313-313 1/2 W 56TH ST 90037
Certificate Information: 313-313 1/2 W 56TH ST 90037
- Application / Permit
- 24010-10000-03097
- Plan Check / Job No.
- B24LA15107
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW TWO STORY DUPLEX (FRONT LOT) -BLDG SPRINKLERED THRU-OUT
- Permit Issued
- Issued on 12/26/2024
- Issuing Office
- Current Status
- CofO Issued on 8/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2024 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 8/6/2024 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 8/9/2024 | KEN GILL |
| Building Plans Picked Up | 8/16/2024 | APPLICANT |
| Plan Check Approved | 12/12/2024 | MAHNAZ NOURHASHEMI |
| Issued | 12/26/2024 | APPLICANT |
| CofO in Progress | 8/14/2025 | MICHAEL LEWIS |
| Permit Finaled | 8/15/2025 | DEROLD HAUFF |
| CofO Issued | 8/15/2025 | DEROLD HAUFF |
| Permit Finaled | 8/15/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/9/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/18/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 9/18/2024 | JUSTIN BICOL |
| Low Impact Development (LID) | Cleared | 9/19/2024 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 10/8/2024 | JUSTIN BICOL |
| Frnt yard landscape/Water mgmt | Cleared | 10/16/2024 | FIPE LEILUA |
| ZI | Cleared | 10/22/2024 | YASMINE BASHIRI |
| Hydrant and Access approval | Cleared | 11/14/2024 | JERRY KAO |
Contact Information
| Contractor | Arrow Construction Co; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/30/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 12/30/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 1/2/2025 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 1/3/2025 | Approved | ENRIQUE MIRELES |
| Deputy Wood Construction | 1/14/2025 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 1/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 3/6/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/19/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/20/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 3/21/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 3/21/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 3/25/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 3/25/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 3/25/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 3/26/2025 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 3/26/2025 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 3/27/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Wood Frame | 3/27/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/28/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 3/28/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| MERV13>=Rough | 3/28/2025 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 3/28/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/3/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/7/2025 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 4/7/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 4/7/2025 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 4/7/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 4/9/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 4/15/2025 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 4/15/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 4/17/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 5/8/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 5/9/2025 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 6/16/2025 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 6/17/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 8/7/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 8/7/2025 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/7/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/11/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 8/11/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/11/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 8/11/2025 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 8/11/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/12/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 8/12/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 8/12/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| MERV13>=Final | 8/12/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/12/2025 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 8/12/2025 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 8/12/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/14/2025 | OK to Issue CofO | MICHAEL LEWIS |
| HVAC-Final | 8/14/2025 | Approved | MICHAEL LEWIS |
| MERV13>=Final | 8/14/2025 | Approved | MICHAEL LEWIS |