4231 S 8TH AVE 90008
Certificate Information: 4231 S 8TH AVE 90008
- Application / Permit
- 24010-10000-03556
- Plan Check / Job No.
- B24LA19464
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. NEW 741SF, 34' x 28' ACCESSORY DWELLING UNIT PER CALIFORNIA GOVERNMENT CODE 65852 IN THE REAR OF A MULTI-FAMILY BUILDING
- Permit Issued
- Issued on 12/11/2024
- Issuing Office
- Current Status
- CofO Issued on 11/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2024 | VARAND SARKISIAN |
| Corrections Issued | 9/3/2024 | VARAND SARKISIAN |
| Quality Review Completed | 9/5/2024 | GARO TELMI |
| Plan Check Approved | 9/26/2024 | VARAND SARKISIAN |
| Issued | 12/11/2024 | APPLICANT |
| CofO in Progress | 11/6/2025 | LUIS CASTRO |
| Permit Finaled | 11/10/2025 | DEROLD HAUFF |
| CofO Issued | 11/10/2025 | DEROLD HAUFF |
| Permit Finaled | 11/10/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 9/13/2024 | RIDWAN HARDY |
| Address approval | Cleared | 9/19/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 9/24/2024 | CELINA MORENO |
| Sewer availability | Cleared | 9/24/2024 | CELINA MORENO |
Contact Information
| Contractor | Archwood Builders & Development Inc; Lic. No.: 992843-B | , |
| Engineer | Liu,, Joseph; Lic. No.: NA60045 | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/17/2024 | Partial Inspection | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 1/29/2025 | Partial Approval | LUIS CASTRO |
| Footing/Foundation/Slab | 1/29/2025 | Approved | LUIS CASTRO |
| Grounding or Bonding | 1/29/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 1/29/2025 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2025 | Approved | LUIS CASTRO |
| HVAC-Rough | 4/8/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 4/8/2025 | Approved | LUIS CASTRO |
| Sewer | 4/8/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Rough | 4/11/2025 | Approved | LUIS CASTRO |
| Underground Mechanical | 4/11/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Rough | 4/14/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 4/18/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 4/18/2025 | Approved | LUIS CASTRO |
| Verify Sprinkler Sign Off | 4/18/2025 | Approved | LUIS CASTRO |
| Wood Frame | 4/18/2025 | Not Ready for Inspection | LUIS CASTRO |
| Interior/Exterior Lathing | 4/22/2025 | Approved | REGINA MENDEZ |
| Insulation | 4/24/2025 | Corrections Issued | ANTHONY RAMOS |
| Drywall Nailing | 5/1/2025 | Partial Approval | MICHAEL LEWIS |
| Insulation | 5/1/2025 | Partial Approval | MICHAEL LEWIS |
| Insulation | 5/5/2025 | Approved | LUIS CASTRO |
| Drywall Nailing | 5/7/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 5/23/2025 | Approved | LUIS CASTRO |
| Final | 8/12/2025 | Not Ready for Inspection | LUIS CASTRO |
| Green Building Final | 8/12/2025 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 8/12/2025 | SGSOV Not Required | LUIS CASTRO |
| Service/Power Release | 8/12/2025 | Not Ready for Inspection | LUIS CASTRO |
| Smoke Detectors | 8/12/2025 | Not Ready for Inspection | LUIS CASTRO |
| Final | 10/14/2025 | Corrections Issued | LUIS CASTRO |
| Service/Power Release | 10/14/2025 | Not Ready for Inspection | LUIS CASTRO |
| Smoke Detectors | 10/14/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 10/21/2025 | Approved | LUIS CASTRO |
| Final | 10/21/2025 | Corrections Issued | LUIS CASTRO |
| HVAC-Final | 10/21/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 10/21/2025 | Approved | LUIS CASTRO |
| Service/Power Release | 10/21/2025 | Not Ready for Inspection | LUIS CASTRO |
| Final | 10/23/2025 | Conditional Approval | LUIS CASTRO |
| Service/Power Release | 10/23/2025 | Approved | LUIS CASTRO |
| Final | 11/5/2025 | OK to Issue CofO | LUIS CASTRO |