5518 N BUSHNELL WAY 90042
Certificate Information: 5518 N BUSHNELL WAY 90042
- Application / Permit
- 24010-10000-03591
- Plan Check / Job No.
- B24LA19848
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. New Detached Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 4/17/2025
- Issuing Office
- Current Status
- CofO Issued on 11/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2024 | AMY GUEVARRA |
| Corrections Issued | 9/5/2024 | AMY GUEVARRA |
| Applicant returned to address corrections | 2/20/2025 | AMY GUEVARRA |
| Applicant returned to address corrections | 3/24/2025 | AMY GUEVARRA |
| Plan Check Approved | 4/4/2025 | REZA HAGHIGHAT |
| Issued | 4/17/2025 | APPLICANT |
| CofO in Progress | 11/20/2025 | LILIANA PORTILLO |
| Permit Finaled | 11/21/2025 | DEROLD HAUFF |
| CofO Issued | 11/21/2025 | DEROLD HAUFF |
| Permit Finaled | 11/21/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/26/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/2/2024 | WALLIE JONG |
| Sewer availability | Cleared | 10/2/2024 | WALLIE JONG |
| Address approval | Cleared | 10/30/2024 | TREVOR QUAN |
| Grading Pre-Inspection | Cleared | 2/27/2025 | AMY GUEVARRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Hong Kook; Lic. No.: NA64529 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/7/2025 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 5/19/2025 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 5/19/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 5/19/2025 | Partial Approval | LILIANA PORTILLO |
| Insulation | 5/20/2025 | Partial Approval | REGINA MENDEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2025 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 6/3/2025 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 6/5/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 6/5/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 6/5/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 6/5/2025 | Approved | ALIZAH MAYAGOITIA |
| MERV13>=Rough | 6/5/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 6/5/2025 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 6/5/2025 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2025 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 6/12/2025 | Conditional Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2025 | Approved | LILIANA PORTILLO |
| Insulation | 6/16/2025 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 6/16/2025 | Partial Approval | LILIANA PORTILLO |
| Drywall Nailing | 6/18/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 6/18/2025 | Approved | REGINA MENDEZ |
| Shower Pan | 6/18/2025 | Approved | REGINA MENDEZ |
| Sewer | 7/1/2025 | Partial Approval | LILIANA PORTILLO |
| Sewer | 7/3/2025 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 7/24/2025 | Approved | BRENDAN MORELLI |
| Footing/Foundation/Slab | 7/24/2025 | Approved | BRENDAN MORELLI |
| Green Building Rough | 7/24/2025 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 7/24/2025 | SGSOV Not Ready | BRENDAN MORELLI |
| Final | 7/29/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 7/29/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 7/29/2025 | Approved | ALIZAH MAYAGOITIA |
| MERV13>=Final | 7/29/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 7/29/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 7/29/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 7/29/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 7/29/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 8/5/2025 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 8/5/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Service/Power Release | 8/5/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 8/26/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 8/26/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 8/26/2025 | Approved | LILIANA PORTILLO |
| Service/Power Release | 8/26/2025 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 11/19/2025 | Approved | LILIANA PORTILLO |
| Final | 11/19/2025 | OK to Issue CofO | LILIANA PORTILLO |