2372 S KELTON AVE 90064

Certificate Information: 2372 S KELTON AVE 90064

Application / Permit
24010-10000-03418
Plan Check / Job No.
B24LA17847
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
[ePlan] new detached 1123 ft 2-story Accessory Dwelling Unit (ADU)
Permit Issued
Issued on 9/25/2024
Issuing Office
Current Status
CofO Issued on 6/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2024 APPLICANT
Assigned to Plan Check Engineer 8/15/2024 VARAND SARKISIAN
Corrections Issued 8/19/2024 VARAND SARKISIAN
Quality Review Completed 8/20/2024 GARO TELMI
Plan Check Approved 9/16/2024 VARAND SARKISIAN
Issued 9/25/2024 APPLICANT
CofO in Progress 6/13/2025 TEMISTOCLES CAAL
Permit Finaled 6/17/2025 RICHARD STEINBACH
CofO Issued 6/17/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 8/21/2024 VLADIMIR ARUTYUNYAN
Specific Plan Cleared 8/22/2024 JAZMIN ROQUE
Specific Plan Cleared 8/26/2024 FREDDY GARCIA
Eng Process Fee Ord 176,300 Cleared 8/27/2024 VLADIMIR ARUTYUNYAN
Roof/Waste drainage to street Cleared 8/27/2024 VLADIMIR ARUTYUNYAN
Sewer availability Cleared 8/27/2024 VLADIMIR ARUTYUNYAN
Grading Pre-Inspection Cleared 9/16/2024 VARAND SARKISIAN

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Oded Kravitz General Contractor Inc; Lic. No.: 1009679-B       ,
Engineer Messiha,, Hany Gamil; Lic. No.: NA56766       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/24/2024 Partial Approval MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 10/30/2024 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 11/18/2024 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 11/21/2024 Conditional Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 1/27/2025 Corrections Issued SEAN HAUPT
HVAC-Rough 1/27/2025 Corrections Issued SEAN HAUPT
PLUMBING-Rough 1/27/2025 Corrections Issued SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 1/31/2025 Partial Approval EVAN COOPER
HVAC-Rough 1/31/2025 Approved EVAN COOPER
PLUMBING-Rough 1/31/2025 Approved EVAN COOPER
BUILDING-Rough-Frame 2/14/2025 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Rough 2/14/2025 Not Ready for Inspection DANIEL VERA
Verify Sprinkler Sign Off 2/14/2025 Corrections Issued DANIEL VERA
BUILDING-Rough-Frame 2/20/2025 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Rough 2/20/2025 Approved DANIEL VERA
Verify Sprinkler Sign Off 2/20/2025 Not Ready for Inspection DANIEL VERA
BUILDING-Rough-Frame 3/6/2025 Approved KIRK SANDERS
Interior/Exterior Lathing 3/6/2025 Approved KIRK SANDERS
Verify Sprinkler Sign Off 3/6/2025 Approved KIRK SANDERS
ELECTRICAL-Final 3/10/2025 Corrections Issued WILBER ROSALES
Insulation 3/10/2025 Approved WILBER ROSALES
Drywall Nailing 3/13/2025 Conditional Approval KIRK SANDERS
Drywall Nailing 6/3/2025 Approved STEPHANIE SWANSON
ELECTRICAL-Final 6/3/2025 Corrections Issued STEPHANIE SWANSON
Final 6/3/2025 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 6/3/2025 Approved STEPHANIE SWANSON
HVAC-Final 6/3/2025 Approved STEPHANIE SWANSON
PLUMBING-Final 6/3/2025 Corrections Issued STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 6/3/2025 SGSOV Not Required STEPHANIE SWANSON
Service/Power Release 6/3/2025 Not Ready for Inspection STEPHANIE SWANSON
Smoke Detectors 6/3/2025 Approved STEPHANIE SWANSON
Final 6/10/2025 Corrections Issued ARAM AVEDISIAN
PLUMBING-Final 6/10/2025 Not Ready for Inspection ARAM AVEDISIAN
Service/Power Release 6/10/2025 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Final 6/12/2025 Approved TEMISTOCLES CAAL
Final 6/12/2025 OK to Issue CofO TEMISTOCLES CAAL
PLUMBING-Final 6/12/2025 Approved TEMISTOCLES CAAL
Service/Power Release 6/12/2025 Approved TEMISTOCLES CAAL