14145 S AINSWORTH ST 90247

Certificate Information: 14145 S AINSWORTH ST 90247

Application / Permit
24010-10000-03202
Plan Check / Job No.
B24LA16004
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN New detached Accessory dwelling unit per LAMC 12.22 A.33(c) and (d), all work per WFPP
Permit Issued
Issued on 6/19/2025
Issuing Office
Current Status
Issued on 6/19/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/31/2024 APPLICANT
Assigned to Plan Check Engineer 8/5/2024 MOHAMMAD ESMAILI
Corrections Issued 8/6/2024 MOHAMMAD ESMAILI
Applicant returned to address corrections 12/12/2024 MOHAMMAD ESMAILI
Plan Check Approved 1/3/2025 OMAR GARNICA
Issued 6/19/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/21/2024 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 8/28/2024 ERIK BEASLEY
Roof/Waste drainage to street Cleared 9/19/2024 ERIK BEASLEY
Sewer availability Cleared 9/19/2024 ERIK BEASLEY
Construction within easement Cleared 11/20/2024 RIDWAN HARDY

Contact Information

Contractor Dhs Ventures Inc; Lic. No.: 1047699-B       ,
Contractor La Ccs; Lic. No.: 1047699-B       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Service/Power Release 7/24/2026   
Final 7/24/2026   

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/13/2025 Approved BEN MOLSTAD
Footing/Foundation/Slab 8/13/2025 Approved BEN MOLSTAD
METHANE-Barrier 8/13/2025 Approved BEN MOLSTAD
METHANE-Subgrade 8/13/2025 Approved BEN MOLSTAD
BUILDING-Rough-Frame 8/20/2025 Partial Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 8/20/2025 Not Ready for Inspection BEN MOLSTAD
Gas Test 8/27/2025 Partial Approval BEN MOLSTAD
PLUMBING-Rough 8/27/2025 Partial Approval BEN MOLSTAD
Insulation 8/28/2025 Partial Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 9/8/2025 Corrections Issued BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 9/9/2025 Partial Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 9/16/2025 Corrections Issued BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 9/18/2025 Partial Approval BEN MOLSTAD
ELECTRICAL-Rough 9/29/2025 Corrections Issued BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 9/29/2025 Partial Approval BEN MOLSTAD
HVAC-Rough 9/29/2025 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Rough 9/29/2025 Partial Approval BEN MOLSTAD
HVAC-Rough 10/2/2025 Not Ready for Inspection BEN MOLSTAD
Interior/Exterior Lathing 10/2/2025 Partial Approval BEN MOLSTAD
ELECTRICAL-Rough 10/17/2025 Corrections Issued BEN MOLSTAD
HVAC-Rough 10/17/2025 Corrections Issued BEN MOLSTAD
Wood Frame 10/17/2025 Not Ready for Inspection BEN MOLSTAD
Rough-Elec/Plmb/HVAC 10/22/2025 Corrections Issued BEN MOLSTAD
Wood Frame 10/22/2025 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 11/6/2025 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 11/6/2025 Approved BEN MOLSTAD
Green Building Rough 11/6/2025 Approved BEN MOLSTAD
HVAC-Rough 11/6/2025 Approved BEN MOLSTAD
MERV13>=Rough 11/6/2025 Approved BEN MOLSTAD
METHANE-Rough 11/6/2025 Approved BEN MOLSTAD
Verify Sprinkler Sign Off 11/6/2025 Approved BEN MOLSTAD
Insulation 11/18/2025 Corrections Issued BEN MOLSTAD
Insulation 11/21/2025 Corrections Issued BEN MOLSTAD
Insulation 11/25/2025 Approved BEN MOLSTAD
Drywall Nailing 12/1/2025 Approved EUGENE CASSIDY
Shower Pan 12/16/2025 Corrections Issued BEN MOLSTAD
Interior/Exterior Lathing 12/30/2025 Approved JOSEPH MCGARRY
Shower Pan 12/30/2025 Approved JOSEPH MCGARRY
Sewer 2/9/2026 Corrections Issued BEN MOLSTAD
Sewer 2/13/2026 Approved BEN MOLSTAD
Underground Mechanical 2/27/2026 Partial Approval DAVID FEILER
ELECTRICAL-Final 3/20/2026 Corrections Issued BEN MOLSTAD
BUILDING-Rough-Frame 3/24/2026 Approved BEN MOLSTAD
Final 3/24/2026 Corrections Issued BEN MOLSTAD
Green Building Final 3/24/2026 Corrections Issued BEN MOLSTAD
MERV13>=Final 3/24/2026 Not Ready for Inspection BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 3/24/2026 SGSOV Not Ready BEN MOLSTAD
Service/Power Release 3/24/2026 Not Ready for Inspection BEN MOLSTAD
Smoke Detectors 3/24/2026 Not Ready for Inspection BEN MOLSTAD
Final 4/14/2026 Corrections Issued BEN MOLSTAD
Green Building Final 4/14/2026 Not Ready for Inspection BEN MOLSTAD
MERV13>=Final 4/14/2026 Approved BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 4/14/2026 SGSOV Not Ready BEN MOLSTAD
Service/Power Release 4/14/2026 Not Ready for Inspection BEN MOLSTAD
Smoke Detectors 4/14/2026 Approved BEN MOLSTAD
Final 4/28/2026 Corrections Issued BEN MOLSTAD
Green Building Final 4/28/2026 Approved BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 4/28/2026 SGSOV Approved BEN MOLSTAD
Service/Power Release 4/28/2026 Not Ready for Inspection BEN MOLSTAD
Final 4/30/2026 Corrections Issued BEN MOLSTAD
Service/Power Release 4/30/2026 Not Ready for Inspection BEN MOLSTAD