4911 E MENDOTA AVE 90042
Certificate Information: 4911 E MENDOTA AVE 90042
- Application / Permit
- 24010-10000-03531
- Plan Check / Job No.
- B24LA19258
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- new 1-story detached accessory dwelling unit per CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 11/5/2024
- Issuing Office
- Current Status
- CofO Issued on 5/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2024 | JAD BASMA |
| Corrections Issued | 9/7/2024 | JAD BASMA |
| Quality Review Completed | 9/13/2024 | GARO TELMI |
| Applicant returned to address corrections | 9/26/2024 | JAD BASMA |
| Applicant returned to address corrections | 10/2/2024 | JAD BASMA |
| Plan Check Approved | 11/4/2024 | JAD BASMA |
| Issued | 11/5/2024 | APPLICANT |
| CofO in Progress | 5/6/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 5/7/2025 | DEROLD HAUFF |
| CofO Issued | 5/7/2025 | DEROLD HAUFF |
| Permit Finaled | 5/7/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/18/2024 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 9/19/2024 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 9/27/2024 | MICHAEL TEMPLE |
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2024 | WALLIE JONG |
| Sewer availability | Cleared | 9/30/2024 | WALLIE JONG |
| GPI Written Notices | Cleared | 11/1/2024 | JAD BASMA |
Contact Information
| Contractor | Pyramid - J E D A Construction Co Inc; Lic. No.: 910045-B | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/10/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 12/10/2024 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 12/12/2024 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 12/12/2024 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 12/13/2024 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2025 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2025 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 2/12/2025 | Corrections Issued | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 2/12/2025 | Corrections Issued | THOMAS LOGRASSO |
| Insulation | 2/21/2025 | Not Ready for Inspection | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 2/21/2025 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 2/28/2025 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 2/28/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 2/28/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 2/28/2025 | Approved | NICHOLAS LOPEZ |
| Rough-Elec/Plmb/HVAC | 2/28/2025 | Approved | NICHOLAS LOPEZ |
| Service/Power Release | 3/19/2025 | Partial Approval | NICHOLAS LOPEZ |
| Underground Mechanical | 3/19/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 4/7/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Final | 4/7/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 4/7/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Final | 4/7/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| HVAC-Final | 4/7/2025 | Corrections Issued | NICHOLAS LOPEZ |
| PLUMBING-Final | 4/7/2025 | Corrections Issued | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 4/7/2025 | SGSOV No Gas | NICHOLAS LOPEZ |
| Service/Power Release | 4/7/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Smoke Detectors | 4/7/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 4/17/2025 | Approved | NICHOLAS LOPEZ |
| Final | 4/17/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 4/17/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| HVAC-Final | 4/17/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Final | 4/17/2025 | Approved | NICHOLAS LOPEZ |
| Service/Power Release | 4/17/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Smoke Detectors | 4/17/2025 | Approved | NICHOLAS LOPEZ |
| Final | 5/6/2025 | OK to Issue CofO | NICHOLAS LOPEZ |
| Green Building Final | 5/6/2025 | Approved | NICHOLAS LOPEZ |
| Service/Power Release | 5/6/2025 | Approved | NICHOLAS LOPEZ |