5313 E HYDE ST 90032
Certificate Information: 5313 E HYDE ST 90032
- Application / Permit
- 24010-10000-03384
- Plan Check / Job No.
- B24LA17568
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN.(N) DETACHED 800 SF ADU. PER LAMC 12.22 A.33(c) AND (d) PER ENGINEER DESIGN.
- Permit Issued
- Issued on 12/25/2024
- Issuing Office
- Current Status
- CofO Issued on 1/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2024 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 8/19/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 10/2/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 11/15/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 11/27/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 12/5/2024 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 12/20/2024 | ALFREDO JARA |
| Issued | 12/25/2024 | APPLICANT |
| CofO in Progress | 1/22/2026 | LILIANA PORTILLO |
| Permit Finaled | 1/26/2026 | DEROLD HAUFF |
| CofO Issued | 1/26/2026 | DEROLD HAUFF |
| Permit Finaled | 1/26/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/21/2024 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 8/21/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 9/16/2024 | DAVID LOPEZ |
| GPI Written Notices | Cleared | 11/16/2024 | MIROOSH KHACHATOORIAN |
| Grading Pre-Inspection | Cleared | 11/16/2024 | MIROOSH KHACHATOORIAN |
Contact Information
| Contractor | Levet Inc; Lic. No.: 1027447-B | , |
| Engineer | Acciani,, Mark; Lic. No.: C83929 | PO BOX 1390 RUNNING SPRINGS, CA 92382 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/22/2025 | Partial Approval | LILIANA PORTILLO |
| Sewer | 1/22/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 1/28/2025 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 1/28/2025 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2025 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2025 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2025 | Partial Approval | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 4/21/2025 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/4/2025 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2025 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 8/4/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 8/4/2025 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/8/2025 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/8/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 8/8/2025 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 9/3/2025 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 9/3/2025 | Partial Approval | LILIANA PORTILLO |
| Underground Mechanical | 9/3/2025 | Approved | LILIANA PORTILLO |
| Insulation | 9/17/2025 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 9/22/2025 | Approved | LILIANA PORTILLO |
| Green Building Rough | 9/22/2025 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 9/30/2025 | Approved | LILIANA PORTILLO |
| Final | 12/8/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Footing/Foundation/Slab | 12/8/2025 | Approved | LILIANA PORTILLO |
| Green Building Final | 12/8/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 12/8/2025 | SGSOV Not Ready | LILIANA PORTILLO |
| Service/Power Release | 12/8/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 12/8/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 12/11/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 12/11/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 12/11/2025 | SGSOV No Gas | ALIZAH MAYAGOITIA |
| Service/Power Release | 12/11/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 12/11/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 1/7/2026 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 1/7/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Service/Power Release | 1/7/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 1/14/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 1/14/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Service/Power Release | 1/14/2026 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 1/21/2026 | Approved | LILIANA PORTILLO |
| Final | 1/21/2026 | OK to Issue CofO | LILIANA PORTILLO |
| Green Building Final | 1/21/2026 | Approved | LILIANA PORTILLO |
| HVAC-Final | 1/21/2026 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 1/21/2026 | Approved | LILIANA PORTILLO |