9100 S FALMOUTH AVE 90293

Certificate Information: 9100 S FALMOUTH AVE 90293

Application / Permit
24010-10000-03212
Plan Check / Job No.
B24LA16153
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(16) Educational Institution
Work Description
EPLAN NEW TYPE IIIB (2) STORY LEARNING LAB WITH OFFICES, MULTI- PURPOSE ASSEMBLY, FIXED SEATING LARGE CLASSROOM, AND GRAB AND GO.
Permit Issued
Issued on 9/4/2025
Issuing Office
Current Status
Issued on 9/4/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/8/2024 APPLICANT
Assigned to Plan Check Engineer 8/15/2024 JOHNNY WU
Assigned to Zoning Architect 8/15/2024 ERIC ROMERO
Corrections Issued 8/27/2024 JOHNNY WU
Quality Review Completed 8/28/2024 RODOLFO ARIAS
Applicant returned to address corrections 10/23/2024 JOHNNY WU
Applicant returned to address corrections 11/14/2024 JOHNNY WU
Applicant returned to address corrections 11/18/2024 JOHNNY WU
Applicant returned to address corrections 1/14/2025 JOHNNY WU
Applicant returned to address corrections 6/13/2025 JOHNNY WU
Applicant returned to address corrections 8/11/2025 JOHNNY WU
Applicant returned to address corrections 8/20/2025 JOHNNY WU
Applicant returned to address corrections 8/21/2025 JOHNNY WU
Plan Check Approved 8/21/2025 JOHNNY WU
Plan Check Approved 8/26/2025 JOHNNY WU
Plan Check Approved 8/29/2025 JOHNNY WU
Issued 9/4/2025 APPLICANT

Permit Application Clearance Information

CPC Cleared 10/17/2024 JACQUELINE TORRES
CPC Cleared 10/17/2024 JACQUELINE TORRES
Highway dedication Cleared 10/22/2024 KIMBERLY HERNANDEZ
Miscellaneous Cleared 10/23/2024 JACQUELINE TORRES
Address approval Cleared 10/26/2024 KIMBERLY HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 10/27/2024 KIMBERLY HERNANDEZ
DAS Clearance Cleared 1/8/2025 ELIZABETH TOMS
Sewer availability Cleared 1/17/2025 KIMBERLY HERNANDEZ
Fire Marshal Fire Life Safety Cleared 3/7/2025 PEJMAN NOORI
Trees in Parkway Cleared 3/27/2025 ADALBERTO VERA
Green Code Cleared 5/2/2025 AARON COSTA
Low Impact Development (LID) Cleared 5/7/2025 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/12/2025 KIMBERLY HERNANDEZ
Hydrant and Access approval Cleared 5/16/2025 JOHN CONNEALLY
Driveway location Cleared 5/17/2025 EDUARDO HERMOSO
Internal circulation Cleared 5/17/2025 EDUARDO HERMOSO
Specific Plan Cleared 5/25/2025 EDUARDO HERMOSO
CPC Cleared 6/13/2025 DANIEL CORONADO
GPI Written Notices Cleared 6/13/2025 JOHNNY WU
Grading Pre-Inspection Cleared 6/13/2025 JOHNNY WU
Miscellaneous Cleared 6/13/2025 JESUS CISNEROS
Zoning Plan Check Cleared 7/25/2025 Jesse Arellano

Contact Information

Architect Hale,, Robert Graydon; Lic. No.: C11663 10328 CRESTA DR.      LOS ANGELES, CA 90064
Contractor Dpr Construction A General Partnership; Lic. No.: 1083716-B       ,
Engineer Crilly,, Joseph David; Lic. No.: S5974 PO BOX 249      PLACERVILLE, CO 81430
Engineer Galvez,, Jimmy Alexander; Lic. No.: C75568 654 N SPRING SUITE 200      LOS ANGELES, CA 90012
Engineer Low,, Yeng-Keong; Lic. No.: S4093 725 S FIGUEROA STREET 37TH FLOOR      LOS ANGELES, CA 90017

Inspector Information

NICK LAROCCA, (213) 473-2153 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/18/2025 Approved DERRICK SPENCER
Pre-Inspection 9/23/2025 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 9/26/2025 Partial Approval NICK LAROCCA
Excavation/Setback/Form/Re-Bar 10/3/2025 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 10/8/2025 Approved NICK LAROCCA
Excavation/Setback/Form/Re-Bar 10/8/2025 Partial Approval NICK LAROCCA
Excavation/Setback/Form/Re-Bar 11/24/2025 Partial Approval NICK LAROCCA
Excavation/Setback/Form/Re-Bar 1/14/2026 Partial Approval NICK LAROCCA
Pre-Inspection 1/14/2026 Approved NICK LAROCCA
Structural Steel Frame 1/14/2026 Not Ready for Inspection NICK LAROCCA
Deputy Reinf. Concrete 1/15/2026 Approved NICK LAROCCA
Deputy Steel/Welding 1/22/2026 Conditional Approval RICARDO ROBLES
Pre-Inspection 1/29/2026 Approved NICK LAROCCA
Pre-Inspection 2/20/2026 Approved NICK LAROCCA
Deputy Reinf. Concrete 3/10/2026 Approved NICK LAROCCA
Deputy Reinf. Concrete 3/11/2026 Partial Approval VASIL MIHALEV
Deputy Reinf. Concrete 3/12/2026 Approved NICK LAROCCA
Excavation/Setback/Form/Re-Bar 3/26/2026 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 3/27/2026 Approved NICK LAROCCA
Deputy Reinf. Masonry 4/2/2026 Approved NICK LAROCCA
Excavation/Setback/Form/Re-Bar 4/2/2026 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 4/3/2026 Approved NICK LAROCCA
Excavation/Setback/Form/Re-Bar 4/13/2026 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 4/14/2026 Approved NICK LAROCCA
Excavation/Setback/Form/Re-Bar 4/14/2026 Partial Approval NICK LAROCCA
Excavation/Setback/Form/Re-Bar 4/15/2026 Partial Approval NICK LAROCCA
Deputy Drilled-In Anchors 4/21/2026 Approved NICK LAROCCA
Deputy Reinf. Concrete 4/22/2026 Approved NICK LAROCCA
Deputy Drilled-In Anchors 4/23/2026 Approved NICK LAROCCA
Light Gage Steel Frame 5/12/2026 Partial Approval NICK LAROCCA
Light Gage Steel Frame 5/19/2026 Partial Approval NICK LAROCCA
Insulation 6/9/2026 Partial Approval NICK LAROCCA
Light Gage Steel Frame 6/9/2026 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 6/17/2026 Approved NICK LAROCCA
Deputy Drilled-In Anchors 6/23/2026 Approved NICK LAROCCA
Interior/Exterior Lathing 7/2/2026 Partial Approval DERRICK SPENCER
Insulation 7/13/2026 Partial Approval NICK LAROCCA
Interior/Exterior Lathing 7/13/2026 Partial Approval NICK LAROCCA
Light Gage Steel Frame 7/13/2026 Partial Approval NICK LAROCCA