1724 S VIRGINIA ROAD 90019
Certificate Information: 1724 S VIRGINIA ROAD 90019
- Application / Permit
- 24010-10000-03140
- Plan Check / Job No.
- B24LA15381
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: (N) DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d). WORK PER ENGINEERED DESIGN.
- Permit Issued
- Issued on 10/18/2024
- Issuing Office
- Current Status
- CofO Issued on 10/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2024 | OMAR GARNICA |
| Corrections Issued | 8/6/2024 | OMAR GARNICA |
| Applicant returned to address corrections | 8/15/2024 | OMAR GARNICA |
| Applicant returned to address corrections | 8/28/2024 | OMAR GARNICA |
| Plan Check Approved | 9/12/2024 | OMAR GARNICA |
| Issued | 10/18/2024 | APPLICANT |
| CofO in Progress | 10/1/2025 | JUSTIN HAWLEY |
| Permit Finaled | 10/1/2025 | DEROLD HAUFF |
| CofO Issued | 10/1/2025 | DEROLD HAUFF |
| Permit Finaled | 10/1/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 8/6/2024 | DAMIAN GATTO |
| Address approval | Cleared | 8/16/2024 | JOSE HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 8/16/2024 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/20/2024 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 8/20/2024 | JOSE HERNANDEZ |
| Construction near power lines | Cleared | 9/9/2024 | TINA MIRANDA |
Contact Information
| Contractor | Liel Construction Inc; Lic. No.: 929105-B | , |
| Engineer | Mustafa,, Ansar; Lic. No.: NA88004 | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/1/2024 | Corrections Issued | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 11/5/2024 | Corrections Issued | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 11/14/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2024 | Partial Approval | JUSTIN HAWLEY |
| PLUMBING-Rough | 11/27/2024 | Partial Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2024 | Partial Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2024 | Partial Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 12/20/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 12/20/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Green Building Rough | 12/20/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| HVAC-Rough | 12/20/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| PLUMBING-Rough | 12/20/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Special/Order Compliance | 12/20/2024 | Corrections Issued | JUSTIN HAWLEY |
| Verify Sprinkler Sign Off | 12/20/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2024 | Approved | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 12/27/2024 | Corrections Issued | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 12/31/2024 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 12/31/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 12/31/2024 | Approved | JUSTIN HAWLEY |
| Insulation | 2/11/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 2/11/2025 | Partial Approval | ALEX COLIN |
| Drywall Nailing | 2/13/2025 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 2/13/2025 | Approved | JUSTIN HAWLEY |
| Wood Frame | 2/25/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 3/5/2025 | Approved | LUIS CASTRO |
| Gas Test | 6/13/2025 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 6/13/2025 | Partial Approval | JUSTIN HAWLEY |
| Final | 9/17/2025 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Final | 9/17/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 9/17/2025 | SGSOV Not Required | JUSTIN HAWLEY |
| Smoke Detectors | 9/17/2025 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 9/30/2025 | Approved | JUSTIN HAWLEY |
| Final | 9/30/2025 | OK to Issue CofO | JUSTIN HAWLEY |
| Green Building Final | 9/30/2025 | Approved | JUSTIN HAWLEY |
| HVAC-Final | 9/30/2025 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 9/30/2025 | Approved | JUSTIN HAWLEY |