10020 S BROADWAY UNIT C-D 90003

Certificate Information: 10020 S BROADWAY UNIT C-D 90003

Application / Permit
24010-10000-03566
Plan Check / Job No.
B24LA19547
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 2-STORY DUPLEX @ REAR OF LOT. UNIT A: 1534SQFT UNIT B: 1534SQFT **13D FIRE SPRINKLER REQUIRED** 2 OF 2
Permit Issued
Issued on 4/22/2025
Issuing Office
Current Status
CofO Issued on 5/29/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/23/2024 APPLICANT
Assigned to Plan Check Engineer 8/29/2024 KHUONG TRUONG
Corrections Issued 9/3/2024 KHUONG TRUONG
Quality Review Completed 9/10/2024 KEN GILL
Applicant returned to address corrections 3/24/2025 KHUONG TRUONG
Plan Check Approved 4/3/2025 KHUONG TRUONG
Issued 4/22/2025 APPLICANT
Permit Closed-Status Void 10/7/2025 ANTHONY EGSON
Re-Activate Permit 10/8/2025 ANTHONY EGSON
CofO in Progress 5/28/2026 ARTHUR NEGRETE
Permit Finaled 5/29/2026 ANSON MAGLASANG
CofO Issued 5/29/2026 ANSON MAGLASANG
Permit Finaled 5/29/2026 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 9/10/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 9/11/2024 WALLIE JONG
Hydrant and Access approval Cleared 11/26/2024 KURT CORRAL
Historic Resource Verification Cleared 2/18/2025 RAFAEL FONTES
Community Plan Implem. Overlay Cleared 2/28/2025 ANACANY HURTADO
ZI Cleared 3/6/2025 DALIA MOKAYED
Redevelopment Project Area Cleared 3/11/2025 YASMINE BASHIRI
Low Impact Development (LID) Cleared 3/13/2025 ERNEST TSE
Construction near power lines Cleared 3/20/2025 OSCAR CASTRO
Roof/Waste drainage to street Cleared 3/28/2025 CINDY QI
Highway dedication Cleared 3/29/2025 ERIK BEASLEY
Sewer availability Cleared 4/2/2025 WALLIE JONG

Contact Information

Contractor Pacific Coast Builders; Lic. No.: 834794-B 9277OTTO ST      DOWNEY, CA 90240
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/25/2025 Approved ANTHONY EGSON
Underground Mechanical 4/25/2025 Partial Approval ANTHONY EGSON
Footing/Foundation/Slab 5/1/2025 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 5/2/2025 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 5/13/2025 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 8/22/2025 Approved ANTHONY EGSON
ELECTRICAL-Rough 9/29/2025 Approved ANTHONY EGSON
PLUMBING-Rough 9/29/2025 Approved ANTHONY EGSON
BUILDING-Rough-Frame 9/30/2025 Not Ready for Inspection BEN MOLSTAD
Green Building Rough 9/30/2025 Not Ready for Inspection BEN MOLSTAD
HVAC-Rough 9/30/2025 Corrections Issued BEN MOLSTAD
MERV13>=Rough 9/30/2025 Approved BEN MOLSTAD
Verify Sprinkler Sign Off 9/30/2025 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 10/2/2025 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 10/2/2025 Approved ANTHONY EGSON
HVAC-Rough 10/2/2025 Partial Approval ANTHONY EGSON
Interior/Exterior Lathing 10/2/2025 Approved ANTHONY EGSON
Verify Sprinkler Sign Off 10/2/2025 Approved ANTHONY EGSON
BUILDING-Rough-Frame 10/7/2025 Approved ANTHONY EGSON
BUILDING-Rough-Frame 10/7/2025 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 10/7/2025 Partial Approval ANTHONY EGSON
Insulation 10/14/2025 Approved BEN MOLSTAD
Drywall Nailing 10/23/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 10/23/2025 Approved ANTHONY EGSON
Sewer 1/29/2026 Approved ARTHUR NEGRETE
Underground Mechanical 1/29/2026 Approved ARTHUR NEGRETE
Underground Mechanical 2/23/2026 Partial Approval BEN MOLSTAD
ELECTRICAL-Final 5/26/2026 Approved ARTHUR NEGRETE
HVAC-Final 5/26/2026 Approved ARTHUR NEGRETE
Smoke Detectors 5/26/2026 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 5/27/2026 Approved ARTHUR NEGRETE
Final 5/27/2026 OK to Issue CofO ARTHUR NEGRETE
Green Building Final 5/27/2026 Approved ARTHUR NEGRETE
MERV13>=Final 5/27/2026 Approved ARTHUR NEGRETE
PLUMBING-Final 5/27/2026 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 5/27/2026 SGSOV Not Required ARTHUR NEGRETE
Service/Power Release 5/27/2026 Approved ARTHUR NEGRETE