193 N BENTLEY AVE 90049
Certificate Information: 193 N BENTLEY AVE 90049
- Application / Permit
- 24010-10000-03555
- Plan Check / Job No.
- B24LA19451
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- epaln New single Story, detached accessory dwelling unit with attached trellis ADU per state law CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g) NFPA 13D SPRINKLERED THROUGH OUT
- Permit Issued
- Issued on 10/1/2024
- Issuing Office
- Current Status
- CofO Issued on 5/15/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2024 | JAD BASMA |
| Corrections Issued | 8/31/2024 | JAD BASMA |
| Quality Review Completed | 9/5/2024 | GARO TELMI |
| Plan Check Approved | 9/26/2024 | JAD BASMA |
| Issued | 10/1/2024 | APPLICANT |
| CofO in Progress | 5/15/2026 | ANDREW NAVE |
| Permit Finaled | 5/15/2026 | RICHARD STEINBACH |
| CofO Issued | 5/15/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/15/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 9/6/2024 | VLADIMIR ARUTYUNYAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2024 | VLADIMIR ARUTYUNYAN |
| Roof/Waste drainage to street | Cleared | 9/6/2024 | VLADIMIR ARUTYUNYAN |
| Sewer availability | Cleared | 9/6/2024 | VLADIMIR ARUTYUNYAN |
| Street Frontage | Cleared | 9/6/2024 | VLADIMIR ARUTYUNYAN |
| Excavation more than 5-ft deep | Cleared | 9/26/2024 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 9/26/2024 | JAD BASMA |
| Grading Pre-Inspection | Cleared | 9/26/2024 | JAD BASMA |
Contact Information
| Contractor | Iv Construction Inc; Lic. No.: 623248-B | , |
Inspector Information
| ANDREW NAVE, (310) 914-3908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/4/2024 | Approved | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 12/11/2024 | Conditional Approval | CARLOS MATAMOROS |
| Piling/Pier/Caisson | 12/12/2024 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 12/16/2024 | Conditional Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 1/23/2025 | Corrections Issued | CARLOS MATAMOROS |
| Deputy Drilled-In Anchors | 1/27/2025 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 1/27/2025 | Conditional Approval | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 2/3/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 2/3/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 2/4/2025 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 2/4/2025 | Partial Approval | STEPHANIE SWANSON |
| Special/Order Compliance | 2/27/2025 | Approved | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 2/28/2025 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Steel/Welding | 3/4/2025 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2025 | Corrections Issued | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2025 | Conditional Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 4/3/2025 | Corrections Issued | CARLOS MATAMOROS |
| Special/Order Compliance | 4/18/2025 | Partial Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 4/21/2025 | Approved | MICHAEL PELHAM |
| Sewer | 4/21/2025 | Approved | MICHAEL PELHAM |
| Special/Order Compliance | 4/21/2025 | Partial Approval | CHRISTOPHER WILSON |
| Underground Mechanical | 4/21/2025 | Partial Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2025 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 6/2/2025 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 6/6/2025 | No Access for Inspection | CHRISTOPHER WILSON |
| HVAC-Rough | 6/6/2025 | No Access for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 6/9/2025 | Approved | CHRISTOPHER WILSON |
| HVAC-Rough | 6/9/2025 | Approved | CHRISTOPHER WILSON |
| Shower Pan | 6/27/2025 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 7/28/2025 | Corrections Issued | CHRISTOPHER WILSON |
| Green Building Rough | 7/28/2025 | Approved | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 7/28/2025 | Approved | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 7/31/2025 | Approved | SEAN HAUPT |
| Insulation | 8/14/2025 | Approved | SEAN HAUPT |
| Drywall Nailing | 9/15/2025 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 9/15/2025 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 12/2/2025 | Approved | CARLOS MATAMOROS |
| Final | 4/6/2026 | Corrections Issued | CARLOS MATAMOROS |
| Final | 5/5/2026 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 5/5/2026 | Approved | EVAN COOPER |
| Green Building Final | 5/5/2026 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 5/5/2026 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 5/5/2026 | Approved | EVAN COOPER |
| Smoke Detectors | 5/5/2026 | Approved | EVAN COOPER |
| Final | 5/12/2026 | Corrections Issued | EVAN COOPER |
| Final | 5/15/2026 | OK to Issue CofO | ANDREW NAVE |