1243 N WATSON AVE 90744

Certificate Information: 1243 N WATSON AVE 90744

Application / Permit
24010-10000-03378
Plan Check / Job No.
B24LA17493
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: NEW 1-story SFD
Permit Issued
Issued on 1/30/2025
Issuing Office
Current Status
Issued on 1/30/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/12/2024 APPLICANT
Assigned to Plan Check Engineer 8/15/2024 ARSALAN SHABESTARI
Corrections Issued 8/17/2024 ARSALAN SHABESTARI
Quality Review Completed 8/22/2024 YOUNG KIM
Applicant returned to address corrections 1/3/2025 ARSALAN SHABESTARI
Plan Check Approved 1/26/2025 ARSALAN SHABESTARI
Issued 1/30/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/11/2024 JILVER MAZARIEGOS
Roof/Waste drainage to street Cleared 9/12/2024 JILVER MAZARIEGOS
"Q" conditions Cleared 9/17/2024 MATHEW QUAN
Clean Up Green Up Cleared 9/17/2024 MATHEW QUAN
ZI Cleared 9/17/2024 MATHEW QUAN
ZI Cleared 9/17/2024 MATHEW QUAN
Eng Process Fee Ord 176,300 Cleared 9/19/2024 JILVER MAZARIEGOS
Sewer availability Cleared 9/19/2024 JILVER MAZARIEGOS
ZI Cleared 10/28/2024 MATHEW QUAN
Hydrant and Access approval Cleared 12/2/2024 JERRY KAO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/26/2025 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 2/26/2025 Not Ready for Inspection EUGENE CASSIDY
METHANE-Barrier 2/26/2025 Not Ready for Inspection EUGENE CASSIDY
METHANE-Subgrade 2/26/2025 Not Ready for Inspection EUGENE CASSIDY
Piling/Pier/Caisson 2/26/2025 Not Ready for Inspection EUGENE CASSIDY
Pre-Inspection 2/26/2025 Not Ready for Inspection EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 2/28/2025 Corrections Issued EUGENE CASSIDY
Piling/Pier/Caisson 2/28/2025 Not Ready for Inspection EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 3/5/2025 Approved EUGENE CASSIDY
Footing/Foundation/Slab 3/5/2025 Approved EUGENE CASSIDY
METHANE-Barrier 3/5/2025 Approved EUGENE CASSIDY
METHANE-Subgrade 3/5/2025 Approved EUGENE CASSIDY
Piling/Pier/Caisson 3/5/2025 Not Ready for Inspection EUGENE CASSIDY
Pre-Inspection 3/5/2025 Approved EUGENE CASSIDY
PLUMBING-Rough 3/18/2025 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 3/19/2025 Partial Approval EUGENE CASSIDY
Wood Frame 3/25/2025 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 4/25/2025 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 4/25/2025 Corrections Issued EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 4/25/2025 Approved EUGENE CASSIDY
Green Building Rough 4/25/2025 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 4/25/2025 Approved EUGENE CASSIDY
PLUMBING-Rough 4/25/2025 Partial Approval EUGENE CASSIDY
Verify Sprinkler Sign Off 4/25/2025 Not Ready for Inspection EUGENE CASSIDY
Wood Frame 4/25/2025 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 5/13/2025 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 5/13/2025 Not Ready for Inspection EUGENE CASSIDY
Wood Frame 5/13/2025 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 9/26/2025 Conditional Approval JOSEPH MCGARRY
ELECTRICAL-Rough 9/26/2025 Approved JOSEPH MCGARRY
HVAC-Rough 9/26/2025 Partial Approval JOSEPH MCGARRY
Interior/Exterior Lathing 9/26/2025 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 9/26/2025 Approved JOSEPH MCGARRY
Underground Mechanical 9/26/2025 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 10/6/2025 Approved EUGENE CASSIDY
Drywall Nailing 10/6/2025 Approved EUGENE CASSIDY
Green Building Rough 10/6/2025 Approved EUGENE CASSIDY
HVAC-Rough 10/6/2025 Approved EUGENE CASSIDY
Insulation 10/6/2025 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 10/6/2025 Approved EUGENE CASSIDY
Shower Pan 10/15/2025 Approved EUGENE CASSIDY
ELECTRICAL-Rough 10/20/2025 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 11/25/2025 Approved EUGENE CASSIDY
Drywall Nailing 11/25/2025 Approved EUGENE CASSIDY
Insulation 11/25/2025 Approved EUGENE CASSIDY
Special/Order Compliance 11/25/2025 Corrections Issued EUGENE CASSIDY
Underground Mechanical 11/25/2025 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 5/18/2026 Corrections Issued BEN MOLSTAD