1638 N ISLAND AVE 90744

Certificate Information: 1638 N ISLAND AVE 90744

Application / Permit
24010-10000-03390
Plan Check / Job No.
B24LA17668
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: NEW 1192 S.F. DETACHED ADU
Permit Issued
Issued on 9/30/2025
Issuing Office
Current Status
Issued on 9/30/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/15/2024 APPLICANT
Assigned to Plan Check Engineer 8/21/2024 JOSEPH RAFOLS
Corrections Issued 8/22/2024 JOSEPH RAFOLS
Applicant returned to address corrections 1/28/2025 JOHN MESIAS
Applicant returned to address corrections 2/4/2025 KELVIN CHUONG
Plan Check Approved 2/27/2025 FERNANDO FLORES
Issued 9/30/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/10/2024 ERIK BEASLEY
Roof/Waste drainage to street Cleared 10/17/2024 XOCHITL ARQUIETA
Clean Up Green Up Cleared 10/24/2024 DAVID URITA
ZA Case Cleared 10/24/2024 DAVID URITA
ZA Case Cleared 10/24/2024 DAVID URITA
Eng Process Fee Ord 176,300 Cleared 2/25/2025 ERIK BEASLEY
Sewer availability Cleared 2/25/2025 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Lionel J; Lic. No.: S4653 24702 NARBONNE AVE      LOMITA, CA 90717

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Insulation 6/24/2026   

Inspection Request History

METHANE-Barrier 1/5/2026 Not Ready for Inspection EUGENE CASSIDY
METHANE-Subgrade 1/5/2026 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 1/5/2026 Partial Approval EUGENE CASSIDY
METHANE-Subgrade 1/15/2026 Approved EUGENE CASSIDY
Deputy Methane Barrier 1/20/2026 Partial Approval EUGENE CASSIDY
METHANE-Final 1/21/2026 Not Ready for Inspection EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 1/27/2026 Approved EUGENE CASSIDY
METHANE-Barrier 1/27/2026 Approved EUGENE CASSIDY
METHANE-Subgrade 1/27/2026 Approved EUGENE CASSIDY
Deputy Methane Barrier 1/28/2026 Partial Approval EUGENE CASSIDY
Deputy Methane Barrier 1/29/2026 Partial Approval JOSEPH MCGARRY
Deputy Methane Barrier 2/3/2026 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 3/17/2026 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 4/20/2026 Approved JOSEPH MCGARRY
Wood Frame 4/20/2026 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 6/1/2026 Approved EUGENE CASSIDY
HVAC-Rough 6/1/2026 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 6/1/2026 Approved EUGENE CASSIDY
Sewer 6/1/2026 Corrections Issued EUGENE CASSIDY
Wood Frame 6/1/2026 Approved EUGENE CASSIDY
HVAC-Rough 6/4/2026 Approved EUGENE CASSIDY
PLUMBING-Rough 6/4/2026 Approved EUGENE CASSIDY
Sewer 6/4/2026 Approved EUGENE CASSIDY
Underground Mechanical 6/11/2026 Partial Approval JOSEPH MCGARRY