1350 1/2 S REDONDO BLVD 90019

Certificate Information: 1350 1/2 S REDONDO BLVD 90019

Application / Permit
24010-10000-03125
Plan Check / Job No.
B24LA15290
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
32'-2 7/8" X 24'-4" IRREGULAR SHAPED ADDITION AND CONVERSION OF DETACHED GARAGE INTO ACCESSORY DWELLING UNIT - PER ENGINEER
Permit Issued
Issued on 2/6/2025
Issuing Office
Current Status
CofO Issued on 2/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2024 APPLICANT
Assigned to Plan Check Engineer 7/31/2024 DANIEL ABRAMYAN
Corrections Issued 8/1/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 10/4/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 10/19/2024 DANIEL ABRAMYAN
Plan Check Approved 11/21/2024 DANIEL ABRAMYAN
Issued 2/6/2025 APPLICANT
CofO in Progress 2/24/2026 JUSTIN HAWLEY
CofO Issued 2/26/2026 DEROLD HAUFF
Permit Finaled 2/26/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/12/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 10/1/2024 CHRISTINA BRACO
Sewer availability Cleared 10/1/2024 CHRISTINA BRACO
Roof/Waste drainage to street Cleared 10/3/2024 CHRISTINA BRACO

Contact Information

Contractor Owner-Builder       ,
Engineer Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 2160 PARNELL WY      ALTADENA, CA 91001

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/11/2025 Approved ENRIQUE MIRELES
Deputy Drilled-In Anchors 4/15/2025 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 4/18/2025 Corrections Issued ENRIQUE MIRELES
METHANE-Barrier 4/18/2025 Not Ready for Inspection ENRIQUE MIRELES
METHANE-Subgrade 4/18/2025 Not Ready for Inspection ENRIQUE MIRELES
Deputy Methane Barrier 5/27/2025 Conditional Approval JOSE MACIAS
BUILDING-Rough-Frame 9/30/2025 Corrections Issued JUSTIN HAWLEY
Green Building Rough 9/30/2025 Not Ready for Inspection JUSTIN HAWLEY
METHANE-Rough 9/30/2025 Approved JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 9/30/2025 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 10/6/2025 Approved ARTHUR NEGRETE
Green Building Rough 10/6/2025 Approved ARTHUR NEGRETE
Insulation 10/6/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 10/24/2025 Approved DEVON JACKSON
ELECTRICAL-Final 1/14/2026 Corrections Issued JUSTIN HAWLEY
Drywall Nailing 1/30/2026 Approved ENRIQUE MIRELES
Final 1/30/2026 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 1/30/2026 Approved ENRIQUE MIRELES
Green Building Final 1/30/2026 Approved ENRIQUE MIRELES
METHANE-Barrier 1/30/2026 Approved ENRIQUE MIRELES
METHANE-Subgrade 1/30/2026 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 1/30/2026 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 1/30/2026 Approved ENRIQUE MIRELES
ELECTRICAL-Final 2/24/2026 Approved JUSTIN HAWLEY
Final 2/24/2026 OK to Issue CofO JUSTIN HAWLEY
HVAC-Final 2/24/2026 Approved JUSTIN HAWLEY
PLUMBING-Final 2/24/2026 Approved JUSTIN HAWLEY