127-129 W 93RD ST 90003

Certificate Information: 127-129 W 93RD ST 90003

Application / Permit
24010-10000-03073
Plan Check / Job No.
B24LA14902
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
EPLAN. NEW 2-STORY DUPLEX WITH ATTACHED GARAGES. EQUIPPED WITH NFPA13D FIRE SPRINKLERS THROUGH OUT.
Permit Issued
Issued on 3/11/2025
Issuing Office
Current Status
CofO Issued on 9/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2024 APPLICANT
Assigned to Plan Check Engineer 8/1/2024 ADRIANA LOPEZ
Corrections Issued 8/3/2024 ADRIANA LOPEZ
Quality Review Completed 8/14/2024 SINA KHOSRAVI
Plan Check Approved 2/26/2025 ADRIANA LOPEZ
Issued 3/11/2025 APPLICANT
CofO in Progress 9/10/2025 JOHN QUINTANILLA
Permit Finaled 9/13/2025 DEROLD HAUFF
Permit Finaled 9/13/2025 DEROLD HAUFF
CofO Issued 9/13/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/21/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 9/3/2024 WALLIE JONG
Low Impact Development (LID) Cleared 9/12/2024 ORVAL HERNANDEZ-MARCI
SB8 RUD Cleared 10/10/2024 BLAKE BOULIGNY
Miscellaneous Cleared 11/25/2024 DAVID URITA
Miscellaneous Cleared 11/25/2024 DAVID URITA
Trees in Parkway Cleared 11/25/2024 MIGUEL ORNELAS
Permit Cleared 12/26/2024 WALLIE JONG
Roof/Waste drainage to street Cleared 12/26/2024 WALLIE JONG
Hydrant and Access approval Cleared 1/9/2025 GILBERT URREA
Sewer availability Cleared 1/16/2025 CHRISTINA BRACO
Construction near power lines Cleared 1/27/2025 RIDWAN HARDY
Construction within easement Cleared 1/27/2025 RIDWAN HARDY

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/11/2025 Approved JOHN QUINTANILLA
Sewer 4/24/2025 Approved JOHN QUINTANILLA
Underground Mechanical 4/24/2025 Approved JOHN QUINTANILLA
Wood Frame 4/24/2025 Partial Approval JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 4/25/2025 Approved JOHN QUINTANILLA
Insulation 4/25/2025 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 5/1/2025 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 6/5/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 6/13/2025 Approved JOHN QUINTANILLA
HVAC-Rough 6/13/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 6/16/2025 Partial Approval LUIS CASTRO
Green Building Rough 6/16/2025 Partial Approval LUIS CASTRO
PLUMBING-Rough 6/16/2025 Approved LUIS CASTRO
Verify Sprinkler Sign Off 6/16/2025 Approved LUIS CASTRO
Insulation 6/18/2025 Approved BRENDAN MORELLI
Interior/Exterior Lathing 6/25/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Final 9/2/2025 Corrections Issued JOHN QUINTANILLA
HVAC-Final 9/2/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 9/3/2025 Approved BARRY HACHE
Drywall Nailing 9/3/2025 Approved BARRY HACHE
ELECTRICAL-Final 9/3/2025 Not Ready for Inspection BARRY HACHE
Green Building Rough 9/3/2025 Approved BARRY HACHE
PLUMBING-Final 9/3/2025 Approved BARRY HACHE
ELECTRICAL-Final 9/5/2025 Approved JOHN QUINTANILLA
PLUMBING-Final 9/5/2025 Approved JOHN QUINTANILLA
Service/Power Release 9/5/2025 Approved JOHN QUINTANILLA
Final 9/9/2025 OK to Issue CofO JOHN QUINTANILLA
Green Building Final 9/9/2025 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 9/9/2025 SGSOV Not Required JOHN QUINTANILLA
Smoke Detectors 9/9/2025 Approved JOHN QUINTANILLA