5313 E HYDE ST 90032

Certificate Information: 5313 E HYDE ST 90032

Application / Permit
24010-10000-03384
Plan Check / Job No.
B24LA17568
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN.(N) DETACHED 800 SF ADU. PER LAMC 12.22 A.33(c) AND (d) PER ENGINEER DESIGN.
Permit Issued
Issued on 12/25/2024
Issuing Office
Current Status
CofO Issued on 1/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2024 APPLICANT
Assigned to Plan Check Engineer 8/16/2024 MIROOSH KHACHATOORIAN
Corrections Issued 8/19/2024 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 10/2/2024 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 11/15/2024 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 11/27/2024 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 12/5/2024 MIROOSH KHACHATOORIAN
Plan Check Approved 12/20/2024 ALFREDO JARA
Issued 12/25/2024 APPLICANT
CofO in Progress 1/22/2026 LILIANA PORTILLO
Permit Finaled 1/26/2026 DEROLD HAUFF
CofO Issued 1/26/2026 DEROLD HAUFF
Permit Finaled 1/26/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/21/2024 DAVID LOPEZ
Roof/Waste drainage to street Cleared 8/21/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 9/16/2024 DAVID LOPEZ
Sewer availability Cleared 9/16/2024 DAVID LOPEZ
GPI Written Notices Cleared 11/16/2024 MIROOSH KHACHATOORIAN
Grading Pre-Inspection Cleared 11/16/2024 MIROOSH KHACHATOORIAN

Contact Information

Contractor Levet Inc; Lic. No.: 1027447-B       ,
Engineer Acciani,, Mark; Lic. No.: C83929 PO BOX 1390      RUNNING SPRINGS, CA 92382

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/22/2025 Partial Approval LILIANA PORTILLO
Sewer 1/22/2025 Not Ready for Inspection LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 1/28/2025 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 1/28/2025 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 2/19/2025 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 2/24/2025 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 4/21/2025 Partial Approval LILIANA PORTILLO
Verify Sprinkler Sign Off 4/21/2025 Approved LILIANA PORTILLO
ELECTRICAL-Rough 8/4/2025 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 8/4/2025 Corrections Issued LILIANA PORTILLO
HVAC-Rough 8/4/2025 Approved LILIANA PORTILLO
PLUMBING-Rough 8/4/2025 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 8/8/2025 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 8/8/2025 Approved LILIANA PORTILLO
PLUMBING-Rough 8/8/2025 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 9/3/2025 Approved LILIANA PORTILLO
Interior/Exterior Lathing 9/3/2025 Partial Approval LILIANA PORTILLO
Underground Mechanical 9/3/2025 Approved LILIANA PORTILLO
Insulation 9/17/2025 Approved LILIANA PORTILLO
Drywall Nailing 9/22/2025 Approved LILIANA PORTILLO
Green Building Rough 9/22/2025 Approved LILIANA PORTILLO
Interior/Exterior Lathing 9/30/2025 Approved LILIANA PORTILLO
Final 12/8/2025 Not Ready for Inspection LILIANA PORTILLO
Footing/Foundation/Slab 12/8/2025 Approved LILIANA PORTILLO
Green Building Final 12/8/2025 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 12/8/2025 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 12/8/2025 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 12/8/2025 Not Ready for Inspection LILIANA PORTILLO
Final 12/11/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 12/11/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 12/11/2025 SGSOV No Gas ALIZAH MAYAGOITIA
Service/Power Release 12/11/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 12/11/2025 Approved ALIZAH MAYAGOITIA
Final 1/7/2026 Corrections Issued LILIANA PORTILLO
Green Building Final 1/7/2026 Not Ready for Inspection LILIANA PORTILLO
Service/Power Release 1/7/2026 Not Ready for Inspection LILIANA PORTILLO
Final 1/14/2026 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 1/14/2026 Not Ready for Inspection LILIANA PORTILLO
Service/Power Release 1/14/2026 Approved LILIANA PORTILLO
ELECTRICAL-Final 1/21/2026 Approved LILIANA PORTILLO
Final 1/21/2026 OK to Issue CofO LILIANA PORTILLO
Green Building Final 1/21/2026 Approved LILIANA PORTILLO
HVAC-Final 1/21/2026 Approved LILIANA PORTILLO
PLUMBING-Final 1/21/2026 Approved LILIANA PORTILLO