2143 N GOWER ST 90068

Certificate Information: 2143 N GOWER ST 90068

Application / Permit
24010-10000-03077
Plan Check / Job No.
B24LA14972
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
2ND FLOOR REMODEL IN (E) 2-STORY DUPLEX WITH NEW 2ND FLOOR BALCONY AND ROOFTOP DECK ABOVE FIRST FLOOR.
Permit Issued
Issued on 10/23/2024
Issuing Office
Current Status
Issued on 10/23/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/25/2024 APPLICANT
Assigned to Plan Check Engineer 8/15/2024 SERGIO GUTIERREZ
Corrections Issued 8/29/2024 SERGIO GUTIERREZ
Quality Review Completed 8/30/2024 RODOLFO ARIAS
Plan Check Approved 10/23/2024 SERGIO GUTIERREZ
Issued 10/23/2024 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/4/2024 DAVID LOPEZ
Sewer availability Cleared 9/4/2024 DAVID LOPEZ
ZA Case Cleared 9/5/2024 JAZMIN ROQUE
Eng Process Fee Ord 176,300 Cleared 9/9/2024 DAVID LOPEZ
Tenant Habitability Plan Cleared 9/30/2024 RICARDO BOHORQUEZ
Grading Pre-Inspection Cleared 10/23/2024 SERGIO GUTIERREZ

Contact Information

Contractor The Fix Construction Co; Lic. No.: 1049919-B       ,
Contractor The Fix Inc; Lic. No.: 1049919-B       ,
Engineer Melchor,, Oscar Elias; Lic. No.: NA76828       ,

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/15/2025 Partial Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 9/25/2025 Partial Approval CRAIG VAUGHAN
HVAC-Rough 9/25/2025 Approved CRAIG VAUGHAN
PLUMBING-Rough 9/25/2025 Approved CRAIG VAUGHAN
Wood Frame 9/30/2025 Partial Approval CRAIG VAUGHAN
Insulation 10/3/2025 Approved CRAIG VAUGHAN
Shower Pan 10/3/2025 Approved CRAIG VAUGHAN
Drywall Nailing 10/16/2025 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 10/16/2025 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 2/13/2026 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Final 2/13/2026 Corrections Issued CRAIG VAUGHAN
Final 2/13/2026 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 2/13/2026 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Final 2/13/2026 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 2/13/2026 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 2/13/2026 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 2/13/2026 Approved CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 3/2/2026 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 3/2/2026 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 4/16/2026 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 4/16/2026 Approved CRAIG VAUGHAN