21122 S DENKER AVE 90501

Certificate Information: 21122 S DENKER AVE 90501

Application / Permit
24010-10000-03247
Plan Check / Job No.
B24LA16457
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW TWO STORY DETACHED ACCESSORY DWELLING UNIT WITH ATTACHED TWO CAR GARAGE, COVERED PORCH & PATIO COVER ADU PER ORDINANCE LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 4/11/2025
Issuing Office
Current Status
Issued on 4/11/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/6/2024 APPLICANT
Assigned to Plan Check Engineer 8/22/2024 JAD BASMA
Corrections Issued 8/27/2024 JAD BASMA
Quality Review Completed 8/27/2024 GARO TELMI
Applicant returned to address corrections 10/30/2024 JAD BASMA
Plan Check Approved 4/4/2025 JAD BASMA
Issued 4/11/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/14/2025 XOCHITL ARQUIETA
Roof/Waste drainage to street Cleared 1/14/2025 XOCHITL ARQUIETA
Eng Process Fee Ord 176,300 Cleared 2/13/2025 JILVER MAZARIEGOS
Construction near power lines Cleared 3/4/2025 THERESA NGUYEN
Sewer availability Cleared 3/12/2025 XOCHITL ARQUIETA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/20/2025 Approved EUGENE CASSIDY
PLUMBING-Rough 6/24/2025 Partial Approval EUGENE CASSIDY
Sewer 6/24/2025 Approved EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 7/7/2025 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 7/7/2025 Not Ready for Inspection EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 7/22/2025 Approved EUGENE CASSIDY
Footing/Foundation/Slab 7/22/2025 Approved EUGENE CASSIDY
Grounding or Bonding 7/22/2025 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 9/4/2025 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/9/2025 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 11/12/2025 Approved EUGENE CASSIDY
ELECTRICAL-Rough 11/12/2025 Approved EUGENE CASSIDY
Gas Test 11/12/2025 Approved EUGENE CASSIDY
Green Building Rough 11/12/2025 Approved EUGENE CASSIDY
HVAC-Rough 11/12/2025 Approved EUGENE CASSIDY
PLUMBING-Rough 11/12/2025 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 11/12/2025 Approved EUGENE CASSIDY
Insulation 11/19/2025 Approved ANTHONY EGSON
Drywall Nailing 12/3/2025 Not Ready for Inspection EUGENE CASSIDY
Interior/Exterior Lathing 12/3/2025 Not Ready for Inspection EUGENE CASSIDY
Shower Pan 12/3/2025 Approved EUGENE CASSIDY
Drywall Nailing 12/5/2025 Approved EUGENE CASSIDY
Interior/Exterior Lathing 12/5/2025 Partial Approval EUGENE CASSIDY
Interior/Exterior Lathing 12/9/2025 Partial Approval ANSON MAGLASANG
Gas Test 2/26/2026 Approved EUGENE CASSIDY