1406 W 59TH ST 90047
Certificate Information: 1406 W 59TH ST 90047
- Application / Permit
- 24010-10000-02942
- Plan Check / Job No.
- B24LA13572
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2- STORY SFD TYPE VB CONSTRUCTION, PER ENGINEER DESIGN ***FIRE SPRINKLER 13D REQUIRED***
- Permit Issued
- Issued on 1/6/2025
- Issuing Office
- Metro
- Current Status
- Issued on 1/6/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2024 | KHUONG TRUONG |
| Corrections Issued | 8/7/2024 | KHUONG TRUONG |
| Quality Review Completed | 8/9/2024 | KEN GILL |
| Building Plans Picked Up | 8/15/2024 | APPLICANT |
| Applicant returned to address corrections | 12/10/2024 | KHUONG TRUONG |
| Plan Check Approved | 1/3/2025 | KHUONG TRUONG |
| Issued | 1/6/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/10/2024 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 9/10/2024 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/12/2024 | JEANIE LAM |
| Sewer availability | Cleared | 9/12/2024 | JEANIE LAM |
| ZA Case | Cleared | 9/12/2024 | DAVID URITA |
| Hydrant and Access approval | Cleared | 11/26/2024 | JERRY KAO |
| Historic Resource Verification | Cleared | 12/2/2024 | YASMINE BASHIRI |
| Redevelopment Project Area | Cleared | 12/2/2024 | YASMINE BASHIRI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/17/2025 | Corrections Issued | BARRY HACHE |
| Sewer | 4/17/2025 | Corrections Issued | BARRY HACHE |
| Footing/Foundation/Slab | 5/16/2025 | Approved | BARRY HACHE |
| PLUMBING-Rough | 5/16/2025 | Partial Approval | BARRY HACHE |
| PLUMBING-Rough | 12/11/2025 | Corrections Issued | BARRY HACHE |
| Sewer | 12/11/2025 | Partial Approval | BARRY HACHE |
| ELECTRICAL-Rough | 12/29/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 12/29/2025 | Corrections Issued | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2025 | Corrections Issued | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 1/2/2026 | Not Ready for Inspection | JOSH MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2026 | Corrections Issued | BARRY HACHE |
| Deputy Wood Construction | 1/6/2026 | Conditional Approval | BARRY HACHE |
| Deputy Wood Construction | 1/7/2026 | Conditional Approval | BARRY HACHE |
| ELECTRICAL-Rough | 1/16/2026 | Not Ready for Inspection | BARRY HACHE |
| HVAC-Rough | 1/16/2026 | Not Ready for Inspection | BARRY HACHE |
| PLUMBING-Rough | 1/16/2026 | Approved | BARRY HACHE |
| ELECTRICAL-Rough | 1/23/2026 | Approved | BARRY HACHE |
| HVAC-Rough | 1/23/2026 | Not Ready for Inspection | BARRY HACHE |
| Interior/Exterior Lathing | 1/28/2026 | Approved | BARRY HACHE |
| HVAC-Rough | 1/30/2026 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 2/2/2026 | Corrections Issued | BARRY HACHE |
| Green Building Rough | 2/2/2026 | Approved | BARRY HACHE |
| Verify Sprinkler Sign Off | 2/2/2026 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 2/9/2026 | Corrections Issued | BARRY HACHE |
| BUILDING-Rough-Frame | 2/17/2026 | Approved | BARRY HACHE |
| Insulation | 2/27/2026 | Corrections Issued | ALEX COLIN |
| Drywall Nailing | 3/18/2026 | Corrections Issued | BARRY HACHE |
| Drywall Nailing | 3/25/2026 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 3/25/2026 | Not Ready for Inspection | ALEX COLIN |
| Interior/Exterior Lathing | 3/31/2026 | Approved | BARRY HACHE |
| Shower Pan | 3/31/2026 | Approved | BARRY HACHE |