438-438 1/2 W 71ST ST 90003

Certificate Information: 438-438 1/2 W 71ST ST 90003

Application / Permit
24010-10000-02920
Plan Check / Job No.
B24LA13494
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ePlan: (N) 2-STORY DUPLEX WITH ATTACHED GARAGE. 13D FIRE SPRINKLER THROUGH-OUT.
Permit Issued
Issued on 1/3/2025
Issuing Office
Current Status
CofO Issued on 7/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/16/2024 APPLICANT
Assigned to Plan Check Engineer 7/18/2024 DANIEL YIP
Corrections Issued 7/21/2024 DANIEL YIP
Quality Review Completed 7/22/2024 GARO TELMI
Plan Check Approved 12/24/2024 DANIEL YIP
Issued 1/3/2025 APPLICANT
CofO in Progress 7/25/2025 RONNIE MINDANAO
Permit Finaled 7/27/2025 DEROLD HAUFF
Permit Finaled 7/27/2025 DEROLD HAUFF
CofO Issued 7/27/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/21/2024 CHRISTINA BRACO
Roof/Waste drainage to street Cleared 8/21/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 9/10/2024 CHRISTINA BRACO
Permit Cleared 9/10/2024 CHRISTINA BRACO
Sewer availability Cleared 9/10/2024 CHRISTINA BRACO
Low Impact Development (LID) Cleared 9/12/2024 ORVAL HERNANDEZ-MARCI
Hydrant and Access approval Cleared 10/29/2024 KURT CORRAL
Trees in Parkway Cleared 11/25/2024 MIGUEL ORNELAS
SB8 RUD Cleared 12/23/2024 SAMANTHA RIVERA

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/31/2025 Approved BARRY HACHE
PLUMBING-Rough 3/4/2025 Approved JOSE MACIAS
Underground Mechanical 3/4/2025 Not Ready for Inspection JOSE MACIAS
Wood Frame 3/4/2025 Partial Approval JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 3/7/2025 Partial Approval WILLIAM SIERRA
Insulation 3/7/2025 Partial Approval WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 3/10/2025 Partial Approval BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 3/24/2025 Approved BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 4/10/2025 Approved WAYNE REGESTER
HVAC-Rough 4/28/2025 Corrections Issued BARRY HACHE
PLUMBING-Rough 4/28/2025 Approved BARRY HACHE
ELECTRICAL-Rough 4/29/2025 Corrections Issued BARRY HACHE
ELECTRICAL-Rough 5/1/2025 Approved BARRY HACHE
BUILDING-Rough-Frame 5/5/2025 Corrections Issued BARRY HACHE
Green Building Rough 5/5/2025 Approved BARRY HACHE
MERV13>=Rough 5/5/2025 Approved BARRY HACHE
Verify Sprinkler Sign Off 5/5/2025 Approved BARRY HACHE
BUILDING-Rough-Frame 5/6/2025 Approved BARRY HACHE
Insulation 5/6/2025 Approved BARRY HACHE
Drywall Nailing 5/14/2025 Approved BARRY HACHE
Interior/Exterior Lathing 5/14/2025 Approved BARRY HACHE
ELECTRICAL-Final 7/16/2025 Conditional Approval BARRY HACHE
HVAC-Final 7/16/2025 Corrections Issued BARRY HACHE
Final 7/17/2025 Not Ready for Inspection BARRY HACHE
Green Building Final 7/17/2025 Corrections Issued BARRY HACHE
HVAC-Final 7/17/2025 Approved BARRY HACHE
MERV13>=Final 7/17/2025 Approved BARRY HACHE
PLUMBING-Final 7/17/2025 Approved BARRY HACHE
SGSOV-Seismic Gas S/O Valve 7/17/2025 SGSOV Not Required BARRY HACHE
Service/Power Release 7/17/2025 Not Ready for Inspection BARRY HACHE
Smoke Detectors 7/17/2025 Corrections Issued BARRY HACHE
ELECTRICAL-Final 7/21/2025 Approved WAYNE REGESTER
Final 7/21/2025 Not Ready for Inspection WAYNE REGESTER
Green Building Final 7/21/2025 Approved WAYNE REGESTER
Service/Power Release 7/21/2025 Approved WAYNE REGESTER
Smoke Detectors 7/21/2025 Approved WAYNE REGESTER
Special/Order Compliance 7/21/2025 Not Ready for Inspection WAYNE REGESTER
Final 7/24/2025 OK to Issue CofO RONNIE MINDANAO