5102 N FALLBROOK AVE 91364

Certificate Information: 5102 N FALLBROOK AVE 91364

Application / Permit
24010-10000-03345
Plan Check / Job No.
B24VN09780
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN.* New detached 1-story ADU at rear of lot. ADU per LAMC 12.22 A.33(c) and (d). < NFPA 13R fire sprinklers REQd thru-out BLDG. >
Permit Issued
Issued on 12/27/2024
Issuing Office
Current Status
Issued on 12/27/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/11/2024 APPLICANT
Assigned to Plan Check Engineer 7/18/2024 HUAN LE
Corrections Issued 8/13/2024 HUAN LE
Quality Review Completed 8/14/2024 GARO TELMI
Applicant returned to address corrections 11/5/2024 HUAN LE
Applicant returned to address corrections 12/17/2024 HUAN LE
Plan Check Approved 12/26/2024 HUAN LE
Issued 12/27/2024 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/9/2024 HUAN LE
Address approval Cleared 8/20/2024 BIAINA HARITUNIAN
BHO/Hillside ordinance Cleared 8/20/2024 BIAINA HARITUNIAN
BHO/Hillside ordinance Cleared 8/20/2024 BIAINA HARITUNIAN
BHO/Hillside ordinance Cleared 8/20/2024 BIAINA HARITUNIAN
BHO/Hillside ordinance Cleared 8/20/2024 BIAINA HARITUNIAN
BHO/Hillside ordinance Cleared 8/20/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 8/21/2024 BIAINA HARITUNIAN
Sewer availability Cleared 10/1/2024 BIAINA HARITUNIAN
Hydrant and Access approval Cleared 10/15/2024 KURT CORRAL
GPI Written Notices Cleared 12/17/2024 HUAN LE
Roof/Waste drainage to street Cleared 12/17/2024 BIAINA HARITUNIAN
Hold Cleared 12/26/2024 HUAN LE

Contact Information

Contractor K & K Modern Construction; Lic. No.: 1126272-B       ,
Engineer Karapetian,, Arbi; Lic. No.: C79953 6854 FOOTHILL BLVD      TUJUNGA, CA 91042

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

ELECTRICAL-Final 6/8/2026   
HVAC-Final 6/8/2026   
Service/Power Release 6/8/2026   
Final 6/8/2026   
PLUMBING-Final 6/8/2026   

Inspection Request History

Pre-Inspection 1/16/2025 Not Ready for Inspection JOHN HAYES
Deputy Drilled-In Anchors 2/10/2025 Conditional Approval JOHN HAYES
PLUMBING-Rough 3/5/2025 Corrections Issued SCOTT SOBEL
PLUMBING-Rough 3/7/2025 Corrections Issued JOHN HAYES
PLUMBING-Rough 3/11/2025 Not Ready for Inspection JOHN COLEMAN
PLUMBING-Rough 3/17/2025 Partial Approval JOHN COLEMAN
Excavation/Setback/Form/Re-Bar 4/10/2025 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 4/10/2025 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 4/14/2025 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 4/17/2025 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 4/21/2025 Approved JOHN HAYES
Wood Frame 5/30/2025 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 6/5/2025 Corrections Issued JOHN COLEMAN
HVAC-Rough 6/5/2025 Not Ready for Inspection JOHN COLEMAN
PLUMBING-Rough 6/5/2025 Corrections Issued JOHN COLEMAN
BUILDING-Rough-Frame 6/13/2025 Corrections Issued JOHN HAYES
Green Building Rough 6/13/2025 Not Ready for Inspection JOHN HAYES
HVAC-Rough 6/13/2025 Not Ready for Inspection JOHN HAYES
MERV13>=Rough 6/13/2025 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 6/13/2025 Not Ready for Inspection JOHN HAYES
Wood Frame 6/13/2025 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 7/14/2025 Corrections Issued JEFFREY PARD
ELECTRICAL-Rough 7/14/2025 Approved JEFFREY PARD
Green Building Rough 7/14/2025 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 7/14/2025 Approved JEFFREY PARD
MERV13>=Rough 7/14/2025 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 7/14/2025 Partial Approval JEFFREY PARD
Verify Sprinkler Sign Off 7/14/2025 Not Ready for Inspection JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 7/15/2025 Approved SEAN WIRCH
Verify Sprinkler Sign Off 7/15/2025 Not Ready for Inspection SEAN WIRCH
Interior/Exterior Lathing 7/18/2025 Partial Approval JOHN HAYES
Wood Frame 7/18/2025 Corrections Issued JOHN HAYES
BUILDING-Rough-Frame 8/5/2025 Corrections Issued JOHN HAYES
Rough-Elec/Plmb/HVAC 8/5/2025 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 8/8/2025 Approved JOHN HAYES
Green Building Rough 8/8/2025 Approved JOHN HAYES
MERV13>=Rough 8/8/2025 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 8/8/2025 Approved JOHN HAYES
Verify Sprinkler Sign Off 8/8/2025 Approved JOHN HAYES
Insulation 8/14/2025 Conditional Approval SCOTT SOBEL
Insulation 8/20/2025 Corrections Issued JOHN HAYES
Shower Pan 8/20/2025 Corrections Issued JOHN HAYES
Insulation 8/25/2025 Approved SCOTT SOBEL
Shower Pan 8/25/2025 Approved SCOTT SOBEL
Drywall Nailing 9/5/2025 Approved JOHN HAYES
Interior/Exterior Lathing 10/21/2025 Partial Approval JEFFREY HARTLINE
Underground Mechanical 12/15/2025 Partial Approval JOHN HAYES
Final 5/13/2026 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 5/13/2026 Approved JOHN HAYES
Green Building Final 5/13/2026 Approved JOHN HAYES
MERV13>=Final 5/13/2026 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 5/13/2026 SGSOV Approved JOHN HAYES
Service/Power Release 5/13/2026 Not Ready for Inspection JOHN HAYES
Smoke Detectors 5/13/2026 Approved JOHN HAYES