10022 S BROADWAY UNIT A-B 90003
Certificate Information: 10022 S BROADWAY UNIT A-B 90003
- Application / Permit
- 24010-10000-03562
- Plan Check / Job No.
- B24LA19541
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (N) 2-STORY DUPLEX @ FRONT OF LOT. UNIT A: 1294SQFT UNIT B: 1378SQFT **13D FIRE SPRINKLER REQUIRED** 1 OF 2
- Permit Issued
- Issued on 4/24/2025
- Issuing Office
- Current Status
- CofO Issued on 5/29/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2024 | KHUONG TRUONG |
| Corrections Issued | 9/3/2024 | KHUONG TRUONG |
| Quality Review Completed | 9/10/2024 | KEN GILL |
| Applicant returned to address corrections | 3/24/2025 | KHUONG TRUONG |
| Plan Check Approved | 4/3/2025 | KHUONG TRUONG |
| Issued | 4/24/2025 | APPLICANT |
| CofO in Progress | 5/28/2026 | ARTHUR NEGRETE |
| Permit Finaled | 5/29/2026 | ANSON MAGLASANG |
| CofO Issued | 5/29/2026 | ANSON MAGLASANG |
| Permit Finaled | 5/29/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 9/10/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2024 | WALLIE JONG |
| Low Impact Development (LID) | Cleared | 9/19/2024 | SARAH YOUSSEF |
| Hydrant and Access approval | Cleared | 11/26/2024 | KURT CORRAL |
| Community Plan Implem. Overlay | Cleared | 2/11/2025 | ANACANY HURTADO |
| Historic Resource Verification | Cleared | 2/18/2025 | RAFAEL FONTES |
| ZI | Cleared | 3/6/2025 | DALIA MOKAYED |
| Roof/Waste drainage to street | Cleared | 3/10/2025 | CARLOS AGUILERA |
| Redevelopment Project Area | Cleared | 3/11/2025 | YASMINE BASHIRI |
| Sewer availability | Cleared | 3/20/2025 | CHRISTINA BRACO |
| Highway dedication | Cleared | 4/22/2025 | CELINA MORENO |
Contact Information
| Contractor | Pacific Coast Builders; Lic. No.: 834794-B | 9277OTTO ST DOWNEY, CA 90240 |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/7/2025 | Partial Approval | ANTHONY EGSON |
| Underground Mechanical | 5/7/2025 | Partial Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 5/13/2025 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2025 | Partial Approval | ANTHONY EGSON |
| Deputy Wood Construction | 8/21/2025 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2025 | Approved | ANTHONY EGSON |
| HVAC-Rough | 10/2/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 10/2/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 10/8/2025 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 10/8/2025 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 10/16/2025 | Partial Inspection | ANTHONY EGSON |
| Green Building Rough | 10/16/2025 | Partial Approval | ANTHONY EGSON |
| HVAC-Rough | 10/16/2025 | Partial Approval | ANTHONY EGSON |
| MERV13>=Rough | 10/16/2025 | Approved | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 10/16/2025 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 10/22/2025 | Approved | ANTHONY EGSON |
| Green Building Rough | 10/22/2025 | Approved | ANTHONY EGSON |
| Insulation | 10/22/2025 | Approved | ANTHONY EGSON |
| Drywall Nailing | 10/29/2025 | Partial Approval | ANTHONY EGSON |
| Insulation | 10/29/2025 | Partial Approval | ANTHONY EGSON |
| HVAC-Rough | 11/4/2025 | Approved | ANTHONY EGSON |
| Insulation | 11/4/2025 | Approved | ANTHONY EGSON |
| Drywall Nailing | 11/12/2025 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 11/12/2025 | Approved | ANTHONY EGSON |
| Sewer | 2/11/2026 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 2/11/2026 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 5/26/2026 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 5/26/2026 | Approved | ARTHUR NEGRETE |
| Smoke Detectors | 5/26/2026 | Approved | ARTHUR NEGRETE |
| Final | 5/27/2026 | OK to Issue CofO | ARTHUR NEGRETE |
| Green Building Final | 5/27/2026 | Approved | ARTHUR NEGRETE |
| MERV13>=Final | 5/27/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 5/27/2026 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 5/27/2026 | SGSOV Not Required | ARTHUR NEGRETE |
| Service/Power Release | 5/27/2026 | Approved | ARTHUR NEGRETE |