1427 N BENTON WAY 90026

Certificate Information: 1427 N BENTON WAY 90026

Application / Permit
24010-10000-03569
Plan Check / Job No.
B24LA19610
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*Eplan.* New detached 2-story ADU w/ rooftop deck per LAMC 12.22 A.33 (c) and (d).
Permit Issued
Issued on 6/19/2025
Issuing Office
Current Status
Issued on 6/19/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/23/2024 APPLICANT
Assigned to Plan Check Engineer 9/5/2024 HUAN LE
Corrections Issued 9/14/2024 MICHAEL LOPEZ
Quality Review Completed 9/18/2024 PRANITA SHAH
Applicant returned to address corrections 11/7/2024 MICHAEL LOPEZ
Applicant returned to address corrections 4/10/2025 HUAN LE
Plan Check Approved 5/6/2025 HUAN LE
Issued 6/19/2025 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 12/18/2024 JERRY KAO
Address approval Cleared 12/26/2024 DAVID LOPEZ
BHO/Hillside ordinance Cleared 2/4/2025 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 2/6/2025 WALLIE JONG
Roof/Waste drainage to street Cleared 3/13/2025 DAVID LOPEZ
Sewer availability Cleared 3/13/2025 DAVID LOPEZ
GPI Written Notices Cleared 4/11/2025 MICHAEL LOPEZ
Grading Pre-Inspection Cleared 4/11/2025 MICHAEL LOPEZ

Contact Information

Contractor 126 Builders Inc; Lic. No.: 1086031-B       ,
Engineer Rhee,, Kyle; Lic. No.: NA78215       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/31/2025 Corrections Issued HAMIK HARTOUNIAN
Pre-Inspection 7/31/2025 Partial Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 8/27/2025 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 9/10/2025 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 9/18/2025 Corrections Issued HAMIK HARTOUNIAN
Deputy Wood Construction 9/19/2025 Conditional Approval HAMIK HARTOUNIAN
Deputy Wood Construction 10/6/2025 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/6/2025 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/17/2025 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 10/17/2025 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/17/2025 Approved HAMIK HARTOUNIAN
Green Building Rough 10/17/2025 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 10/17/2025 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 10/17/2025 Approved HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 10/17/2025 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 11/18/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 11/18/2025 Approved HAMIK HARTOUNIAN
HVAC-Rough 11/18/2025 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 11/18/2025 Partial Approval HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 11/18/2025 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/1/2025 Corrections Issued HAMIK HARTOUNIAN
Insulation 12/1/2025 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/3/2025 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 12/3/2025 Approved HAMIK HARTOUNIAN
Drywall Nailing 12/8/2025 Partial Approval GEM DE OCAMPO
Pre-Inspection 1/6/2026 Partial Inspection HAMIK HARTOUNIAN
Sewer 1/15/2026 Not Ready for Inspection HAMIK HARTOUNIAN
Shower Pan 1/15/2026 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 3/6/2026 Partial Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 5/13/2026 Partial Approval FREDDIE RIVERA
Sewer 5/13/2026 Approved FREDDIE RIVERA