 REZA HAGHIGHAT
Issued 4/17/2025 APPLICANT
CofO in Progress 11/20/2025 LILIANA PORTILLO
Permit Finaled 11/21/2025 DEROLD HAUFF
CofO Issued 11/21/2025 DEROLD HAUFF
Permit Finaled 11/21/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/26/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 10/2/2024 WALLIE JONG
Sewer availability Cleared 10/2/2024 WALLIE JONG
Address approval Cleared 10/30/2024 TREVOR QUAN
Grading Pre-Inspection Cleared 2/27/2025 AMY GUEVARRA

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Hong Kook; Lic. No.: NA64529       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/7/2025 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 5/19/2025 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 5/19/2025 Approved LILIANA PORTILLO
PLUMBING-Rough 5/19/2025 Partial Approval LILIANA PORTILLO
Insulation 5/20/2025 Partial Approval REGINA MENDEZ
Floor/Roof Diaphrgm/Shear Wall 5/29/2025 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 6/3/2025 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 6/5/2025 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Rough 6/5/2025 Approved ALIZAH MAYAGOITIA
Green Building Rough 6/5/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Rough 6/5/2025 Approved ALIZAH MAYAGOITIA
MERV13>=Rough 6/5/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 6/5/2025 Approved ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 6/5/2025 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 6/10/2025 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 6/12/2025 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 6/12/2025 Approved LILIANA PORTILLO
Insulation 6/16/2025 Approved LILIANA PORTILLO
Interior/Exterior Lathing 6/16/2025 Partial Approval LILIANA PORTILLO
Drywall Nailing 6/18/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 6/18/2025 Approved REGINA MENDEZ
Shower Pan 6/18/2025 Approved REGINA MENDEZ
Sewer 7/1/2025 Partial Approval LILIANA PORTILLO
Sewer 7/3/2025 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 7/24/2025 Approved BRENDAN MORELLI
Footing/Foundation/Slab 7/24/2025 Approved BRENDAN MORELLI
Green Building Rough 7/24/2025 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 7/24/2025 SGSOV Not Ready BRENDAN MORELLI
Final 7/29/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 7/29/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Final 7/29/2025 Approved ALIZAH MAYAGOITIA
MERV13>=Final 7/29/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 7/29/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 7/29/2025 SGSOV Approved ALIZAH MAYAGOITIA
Service/Power Release 7/29/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 7/29/2025 Approved ALIZAH MAYAGOITIA
Final 8/5/2025 Corrections Issued LILIANA PORTILLO
Green Building Final 8/5/2025 Not Ready for Inspection LILIANA PORTILLO
Service/Power Release 8/5/2025 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 8/26/2025 Not Ready for Inspection LILIANA PORTILLO
Final 8/26/2025 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 8/26/2025 Approved LILIANA PORTILLO
Service/Power Release 8/26/2025 Approved LILIANA PORTILLO
ELECTRICAL-Final 11/19/2025 Approved LILIANA PORTILLO
Final 11/19/2025 OK to Issue CofO LILIANA PORTILLO