3523 W 60TH ST 90043

Certificate Information: 3523 W 60TH ST 90043

Application / Permit
24010-10000-03192
Plan Check / Job No.
B24LA15835
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY 20'-6" X 20'-11" A.D.U. PER STATE LAW.
Permit Issued
Issued on 9/13/2024
Issuing Office
Metro
Current Status
CofO Issued on 8/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2024 APPLICANT
Assigned to Plan Check Engineer 8/1/2024 MINA HABILI
Corrections Issued 8/2/2024 MINA HABILI
Building Plans Picked Up 8/5/2024 APPLICANT
Applicant returned to address corrections 9/12/2024 CRISTINA SALAZAR
Plan Check Approved 9/13/2024 ALEXANDER JOO
Issued 9/13/2024 APPLICANT
CofO in Progress 8/14/2025 WAYNE REGESTER
Permit Finaled 8/15/2025 DEROLD HAUFF
CofO Issued 8/15/2025 DEROLD HAUFF
Permit Finaled 8/15/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/15/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 9/9/2024 TREVOR QUAN
Address approval Cleared 9/10/2024 TREVOR QUAN
Construction near power lines Cleared 9/12/2024 OSCAR CASTRO
Sewer availability Cleared 9/12/2024 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/18/2024 Not Ready for Inspection AMIR NAZARIAN
Grading Pre-Inspection 9/18/2024 Not Ready for Inspection AMIR NAZARIAN
PLUMBING-Rough 9/18/2024 Partial Approval AMIR NAZARIAN
Pre-Inspection 9/18/2024 Not Ready for Inspection AMIR NAZARIAN
Footing/Foundation/Slab 9/23/2024 Approved AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 10/2/2024 Approved AMIR NAZARIAN
Wood Frame 10/2/2024 Not Ready for Inspection AMIR NAZARIAN
ELECTRICAL-Final 10/8/2024 Approved JOSE MACIAS
PLUMBING-Final 10/8/2024 Conditional Approval JOSE MACIAS
ELECTRICAL-Rough 10/16/2024 Corrections Issued AMIR NAZARIAN
HVAC-Rough 10/16/2024 Corrections Issued AMIR NAZARIAN
PLUMBING-Rough 10/16/2024 Approved AMIR NAZARIAN
ELECTRICAL-Rough 10/18/2024 Approved AMIR NAZARIAN
HVAC-Rough 10/18/2024 Corrections Issued AMIR NAZARIAN
HVAC-Rough 10/22/2024 Corrections Issued AMIR NAZARIAN
HVAC-Rough 10/24/2024 Partial Approval CRAIG DAVIS
Insulation 10/24/2024 Corrections Issued CRAIG DAVIS
Interior/Exterior Lathing 10/24/2024 Approved CRAIG DAVIS
Rough-Elec/Plmb/HVAC 10/24/2024 Corrections Issued CRAIG DAVIS
Shower Pan 10/24/2024 Not Ready for Inspection CRAIG DAVIS
Underground Mechanical 10/24/2024 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 10/31/2024 Conditional Approval AMIR NAZARIAN
Drywall Nailing 10/31/2024 Approved AMIR NAZARIAN
HVAC-Rough 10/31/2024 Approved AMIR NAZARIAN
Insulation 10/31/2024 Approved AMIR NAZARIAN
Underground Mechanical 10/31/2024 Approved AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 11/5/2024 Approved JOSE MACIAS
BUILDING-Rough-Frame 12/18/2024 Approved MICHAEL LEWIS
Final 12/18/2024 Corrections Issued MICHAEL LEWIS
Green Building Final 12/18/2024 Approved MICHAEL LEWIS
Green Building Rough 12/18/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 12/18/2024 SGSOV Not Ready MICHAEL LEWIS
Service/Power Release 12/18/2024 Corrections Issued MICHAEL LEWIS
Smoke Detectors 12/18/2024 Corrections Issued MICHAEL LEWIS
Verify Sprinkler Sign Off 12/18/2024 Approved MICHAEL LEWIS
Special/Order Compliance 12/27/2024 Corrections Issued AMIR NAZARIAN
Final 1/27/2025 Corrections Issued MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 1/27/2025 SGSOV Approved MICHAEL LEWIS
Service/Power Release 1/27/2025 Not Required MICHAEL LEWIS
Smoke Detectors 1/27/2025 Approved MICHAEL LEWIS
Final 3/17/2025 Corrections Issued JOSE MACIAS
Final 4/7/2025 Not Ready for Inspection WAYNE REGESTER
Final 4/10/2025 Partial Approval WAYNE REGESTER
Final 4/21/2025 Not Ready for Inspection WAYNE REGESTER
Final 4/28/2025 Partial Approval WAYNE REGESTER
Final 8/13/2025 OK to Issue CofO WAYNE REGESTER