818 1/2 N MCDONALD AVE 90744
Certificate Information: 818 1/2 N MCDONALD AVE 90744
- Application / Permit
- 24010-10000-02934
- Plan Check / Job No.
- B24LA13543
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 29'-11" x 25'-8" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) AND (d).
- Permit Issued
- Issued on 10/7/2024
- Issuing Office
- Current Status
- CofO Issued on 2/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2024 | GIOVANNY CHAVEZ |
| Corrections Issued | 7/23/2024 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 9/11/2024 | GIOVANNY CHAVEZ |
| Plan Check Approved | 10/5/2024 | GIOVANNY CHAVEZ |
| Issued | 10/7/2024 | APPLICANT |
| CofO in Progress | 2/25/2025 | EUGENE CASSIDY |
| CofO Issued | 2/26/2025 | ANSON MAGLASANG |
| Permit Finaled | 2/26/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 8/6/2024 | JILVER MAZARIEGOS |
| Roof/Waste drainage to street | Cleared | 8/6/2024 | JILVER MAZARIEGOS |
| Sewer availability | Cleared | 8/8/2024 | JILVER MAZARIEGOS |
| "Q" conditions | Cleared | 8/20/2024 | DAVID URITA |
| Clean Up Green Up | Cleared | 8/20/2024 | DAVID URITA |
| Eng Process Fee Ord 176,300 | Cleared | 9/3/2024 | JILVER MAZARIEGOS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nagovitsyn,, Evgeny; Lic. No.: C93527 | 17436 ARMINTA ST NORTHRIDGE, CA 91325 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/28/2024 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 10/28/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Barrier | 10/28/2024 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 10/28/2024 | Approved | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 10/31/2024 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 10/31/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 11/1/2024 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 11/6/2024 | Partial Approval | BEN MOLSTAD |
| Green Building Rough | 11/6/2024 | Not Ready for Inspection | BEN MOLSTAD |
| METHANE-Rough | 11/6/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 11/6/2024 | Partial Approval | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 11/6/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Insulation | 11/7/2024 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2024 | Partial Approval | BEN MOLSTAD |
| Pre-Inspection | 11/12/2024 | Approved | BEN MOLSTAD |
| Wood Frame | 11/12/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 12/10/2024 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 12/10/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 12/10/2024 | Approved | EUGENE CASSIDY |
| Sewer | 12/10/2024 | Partial Approval | EUGENE CASSIDY |
| Wood Frame | 12/10/2024 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 12/12/2024 | Approved | EUGENE CASSIDY |
| Green Building Rough | 12/12/2024 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 12/12/2024 | Approved | EUGENE CASSIDY |
| Insulation | 12/19/2024 | Corrections Issued | EUGENE CASSIDY |
| Interior/Exterior Lathing | 12/19/2024 | Approved | EUGENE CASSIDY |
| Shower Pan | 12/19/2024 | Approved | EUGENE CASSIDY |
| Insulation | 12/23/2024 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 12/23/2024 | Approved | EUGENE CASSIDY |
| Shower Pan | 12/23/2024 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 12/27/2024 | Approved | BOBBY KEY |
| Final | 2/3/2025 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 2/3/2025 | Approved | EUGENE CASSIDY |
| Green Building Final | 2/3/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 2/3/2025 | SGSOV Not Required | EUGENE CASSIDY |
| Service/Power Release | 2/3/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 2/3/2025 | Approved | EUGENE CASSIDY |
| Final | 2/10/2025 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 2/10/2025 | Approved | EUGENE CASSIDY |
| Service/Power Release | 2/10/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 2/24/2025 | Approved | EUGENE CASSIDY |
| Final | 2/24/2025 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 2/24/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 2/24/2025 | Approved | EUGENE CASSIDY |
| Service/Power Release | 2/24/2025 | Approved | EUGENE CASSIDY |