3523 W 60TH ST 90043
Certificate Information: 3523 W 60TH ST 90043
- Application / Permit
- 24010-10000-03192
- Plan Check / Job No.
- B24LA15835
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY 20'-6" X 20'-11" A.D.U. PER STATE LAW.
- Permit Issued
- Issued on 9/13/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2024 | MINA HABILI |
| Corrections Issued | 8/2/2024 | MINA HABILI |
| Building Plans Picked Up | 8/5/2024 | APPLICANT |
| Applicant returned to address corrections | 9/12/2024 | CRISTINA SALAZAR |
| Plan Check Approved | 9/13/2024 | ALEXANDER JOO |
| Issued | 9/13/2024 | APPLICANT |
| CofO in Progress | 8/14/2025 | WAYNE REGESTER |
| Permit Finaled | 8/15/2025 | DEROLD HAUFF |
| CofO Issued | 8/15/2025 | DEROLD HAUFF |
| Permit Finaled | 8/15/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/15/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2024 | TREVOR QUAN |
| Address approval | Cleared | 9/10/2024 | TREVOR QUAN |
| Construction near power lines | Cleared | 9/12/2024 | OSCAR CASTRO |
| Sewer availability | Cleared | 9/12/2024 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/18/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Grading Pre-Inspection | 9/18/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| PLUMBING-Rough | 9/18/2024 | Partial Approval | AMIR NAZARIAN |
| Pre-Inspection | 9/18/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Footing/Foundation/Slab | 9/23/2024 | Approved | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2024 | Approved | AMIR NAZARIAN |
| Wood Frame | 10/2/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| ELECTRICAL-Final | 10/8/2024 | Approved | JOSE MACIAS |
| PLUMBING-Final | 10/8/2024 | Conditional Approval | JOSE MACIAS |
| ELECTRICAL-Rough | 10/16/2024 | Corrections Issued | AMIR NAZARIAN |
| HVAC-Rough | 10/16/2024 | Corrections Issued | AMIR NAZARIAN |
| PLUMBING-Rough | 10/16/2024 | Approved | AMIR NAZARIAN |
| ELECTRICAL-Rough | 10/18/2024 | Approved | AMIR NAZARIAN |
| HVAC-Rough | 10/18/2024 | Corrections Issued | AMIR NAZARIAN |
| HVAC-Rough | 10/22/2024 | Corrections Issued | AMIR NAZARIAN |
| HVAC-Rough | 10/24/2024 | Partial Approval | CRAIG DAVIS |
| Insulation | 10/24/2024 | Corrections Issued | CRAIG DAVIS |
| Interior/Exterior Lathing | 10/24/2024 | Approved | CRAIG DAVIS |
| Rough-Elec/Plmb/HVAC | 10/24/2024 | Corrections Issued | CRAIG DAVIS |
| Shower Pan | 10/24/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Underground Mechanical | 10/24/2024 | Corrections Issued | CRAIG DAVIS |
| BUILDING-Rough-Frame | 10/31/2024 | Conditional Approval | AMIR NAZARIAN |
| Drywall Nailing | 10/31/2024 | Approved | AMIR NAZARIAN |
| HVAC-Rough | 10/31/2024 | Approved | AMIR NAZARIAN |
| Insulation | 10/31/2024 | Approved | AMIR NAZARIAN |
| Underground Mechanical | 10/31/2024 | Approved | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 12/18/2024 | Approved | MICHAEL LEWIS |
| Final | 12/18/2024 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 12/18/2024 | Approved | MICHAEL LEWIS |
| Green Building Rough | 12/18/2024 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 12/18/2024 | SGSOV Not Ready | MICHAEL LEWIS |
| Service/Power Release | 12/18/2024 | Corrections Issued | MICHAEL LEWIS |
| Smoke Detectors | 12/18/2024 | Corrections Issued | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 12/18/2024 | Approved | MICHAEL LEWIS |
| Special/Order Compliance | 12/27/2024 | Corrections Issued | AMIR NAZARIAN |
| Final | 1/27/2025 | Corrections Issued | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 1/27/2025 | SGSOV Approved | MICHAEL LEWIS |
| Service/Power Release | 1/27/2025 | Not Required | MICHAEL LEWIS |
| Smoke Detectors | 1/27/2025 | Approved | MICHAEL LEWIS |
| Final | 3/17/2025 | Corrections Issued | JOSE MACIAS |
| Final | 4/7/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 4/10/2025 | Partial Approval | WAYNE REGESTER |
| Final | 4/21/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 4/28/2025 | Partial Approval | WAYNE REGESTER |
| Final | 8/13/2025 | OK to Issue CofO | WAYNE REGESTER |