2933 S OAKHURST AVE 90034

Certificate Information: 2933 S OAKHURST AVE 90034

Application / Permit
24010-10000-03107
Plan Check / Job No.
B24LA15159
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached ADU
Permit Issued
Issued on 12/9/2024
Issuing Office
Current Status
CofO Issued on 7/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2024 APPLICANT
Assigned to Plan Check Engineer 7/29/2024 SERGIO MUNIZ
Corrections Issued 7/30/2024 SERGIO MUNIZ
Applicant returned to address corrections 9/10/2024 SERGIO MUNIZ
Applicant returned to address corrections 10/22/2024 SERGIO MUNIZ
Applicant returned to address corrections 11/14/2024 SERGIO MUNIZ
Applicant returned to address corrections 11/26/2024 ALEC MOUSAKHANIAN
Plan Check Approved 12/3/2024 ALEC MOUSAKHANIAN
Issued 12/9/2024 APPLICANT
CofO in Progress 7/18/2025 ARAM AVEDISIAN
Permit Finaled 7/21/2025 RICHARD STEINBACH
CofO Issued 7/21/2025 RICHARD STEINBACH
Permit Finaled 7/21/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 9/3/2024 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 9/5/2024 HISASHI KOBAYAKAWA
Sewer availability Cleared 9/5/2024 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 9/16/2024 HISASHI KOBAYAKAWA
Construction near power lines Cleared 11/7/2024 RIDWAN HARDY
ZA Case Cleared 11/7/2024 NOAH MCCOY
ZA Case Cleared 11/7/2024 NOAH MCCOY
Grading Pre-Inspection Cleared 12/2/2024 VASIL MIHALEV

Contact Information

Contractor Bichai Construction Corporation; Lic. No.: 1083309-B       ,
Engineer Ramos,, Victor; Lic. No.: C86568 4823 ALMAGUER AVE      GUADALUPE, CA 93434

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/16/2025 Partial Inspection ASHLEY THOMPSON
PLUMBING-Rough 2/26/2025 Partial Approval EVAN COOPER
Sewer 2/26/2025 Partial Approval EVAN COOPER
ELECTRICAL-Rough 2/27/2025 Partial Approval ASHLEY THOMPSON
Sewer 2/27/2025 Corrections Issued ASHLEY THOMPSON
Footing/Foundation/Slab 3/12/2025 Corrections Issued ASHLEY THOMPSON
Deputy Reinf. Concrete 3/19/2025 Conditional Approval ASHLEY THOMPSON
Footing/Foundation/Slab 3/19/2025 Approved ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 4/2/2025 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 4/29/2025 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Rough 4/29/2025 Corrections Issued ASHLEY THOMPSON
Green Building Rough 4/29/2025 Not Ready for Inspection ASHLEY THOMPSON
HVAC-Rough 4/29/2025 Corrections Issued ASHLEY THOMPSON
PLUMBING-Rough 4/29/2025 Corrections Issued ASHLEY THOMPSON
Verify Sprinkler Sign Off 4/29/2025 Not Ready for Inspection ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 4/30/2025 Corrections Issued ASHLEY THOMPSON
Deputy Wood Construction 5/1/2025 Conditional Approval ASHLEY THOMPSON
BUILDING-Rough-Frame 5/2/2025 Corrections Issued ASHLEY THOMPSON
ELECTRICAL-Rough 5/2/2025 Approved ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 5/2/2025 Partial Approval ASHLEY THOMPSON
Green Building Rough 5/2/2025 Not Ready for Inspection ASHLEY THOMPSON
PLUMBING-Rough 5/2/2025 Approved ASHLEY THOMPSON
Verify Sprinkler Sign Off 5/2/2025 Approved ASHLEY THOMPSON
HVAC-Rough 5/7/2025 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 5/12/2025 Approved STEPHANIE SWANSON
Green Building Rough 5/12/2025 Approved STEPHANIE SWANSON
HVAC-Rough 5/12/2025 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 5/12/2025 Approved STEPHANIE SWANSON
Insulation 5/16/2025 Approved ASHLEY THOMPSON
Drywall Nailing 5/21/2025 Corrections Issued ASHLEY THOMPSON
Drywall Nailing 5/23/2025 Approved ASHLEY THOMPSON
Shower Pan 5/23/2025 Corrections Issued ASHLEY THOMPSON
Interior/Exterior Lathing 6/2/2025 Approved JAYLIN GRAVITTE
Shower Pan 6/2/2025 Approved JAYLIN GRAVITTE
SGSOV-Seismic Gas S/O Valve 7/14/2025 SGSOV Not Ready EVAN COOPER
Final 7/15/2025 Corrections Issued ASHLEY THOMPSON
Green Building Final 7/15/2025 Approved ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 7/15/2025 SGSOV Not Required ASHLEY THOMPSON
Service/Power Release 7/15/2025 Not Ready for Inspection ASHLEY THOMPSON
Smoke Detectors 7/15/2025 Approved ASHLEY THOMPSON
ELECTRICAL-Final 7/18/2025 Approved ARAM AVEDISIAN
Final 7/18/2025 OK to Issue CofO ARAM AVEDISIAN
HVAC-Final 7/18/2025 Approved ARAM AVEDISIAN
PLUMBING-Final 7/18/2025 Approved ARAM AVEDISIAN