4172 N SUNNYSLOPE AVE 91423
Certificate Information: 4172 N SUNNYSLOPE AVE 91423
- Application / Permit
- 24010-10000-02955
- Plan Check / Job No.
- B24LA12925
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan NEW DETACHED ADU 799.9SQFT PER STATE LAW **FIRE SPRINKLER 13D REQUIRED** 2 OF 3
- Permit Issued
- Issued on 12/13/2024
- Issuing Office
- Current Status
- CofO Issued on 2/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2024 | KHUONG TRUONG |
| Corrections Issued | 7/18/2024 | KHUONG TRUONG |
| Quality Review Completed | 7/25/2024 | GARO TELMI |
| Plan Check Approved | 9/19/2024 | KHUONG TRUONG |
| Issued | 12/13/2024 | APPLICANT |
| CofO in Progress | 1/15/2026 | JOSE AVILA |
| Permit Finaled | 2/12/2026 | RUBEN SALAS |
| CofO Issued | 2/12/2026 | RUBEN SALAS |
| Permit Finaled | 2/12/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 7/30/2024 | SARAH YOUSSEF |
| Address approval | Cleared | 8/2/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 8/2/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 8/2/2024 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 8/28/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/6/2025 | Partial Approval | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 2/11/2025 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 2/13/2025 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2025 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2025 | Partial Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 4/30/2025 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 4/30/2025 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 4/30/2025 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/12/2025 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 5/12/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 5/12/2025 | Corrections Issued | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 5/12/2025 | Approved | MISAEL ESPARZA |
| Special/Order Compliance | 5/13/2025 | Partial Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 5/21/2025 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Rough | 5/21/2025 | Approved | JUAN VALENZUELA |
| Green Building Rough | 5/21/2025 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 5/21/2025 | Partial Approval | JUAN VALENZUELA |
| Shower Pan | 5/21/2025 | Approved | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 5/21/2025 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 5/28/2025 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 5/28/2025 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 10/15/2025 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 10/15/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| Final | 10/15/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| Footing/Foundation/Slab | 10/15/2025 | Approved | JUAN VALENZUELA |
| Green Building Final | 10/15/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Final | 10/15/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Final | 10/15/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| Service/Power Release | 10/15/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| Smoke Detectors | 10/15/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| Final | 12/26/2025 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 12/26/2025 | Approved | JACK KARGODORIAN |
| Service/Power Release | 12/26/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Smoke Detectors | 12/26/2025 | Approved | JACK KARGODORIAN |
| Final | 1/14/2026 | OK to Issue CofO | JOSE AVILA |
| Service/Power Release | 1/14/2026 | Approved | JOSE AVILA |