1029 S RIDGELEY DR 90019
Certificate Information: 1029 S RIDGELEY DR 90019
- Application / Permit
- 24010-10000-02905
- Plan Check / Job No.
- B24LA13436
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d), ALL WORK PER ENG.
- Permit Issued
- Issued on 1/6/2025
- Issuing Office
- Current Status
- CofO Issued on 8/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/19/2024 | ROSENDO MEDINA |
| Corrections Issued | 7/21/2024 | ROSENDO MEDINA |
| Applicant returned to address corrections | 10/2/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 11/20/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 12/11/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 1/5/2025 | LUISANGEL VALENZUELA |
| Issued | 1/6/2025 | APPLICANT |
| CofO in Progress | 8/6/2025 | RONNIE MINDANAO |
| Permit Finaled | 8/21/2025 | DEROLD HAUFF |
| CofO Issued | 8/21/2025 | DEROLD HAUFF |
| Permit Finaled | 8/21/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/17/2024 | JESSICA OPINION |
| HPOZ | Cleared | 10/24/2024 | ERIK VAN BREENE |
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 10/30/2024 | JESSICA OPINION |
| Construction near power lines | Cleared | 12/18/2024 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 12/23/2024 | JESSICA OPINION |
Contact Information
| Contractor | Vaisman Construction Inc; Lic. No.: 1076712-B | , |
| Engineer | Ramos,, Victor; Lic. No.: C86568 | 4823 ALMAGUER AVE GUADALUPE, CA 93434 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/29/2025 | Partial Approval | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 2/11/2025 | Corrections Issued | JOSE MACIAS |
| METHANE-Subgrade | 2/11/2025 | Not Ready for Inspection | JOSE MACIAS |
| Sewer | 2/11/2025 | Corrections Issued | JOSE MACIAS |
| Footing/Foundation/Slab | 2/24/2025 | Corrections Issued | RONNIE MINDANAO |
| METHANE-Barrier | 2/24/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Rough | 2/24/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Subgrade | 2/24/2025 | Approved | RONNIE MINDANAO |
| Sewer | 2/24/2025 | Corrections Issued | RONNIE MINDANAO |
| METHANE-Barrier | 2/28/2025 | Approved | RONNIE MINDANAO |
| Sewer | 2/28/2025 | Approved | RONNIE MINDANAO |
| Footing/Foundation/Slab | 3/6/2025 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 4/15/2025 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Rough | 4/15/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Rough | 4/15/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Underground Mechanical | 4/15/2025 | Corrections Issued | RONNIE MINDANAO |
| ELECTRICAL-Rough | 4/17/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| HVAC-Rough | 4/17/2025 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Rough | 4/17/2025 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Shower Pan | 4/21/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 4/28/2025 | Conditional Approval | RONNIE MINDANAO |
| Green Building Rough | 4/28/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Rough | 4/28/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Interior/Exterior Lathing | 5/1/2025 | Corrections Issued | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 5/5/2025 | Conditional Approval | JOSE MACIAS |
| ELECTRICAL-Rough | 5/5/2025 | Approved | JOSE MACIAS |
| Green Building Rough | 5/5/2025 | Approved | JOSE MACIAS |
| HVAC-Rough | 5/5/2025 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 5/5/2025 | Approved | JOSE MACIAS |
| METHANE-Final | 5/5/2025 | Not Ready for Inspection | JOSE MACIAS |
| METHANE-Rough | 5/5/2025 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 5/5/2025 | Approved | JOSE MACIAS |
| Rough-Elec/Plmb/HVAC | 5/5/2025 | Not Ready for Inspection | JOSE MACIAS |
| Verify Sprinkler Sign Off | 5/5/2025 | Approved | JOSE MACIAS |
| Insulation | 5/6/2025 | Corrections Issued | RONNIE MINDANAO |
| Interior/Exterior Lathing | 5/8/2025 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 5/13/2025 | Approved | ALEX COLIN |
| Insulation | 5/13/2025 | Approved | ALEX COLIN |
| BUILDING-Rough-Frame | 7/11/2025 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Final | 7/11/2025 | Corrections Issued | JOSE MACIAS |
| Final | 7/11/2025 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 7/11/2025 | Approved | JOSE MACIAS |
| HVAC-Final | 7/11/2025 | Corrections Issued | JOSE MACIAS |
| METHANE-Final | 7/11/2025 | Corrections Issued | JOSE MACIAS |
| METHANE-Rough | 7/11/2025 | Approved | JOSE MACIAS |
| PLUMBING-Final | 7/11/2025 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 7/11/2025 | SGSOV Approved | JOSE MACIAS |
| Service/Power Release | 7/11/2025 | Not Ready for Inspection | JOSE MACIAS |
| Smoke Detectors | 7/11/2025 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 7/17/2025 | Approved | RONNIE MINDANAO |
| Final | 7/17/2025 | Corrections Issued | RONNIE MINDANAO |
| METHANE-Final | 7/17/2025 | Approved | RONNIE MINDANAO |
| METHANE-Rough | 7/17/2025 | Approved | RONNIE MINDANAO |
| Service/Power Release | 7/17/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 8/5/2025 | OK to Issue CofO | RONNIE MINDANAO |
| Service/Power Release | 8/5/2025 | Approved | RONNIE MINDANAO |