815-817 W G ST 90744

Certificate Information: 815-817 W G ST 90744

Application / Permit
24010-10000-03253
Plan Check / Job No.
B24LA16499
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 2-STORY DUPLEX
Permit Issued
Issued on 1/31/2025
Issuing Office
Metro
Current Status
CofO Issued on 12/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2024 APPLICANT
Assigned to Plan Check Engineer 8/8/2024 DANIEL YIP
Corrections Issued 8/12/2024 DANIEL YIP
Quality Review Completed 8/13/2024 KEN GILL
Building Plans Picked Up 8/20/2024 APPLICANT
Plan Check Approved 1/31/2025 DANIEL YIP
Issued 1/31/2025 APPLICANT
CofO in Progress 12/5/2025 EUGENE CASSIDY
Permit Finaled 12/10/2025 ANSON MAGLASANG
CofO Issued 12/10/2025 ANSON MAGLASANG
Permit Finaled 12/10/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 10/1/2024 ERIK BEASLEY
Permit Cleared 10/1/2024 ERIK BEASLEY
Roof/Waste drainage to street Cleared 10/1/2024 ERIK BEASLEY
"Q" conditions Cleared 10/2/2024 JAZMIN ROQUE
Clean Up Green Up Cleared 10/2/2024 JAZMIN ROQUE
ZA Case Cleared 10/2/2024 JAZMIN ROQUE
Eng Process Fee Ord 176,300 Cleared 10/21/2024 ERIK BEASLEY
Sewer availability Cleared 10/21/2024 ERIK BEASLEY
Frnt yard landscape/Water mgmt Cleared 10/22/2024 JAZMIN ROQUE
Trees in Parkway Cleared 10/28/2024 ADALBERTO VERA
Construction near power lines Cleared 11/19/2024 RIDWAN HARDY
Hydrant and Access approval Cleared 1/17/2025 RUEL COLE

Contact Information

Contractor F S Z Bros General Contractors Inc; Lic. No.: 794097-B 9036 IMPERIAL HWY      DOWNEY, CA 90242
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/10/2025 Not Ready for Inspection EUGENE CASSIDY
METHANE-Barrier 3/10/2025 Approved EUGENE CASSIDY
METHANE-Subgrade 3/10/2025 Approved EUGENE CASSIDY
PLUMBING-Rough 4/1/2025 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 4/7/2025 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 4/7/2025 Not Ready for Inspection EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 4/11/2025 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 4/11/2025 Partial Inspection EUGENE CASSIDY
PLUMBING-Rough 4/11/2025 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 5/23/2025 Partial Approval EUGENE CASSIDY
HVAC-Rough 6/11/2025 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 6/11/2025 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 6/26/2025 Approved JOHN KLARIN
ELECTRICAL-Rough 6/26/2025 Approved JOHN KLARIN
Green Building Rough 6/26/2025 Approved JOHN KLARIN
HVAC-Rough 6/26/2025 Approved JOHN KLARIN
METHANE-Rough 6/26/2025 Approved JOHN KLARIN
Verify Sprinkler Sign Off 6/26/2025 Approved JOHN KLARIN
Insulation 7/3/2025 Not Ready for Inspection EUGENE CASSIDY
Insulation 7/9/2025 Not Ready for Inspection EUGENE CASSIDY
Interior/Exterior Lathing 7/9/2025 Corrections Issued EUGENE CASSIDY
Insulation 7/15/2025 Approved EUGENE CASSIDY
Interior/Exterior Lathing 7/15/2025 Partial Approval EUGENE CASSIDY
Drywall Nailing 7/28/2025 Approved JOHN KLARIN
ELECTRICAL-Final 10/24/2025 Approved JOSEPH MCGARRY
HVAC-Final 10/24/2025 Approved JOSEPH MCGARRY
PLUMBING-Final 10/24/2025 Approved JOSEPH MCGARRY
ELECTRICAL-Final 11/17/2025 Approved EUGENE CASSIDY
Final 11/17/2025 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 11/17/2025 Approved EUGENE CASSIDY
Gas Test 11/17/2025 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 11/17/2025 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 11/17/2025 Approved EUGENE CASSIDY
PLUMBING-Final 11/17/2025 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 11/17/2025 SGSOV Not Required EUGENE CASSIDY
Service/Power Release 11/17/2025 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 11/17/2025 Approved EUGENE CASSIDY
ELECTRICAL-Final 11/20/2025 Approved EUGENE CASSIDY
Final 11/20/2025 Corrections Issued EUGENE CASSIDY
Gas Test 11/20/2025 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 11/20/2025 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 11/20/2025 Approved EUGENE CASSIDY
PLUMBING-Final 11/20/2025 Approved EUGENE CASSIDY
Service/Power Release 11/20/2025 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 12/5/2025 Approved EUGENE CASSIDY
Final 12/5/2025 OK to Issue CofO EUGENE CASSIDY
Green Building Final 12/5/2025 Approved EUGENE CASSIDY
HVAC-Final 12/5/2025 Approved EUGENE CASSIDY
PLUMBING-Final 12/5/2025 Approved EUGENE CASSIDY
Service/Power Release 12/5/2025 Approved EUGENE CASSIDY