10909-10909 1/2 S MAIN ST 90061
Certificate Information: 10909-10909 1/2 S MAIN ST 90061
- Application / Permit
- 24010-10000-03289
- Plan Check / Job No.
- B24LA16836
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX. fire sprinkler
- Permit Issued
- Issued on 1/24/2025
- Issuing Office
- Current Status
- CofO Issued on 5/1/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2024 | KHEDER ALRAZAA |
| Corrections Issued | 8/10/2024 | KHEDER ALRAZAA |
| Quality Review Completed | 8/16/2024 | KEN GILL |
| Building Plans Picked Up | 8/19/2024 | APPLICANT |
| Plan Check Approved | 1/22/2025 | KHEDER ALRAZAA |
| Issued | 1/24/2025 | APPLICANT |
| CofO in Progress | 5/1/2026 | JOSEPH MCGARRY |
| Permit Finaled | 5/1/2026 | ANSON MAGLASANG |
| CofO Issued | 5/1/2026 | ANSON MAGLASANG |
| Permit Finaled | 5/1/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 9/10/2024 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 9/10/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2024 | CELINA MORENO |
| Community Plan Implem. Overlay | Cleared | 9/18/2024 | EDGAR PASCUA |
| Construction near power lines | Cleared | 9/18/2024 | EDGAR PASCUA |
| Community Plan Implem. Overlay | Cleared | 9/20/2024 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 11/26/2024 | KURT CORRAL |
| Community Plan Implem. Overlay | Cleared | 12/6/2024 | ANACANY HURTADO |
| Community Plan Implem. Overlay | Cleared | 12/20/2024 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 12/20/2024 | ADRIAN SANCHEZ |
| Community Plan Implem. Overlay | Cleared | 12/30/2024 | COLLINS ALLAN |
Contact Information
| Contractor | Arrow Construction Co; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/5/2025 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 3/5/2025 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 3/21/2025 | Approved | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2025 | Partial Approval | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2025 | Corrections Issued | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2025 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 8/25/2025 | Approved | BEN MOLSTAD |
| HVAC-Rough | 9/3/2025 | Partial Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 9/3/2025 | Conditional Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 9/3/2025 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 9/8/2025 | No Access for Inspection | BEN MOLSTAD |
| HVAC-Rough | 9/9/2025 | Corrections Issued | BEN MOLSTAD |
| BUILDING-Rough-Frame | 10/17/2025 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 10/17/2025 | Corrections Issued | BEN MOLSTAD |
| Green Building Rough | 10/17/2025 | Approved | BEN MOLSTAD |
| HVAC-Rough | 10/17/2025 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 10/17/2025 | Approved | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 10/17/2025 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Rough | 10/20/2025 | Corrections Issued | BEN MOLSTAD |
| BUILDING-Rough-Frame | 10/21/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 10/21/2025 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 10/24/2025 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Rough | 10/24/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 10/24/2025 | Approved | BEN MOLSTAD |
| Insulation | 10/31/2025 | Corrections Issued | BEN MOLSTAD |
| BUILDING-Rough-Frame | 11/3/2025 | Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 11/3/2025 | Approved | BEN MOLSTAD |
| HVAC-Rough | 11/3/2025 | Approved | BEN MOLSTAD |
| Insulation | 11/3/2025 | Approved | BEN MOLSTAD |
| Drywall Nailing | 11/24/2025 | Corrections Issued | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 1/9/2026 | Corrections Issued | BEN MOLSTAD |
| Interior/Exterior Lathing | 1/13/2026 | Corrections Issued | BEN MOLSTAD |
| Interior/Exterior Lathing | 1/14/2026 | Approved | BEN MOLSTAD |
| Pre-Inspection | 1/14/2026 | Approved | BEN MOLSTAD |
| Underground Mechanical | 1/29/2026 | Corrections Issued | BEN MOLSTAD |
| Pre-Inspection | 1/30/2026 | Approved | BEN MOLSTAD |
| Underground Mechanical | 1/30/2026 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 4/9/2026 | Corrections Issued | BEN MOLSTAD |
| Final | 4/9/2026 | Corrections Issued | BEN MOLSTAD |
| HVAC-Final | 4/9/2026 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Final | 4/9/2026 | Corrections Issued | BEN MOLSTAD |
| Drywall Nailing | 4/14/2026 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 4/14/2026 | Corrections Issued | BEN MOLSTAD |
| Final | 4/14/2026 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 4/14/2026 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Final | 4/14/2026 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 4/14/2026 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 4/14/2026 | SGSOV Not Ready | BEN MOLSTAD |
| Service/Power Release | 4/14/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Smoke Detectors | 4/14/2026 | Approved | BEN MOLSTAD |
| Drywall Nailing | 4/24/2026 | Approved | BEN MOLSTAD |
| Final | 4/24/2026 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 4/24/2026 | Not Ready for Inspection | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 4/24/2026 | SGSOV Approved | BEN MOLSTAD |
| Service/Power Release | 4/24/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 4/27/2026 | OK to Issue CofO | JOSEPH MCGARRY |
| Green Building Final | 4/27/2026 | Approved | JOSEPH MCGARRY |
| Service/Power Release | 4/27/2026 | Approved | JOSEPH MCGARRY |