6117 S HARCOURT AVE 90043

Certificate Information: 6117 S HARCOURT AVE 90043

Application / Permit
24010-10000-03041
Plan Check / Job No.
B24LA14542
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 1 STORY ADU PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 8/21/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/23/2024 APPLICANT
Assigned to Plan Check Engineer 7/25/2024 SAMUEL GONZALEZ
Corrections Issued 7/26/2024 SAMUEL GONZALEZ
Building Plans Picked Up 8/9/2024 APPLICANT
Plan Check Approved 8/16/2024 JOSEPH RAFOLS
Issued 8/21/2024 APPLICANT
CofO in Progress 1/23/2025 NICHOLAS LOPEZ
Permit Finaled 1/28/2025 DEROLD HAUFF
CofO Issued 1/28/2025 DEROLD HAUFF
Permit Finaled 1/28/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/14/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 8/14/2024 JUSTIN BICOL
Roof/Waste drainage to street Cleared 8/14/2024 JUSTIN BICOL
Sewer availability Cleared 8/14/2024 JUSTIN BICOL

Contact Information

Contractor R M C Construction Electric Inc; Lic. No.: 961296-B 6115 S HARCOURT AVENUE      LOS ANGELES, CA 90043
Engineer Wong,, Jim C; Lic. No.: C69393 1822 E ROUTE 66, SUITE A, PO BOX 328      GLENDORA, CA 91740

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/5/2024 Corrections Issued AMIR NAZARIAN
Sewer 9/24/2024 Approved MICHAEL LEWIS
Underground Mechanical 9/24/2024 Approved MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 10/1/2024 Approved AMIR NAZARIAN
Footing/Foundation/Slab 10/1/2024 Approved AMIR NAZARIAN
Deputy Drilled-In Anchors 10/18/2024 No Access for Inspection AMIR NAZARIAN
ELECTRICAL-Rough 10/22/2024 Conditional Approval AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 10/22/2024 Partial Approval AMIR NAZARIAN
BUILDING-Rough-Frame 10/31/2024 Conditional Approval AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 10/31/2024 Approved AMIR NAZARIAN
HVAC-Rough 10/31/2024 Approved AMIR NAZARIAN
PLUMBING-Rough 10/31/2024 Approved AMIR NAZARIAN
Pre-Inspection 10/31/2024 Approved AMIR NAZARIAN
Interior/Exterior Lathing 11/5/2024 Corrections Issued ALEX COLIN
Insulation 11/14/2024 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 11/14/2024 Approved JOHN QUINTANILLA
Service/Power Release 11/14/2024 Not Ready for Inspection JOHN QUINTANILLA
Drywall Nailing 11/18/2024 Approved ALEX COLIN
Green Building Rough 11/18/2024 Approved ALEX COLIN
BUILDING-Rough-Frame 1/23/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Final 1/23/2025 Approved NICHOLAS LOPEZ
Final 1/23/2025 OK to Issue CofO NICHOLAS LOPEZ
Green Building Final 1/23/2025 Approved NICHOLAS LOPEZ
HVAC-Final 1/23/2025 Approved NICHOLAS LOPEZ
PLUMBING-Final 1/23/2025 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 1/23/2025 SGSOV No Gas NICHOLAS LOPEZ
Service/Power Release 1/23/2025 Approved NICHOLAS LOPEZ
Smoke Detectors 1/23/2025 Approved NICHOLAS LOPEZ
Verify Sprinkler Sign Off 1/23/2025 Approved NICHOLAS LOPEZ