4412 E CATALPA ST 90032

Certificate Information: 4412 E CATALPA ST 90032

Application / Permit
24010-10000-03434
Plan Check / Job No.
B24LA18029
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. New detatched ADU per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 1/6/2025
Issuing Office
Current Status
CofO Issued on 12/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/4/2024 APPLICANT
Assigned to Plan Check Engineer 9/9/2024 ALEXANDER JOO
Corrections Issued 9/10/2024 ALEXANDER JOO
Plan Check Approved 11/8/2024 ADAM HEGAZI
Issued 1/6/2025 APPLICANT
CofO in Progress 12/11/2025 LILIANA PORTILLO
Permit Finaled 12/12/2025 DEROLD HAUFF
CofO Issued 12/12/2025 DEROLD HAUFF
Permit Finaled 12/12/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/7/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 10/7/2024 JUSTIN BICOL
Roof/Waste drainage to street Cleared 10/7/2024 JUSTIN BICOL
Sewer availability Cleared 10/7/2024 JUSTIN BICOL

Contact Information

Contractor Danick'S Construction; Lic. No.: 1090811-B       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/18/2025 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 2/20/2025 Partial Approval LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 3/10/2025 Corrections Issued LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 3/13/2025 Approved LILIANA PORTILLO
Pre-Inspection 4/10/2025 Partial Inspection LILIANA PORTILLO
Deputy Wood Construction 4/15/2025 Conditional Approval LILIANA PORTILLO
Underground Mechanical 4/15/2025 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 7/1/2025 Approved LILIANA PORTILLO
Rough-Elec/Plmb/HVAC 7/1/2025 Corrections Issued LILIANA PORTILLO
Verify Sprinkler Sign Off 7/1/2025 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 7/22/2025 Conditional Approval LILIANA PORTILLO
ELECTRICAL-Rough 7/22/2025 Approved LILIANA PORTILLO
Green Building Rough 7/22/2025 Not Ready for Inspection LILIANA PORTILLO
HVAC-Rough 7/22/2025 Approved LILIANA PORTILLO
Insulation 7/22/2025 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 7/22/2025 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 7/22/2025 Approved LILIANA PORTILLO
Insulation 8/8/2025 Approved REGINA MENDEZ
Shower Pan 8/8/2025 Approved REGINA MENDEZ
Drywall Nailing 9/16/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 9/16/2025 Approved REGINA MENDEZ
Service/Power Release 11/3/2025 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 11/14/2025 Approved LILIANA PORTILLO
Final 11/14/2025 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 11/14/2025 Approved LILIANA PORTILLO
Green Building Final 11/14/2025 Approved LILIANA PORTILLO
Green Building Rough 11/14/2025 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 11/14/2025 SGSOV No Gas LILIANA PORTILLO
Service/Power Release 11/14/2025 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 11/14/2025 Approved LILIANA PORTILLO
Final 11/18/2025 Not Ready for Inspection LILIANA PORTILLO
Service/Power Release 11/18/2025 Conditional Approval LILIANA PORTILLO
ELECTRICAL-Final 12/10/2025 Approved LILIANA PORTILLO
Final 12/10/2025 OK to Issue CofO LILIANA PORTILLO
HVAC-Final 12/10/2025 Approved LILIANA PORTILLO
PLUMBING-Final 12/10/2025 Approved LILIANA PORTILLO
Service/Power Release 12/10/2025 Approved LILIANA PORTILLO