900 W ANAHEIM ST 90744
Certificate Information: 900 W ANAHEIM ST 90744
- Application / Permit
- 24010-10000-03463
- Plan Check / Job No.
- B24LA18499
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- ePlan: (N) RESTAURANT WITH DRIVE-THRU
- Permit Issued
- Issued on 10/21/2025
- Issuing Office
- Current Status
- Issued on 10/21/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/20/2024 | APPLICANT |
| Assigned to Zoning Architect | 8/29/2024 | LY CHEA |
| Assigned to Plan Check Engineer | 9/5/2024 | DANIEL YIP |
| Corrections Issued | 9/13/2024 | DANIEL YIP |
| Quality Review Completed | 9/26/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 4/10/2025 | DANIEL YIP |
| Applicant returned to address corrections | 4/22/2025 | DANIEL YIP |
| Applicant returned to address corrections | 5/1/2025 | DANIEL YIP |
| Applicant returned to address corrections | 5/29/2025 | DANIEL YIP |
| Plan Check Approved | 10/20/2025 | DANIEL YIP |
| Issued | 10/21/2025 | APPLICANT |
Permit Application Clearance Information
| Permit | Cleared | 2/20/2025 | XOCHITL ARQUIETA |
| Hydrant and Access approval | Cleared | 2/21/2025 | RUEL COLE |
| Methane Ordinance | Cleared | 2/21/2025 | VIDAL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2025 | DAVID PEREZ |
| Sewer availability | Cleared | 2/26/2025 | DAVID PEREZ |
| Highway dedication | Cleared | 3/28/2025 | DAVID PEREZ |
| Construction near power lines | Cleared | 4/24/2025 | RIDWAN HARDY |
| Green Code | Cleared | 5/9/2025 | Angelica Martinez |
| Drive Through | Cleared | 5/13/2025 | RICHARD WOO |
| Driveway location | Cleared | 5/13/2025 | RICHARD WOO |
| DAS Clearance | Cleared | 7/22/2025 | LY CHEA |
| Low Impact Development (LID) | Cleared | 8/28/2025 | LUIS LUVANO |
| "Q" conditions | Cleared | 8/29/2025 | YINGSHI HUANG |
| Comm Cor/Mini-Mall | Cleared | 8/29/2025 | YINGSHI HUANG |
| Comm Cor/Mini-Mall | Cleared | 8/29/2025 | YINGSHI HUANG |
| Drive-through fast food | Cleared | 8/29/2025 | YINGSHI HUANG |
| ZA Case | Cleared | 8/29/2025 | YINGSHI HUANG |
| ZA Case | Cleared | 8/29/2025 | YINGSHI HUANG |
| ZA Case | Cleared | 8/29/2025 | YINGSHI HUANG |
| ZA Case | Cleared | 8/29/2025 | YINGSHI HUANG |
| Roof/Waste drainage to street | Cleared | 9/8/2025 | XOCHITL ARQUIETA |
| Zoning Plan Check | Cleared | 9/22/2025 | LY CHEA |
| Food establishment approval | Cleared | 10/20/2025 | LACDHS APPROVED |
Contact Information
| Architect | Bickel,, James S; Lic. No.: C20925 | 3600 BIRCH STREET SUITE 120 NEWPORT BEACH, CA 92660 |
| Contractor | W C C G Inc; Lic. No.: 1080578-B | , |
| Engineer | Ferrer,, Eric Joseph Rabano; Lic. No.: C97020 | 12651 ARTESIA BLVD APT 340 CERRITOS, CA 90703 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/10/2026 | Partial Inspection | DAVID TSAU |
| Deputy Methane Barrier | 2/27/2026 | Conditional Approval | DAVID TSAU |
| Footing/Foundation/Slab | 3/5/2026 | Not Ready for Inspection | DAVID TSAU |
| METHANE-Barrier | 3/5/2026 | Not Ready for Inspection | DAVID TSAU |
| METHANE-Subgrade | 3/5/2026 | Not Ready for Inspection | DAVID TSAU |
| Footing/Foundation/Slab | 3/11/2026 | Not Ready for Inspection | DAVID TSAU |
| METHANE-Barrier | 3/11/2026 | Approved | DAVID TSAU |
| METHANE-Subgrade | 3/11/2026 | Approved | DAVID TSAU |
| Special/Order Compliance | 3/11/2026 | Partial Approval | MICHAEL PETRUSKO |
| Footing/Foundation/Slab | 3/12/2026 | Partial Approval | DAVID TSAU |
| Pre-Inspection | 3/12/2026 | Approved | DAVID TSAU |
| Deputy Reinf. Concrete | 3/13/2026 | Approved | DAVID TSAU |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2026 | Not Ready for Inspection | DAVID TSAU |
| Green Building Rough | 3/19/2026 | Not Ready for Inspection | DAVID TSAU |
| METHANE-Rough | 3/19/2026 | Not Ready for Inspection | DAVID TSAU |
| Verify Sprinkler Sign Off | 3/19/2026 | Not Ready for Inspection | DAVID TSAU |
| Wood Frame | 3/19/2026 | Not Ready for Inspection | DAVID TSAU |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2026 | Partial Inspection | DAVID TSAU |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2026 | Partial Approval | DAVID TSAU |
| Green Building Rough | 3/25/2026 | Not Ready for Inspection | DAVID TSAU |
| METHANE-Rough | 3/25/2026 | Not Ready for Inspection | DAVID TSAU |
| Verify Sprinkler Sign Off | 3/25/2026 | Not Ready for Inspection | DAVID TSAU |
| Wood Frame | 3/25/2026 | Not Ready for Inspection | DAVID TSAU |
| Insulation | 3/26/2026 | Partial Approval | DAVID TSAU |
| Green Building Rough | 4/3/2026 | Not Ready for Inspection | DAVID TSAU |
| METHANE-Rough | 4/3/2026 | Not Ready for Inspection | DAVID TSAU |
| Verify Sprinkler Sign Off | 4/3/2026 | Not Ready for Inspection | DAVID TSAU |
| Wood Frame | 4/3/2026 | Partial Inspection | DAVID TSAU |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2026 | Partial Approval | DAVID TSAU |
| Green Building Rough | 4/6/2026 | Not Ready for Inspection | DAVID TSAU |
| METHANE-Rough | 4/6/2026 | Not Ready for Inspection | DAVID TSAU |
| Verify Sprinkler Sign Off | 4/6/2026 | Not Ready for Inspection | DAVID TSAU |
| Wood Frame | 4/6/2026 | Not Ready for Inspection | DAVID TSAU |
| Green Building Rough | 4/8/2026 | Approved | MICHAEL PETRUSKO |
| Insulation | 4/8/2026 | Approved | MICHAEL PETRUSKO |
| METHANE-Rough | 4/8/2026 | Approved | MICHAEL PETRUSKO |
| Verify Sprinkler Sign Off | 4/8/2026 | Approved | MICHAEL PETRUSKO |
| Wood Frame | 4/8/2026 | Approved | MICHAEL PETRUSKO |
| Deputy Wood Construction | 4/9/2026 | Conditional Approval | MICHAEL PETRUSKO |
| Drywall Nailing | 4/15/2026 | Partial Approval | DAVID TSAU |
| Interior/Exterior Lathing | 4/20/2026 | Partial Approval | DAVID TSAU |
| Deputy Reinf. Concrete | 4/29/2026 | Conditional Approval | MICHAEL PETRUSKO |
| Footing/Foundation/Slab | 5/6/2026 | Partial Approval | DAVID TSAU |
| Deputy Reinf. Concrete | 5/11/2026 | Conditional Approval | DAVID TSAU |
| T-Bar Ceiling | 5/15/2026 | Not Ready for Inspection | DAVID TSAU |
| T-Bar Ceiling | 5/18/2026 | Partial Inspection | DAVID TSAU |
| T-Bar Ceiling | 6/2/2026 | Not Ready for Inspection | DAVID TSAU |