6117 S HARCOURT AVE 90043
Certificate Information: 6117 S HARCOURT AVE 90043
- Application / Permit
- 24010-10000-03041
- Plan Check / Job No.
- B24LA14542
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 1 STORY ADU PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 8/21/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2024 | SAMUEL GONZALEZ |
| Corrections Issued | 7/26/2024 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 8/9/2024 | APPLICANT |
| Plan Check Approved | 8/16/2024 | JOSEPH RAFOLS |
| Issued | 8/21/2024 | APPLICANT |
| CofO in Progress | 1/23/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 1/28/2025 | DEROLD HAUFF |
| CofO Issued | 1/28/2025 | DEROLD HAUFF |
| Permit Finaled | 1/28/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/14/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 8/14/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 8/14/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 8/14/2024 | JUSTIN BICOL |
Contact Information
| Contractor | R M C Construction Electric Inc; Lic. No.: 961296-B | 6115 S HARCOURT AVENUE LOS ANGELES, CA 90043 |
| Engineer | Wong,, Jim C; Lic. No.: C69393 | 1822 E ROUTE 66, SUITE A, PO BOX 328 GLENDORA, CA 91740 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/5/2024 | Corrections Issued | AMIR NAZARIAN |
| Sewer | 9/24/2024 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 9/24/2024 | Approved | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 10/1/2024 | Approved | AMIR NAZARIAN |
| Footing/Foundation/Slab | 10/1/2024 | Approved | AMIR NAZARIAN |
| Deputy Drilled-In Anchors | 10/18/2024 | No Access for Inspection | AMIR NAZARIAN |
| ELECTRICAL-Rough | 10/22/2024 | Conditional Approval | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2024 | Partial Approval | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 10/31/2024 | Conditional Approval | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2024 | Approved | AMIR NAZARIAN |
| HVAC-Rough | 10/31/2024 | Approved | AMIR NAZARIAN |
| PLUMBING-Rough | 10/31/2024 | Approved | AMIR NAZARIAN |
| Pre-Inspection | 10/31/2024 | Approved | AMIR NAZARIAN |
| Interior/Exterior Lathing | 11/5/2024 | Corrections Issued | ALEX COLIN |
| Insulation | 11/14/2024 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 11/14/2024 | Approved | JOHN QUINTANILLA |
| Service/Power Release | 11/14/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| Drywall Nailing | 11/18/2024 | Approved | ALEX COLIN |
| Green Building Rough | 11/18/2024 | Approved | ALEX COLIN |
| BUILDING-Rough-Frame | 1/23/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 1/23/2025 | Approved | NICHOLAS LOPEZ |
| Final | 1/23/2025 | OK to Issue CofO | NICHOLAS LOPEZ |
| Green Building Final | 1/23/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Final | 1/23/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Final | 1/23/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 1/23/2025 | SGSOV No Gas | NICHOLAS LOPEZ |
| Service/Power Release | 1/23/2025 | Approved | NICHOLAS LOPEZ |
| Smoke Detectors | 1/23/2025 | Approved | NICHOLAS LOPEZ |
| Verify Sprinkler Sign Off | 1/23/2025 | Approved | NICHOLAS LOPEZ |