1646 W 213TH ST 90501

Certificate Information: 1646 W 213TH ST 90501

Application / Permit
24010-10000-02962
Plan Check / Job No.
B24LA13726
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 32'-0" x 37'-6" DETACHED, FULLY ELECTRIC ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c) AND (e). WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 9/1/2024
Issuing Office
Current Status
CofO Issued on 3/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/17/2024 APPLICANT
Assigned to Plan Check Engineer 7/22/2024 MADISON ODELL
Corrections Issued 7/23/2024 MADISON ODELL
Applicant returned to address corrections 8/15/2024 SARKIS HARABEDIAN
Plan Check Approved 8/31/2024 SARKIS HARABEDIAN
Issued 9/1/2024 APPLICANT
CofO in Progress 2/28/2025 EUGENE CASSIDY
Permit Finaled 3/3/2025 ANSON MAGLASANG
CofO Issued 3/3/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 8/2/2024 KHAING AYE
Roof/Waste drainage to street Cleared 8/15/2024 JILVER MAZARIEGOS
Eng Process Fee Ord 176,300 Cleared 8/29/2024 JILVER MAZARIEGOS
Sewer availability Cleared 8/29/2024 JILVER MAZARIEGOS

Contact Information

Contractor Owner-Builder       ,
Engineer Xi,, Wang; Lic. No.: C85148 422 FALLINGSTAR      IRVINE, CA 92614

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/9/2024 Approved JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 9/26/2024 Approved EUGENE CASSIDY
Footing/Foundation/Slab 9/26/2024 Approved EUGENE CASSIDY
METHANE-Barrier 9/26/2024 Approved EUGENE CASSIDY
METHANE-Subgrade 9/26/2024 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/3/2024 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 10/3/2024 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/7/2024 Partial Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/11/2024 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/16/2024 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/21/2024 Partial Approval EUGENE CASSIDY
Green Building Rough 10/21/2024 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 10/21/2024 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 10/21/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/25/2024 Not Ready for Inspection EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 10/25/2024 Not Ready for Inspection EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 10/29/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/31/2024 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 11/6/2024 Approved EUGENE CASSIDY
Green Building Rough 11/6/2024 Approved EUGENE CASSIDY
Insulation 11/6/2024 Approved EUGENE CASSIDY
Drywall Nailing 11/12/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 11/12/2024 Partial Approval EUGENE CASSIDY
Shower Pan 11/26/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 12/4/2024 Approved EUGENE CASSIDY
Sewer 12/20/2024 Approved EUGENE CASSIDY
Underground Mechanical 12/20/2024 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 12/27/2024 Corrections Issued BOBBY KEY
Underground Mechanical 12/31/2024 Approved EUGENE CASSIDY
Final 1/24/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 1/24/2025 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 1/24/2025 SGSOV Not Required EUGENE CASSIDY
Service/Power Release 1/24/2025 Not Required EUGENE CASSIDY
Smoke Detectors 1/24/2025 Approved EUGENE CASSIDY
Final 1/29/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 1/29/2025 Not Ready for Inspection EUGENE CASSIDY
Final 2/21/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 2/21/2025 Approved EUGENE CASSIDY
ELECTRICAL-Final 2/27/2025 Approved EUGENE CASSIDY
Final 2/27/2025 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 2/27/2025 Approved EUGENE CASSIDY
PLUMBING-Final 2/27/2025 Approved EUGENE CASSIDY