761 N ALMAR AVE 90272

Certificate Information: 761 N ALMAR AVE 90272

Application / Permit
24010-10000-02941
Plan Check / Job No.
B24LA13220
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
(N) DETACHED ONE STORY RECREATION ROOM
Permit Issued
Issued on 12/19/2024
Issuing Office
Current Status
Issued on 12/19/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/11/2024 APPLICANT
Assigned to Plan Check Engineer 7/11/2024 SERGIO GUTIERREZ
Corrections Issued 7/16/2024 SERGIO GUTIERREZ
Quality Review Completed 7/23/2024 JOHNNY WU
Plan Check Approved 12/18/2024 SERGIO GUTIERREZ
Issued 12/19/2024 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 7/27/2024 LIAM ODONOVAN
Eng Process Fee Ord 176,300 Cleared 8/6/2024 LIAM ODONOVAN
Hydrant and Access approval Cleared 10/18/2024 RUEL COLE
Roof/Waste drainage to street Cleared 11/19/2024 VLADIMIR ARUTYUNYAN
GPI Written Notices Cleared 12/18/2024 SERGIO GUTIERREZ
Grading Pre-Inspection Cleared 12/18/2024 SERGIO GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367
Engineer Montemayor,, G F; Lic. No.: C25258 1617 S WAVERLY GLEN WAY      HACIENDA HEIGHTS, CA 91745

Inspector Information

MEL KHACHATOURIAN, (213) 796-6439 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/3/2025 Corrections Issued MEL KHACHATOURIAN
Footing/Foundation/Slab 9/8/2025 Partial Approval MEL KHACHATOURIAN
Footing/Foundation/Slab 9/23/2025 Approved MEL KHACHATOURIAN
PLUMBING-Rough 2/25/2026 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 2/27/2026 Approved MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 3/2/2026 Partial Approval MEL KHACHATOURIAN
Green Building Rough 3/2/2026 Not Ready for Inspection MEL KHACHATOURIAN
Verify Sprinkler Sign Off 3/2/2026 Approved MEL KHACHATOURIAN
ELECTRICAL-Rough 3/6/2026 Conditional Approval MEL KHACHATOURIAN
HVAC-Rough 3/6/2026 Approved MEL KHACHATOURIAN
ELECTRICAL-Rough 3/9/2026 Not Ready for Inspection MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 3/9/2026 Corrections Issued MICHAEL ALLEN
BUILDING-Rough-Frame 3/10/2026 Partial Approval EVAN COOPER
Green Building Rough 3/10/2026 Not Ready for Inspection EVAN COOPER
Interior/Exterior Lathing 3/18/2026 Conditional Approval MEL KHACHATOURIAN
Interior/Exterior Lathing 4/14/2026 Partial Approval DANIEL VERA
BUILDING-Rough-Frame 4/16/2026 Conditional Approval MEL KHACHATOURIAN
Green Building Rough 4/16/2026 Approved MEL KHACHATOURIAN
Insulation 4/22/2026 Conditional Approval BOBBY KEY
Shower Pan 4/23/2026 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 5/4/2026 Partial Approval BOBBY KEY
Drywall Nailing 5/8/2026 Approved MEL KHACHATOURIAN