4129 S CENTINELA AVE 1-72 90066
Certificate Information: 4129 S CENTINELA AVE 1-72 90066
- Application / Permit
- 24010-10000-02877
- Plan Check / Job No.
- B24LA13222
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 7 STORY 72 UNITS (56 LI + 15 MI + 1 MGR) AFFORDABLE HOUSING APARTMENT TO INCLUDE 5 STORY TYPE IIIA APARTMENT OVER 2 STORY TYPE IA APARTMENT AND RETAIL, USING 12.22.A.25 INCENTIVES
- Permit Issued
- Issued on 12/15/2025
- Issuing Office
- Metro
- Current Status
- Issued on 12/15/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2024 | MANUEL MONTUFAR |
| Assigned to Zoning Architect | 7/19/2024 | NICOLE SALEEBA |
| Corrections Issued | 7/31/2024 | MANUEL MONTUFAR |
| Quality Review Completed | 8/1/2024 | EUGENE BARBEAU |
| Plan Check Approved | 12/11/2025 | VU NGUYEN |
| Issued | 12/15/2025 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 2/5/2025 | SARAH YOUSSEF |
| Eng Process Fee Ord 176,300 | Cleared | 2/12/2025 | DARIN LAM |
| Bicycle Parking | Cleared | 2/20/2025 | DARIN LAM |
| Address approval | Cleared | 3/4/2025 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 3/4/2025 | DARIN LAM |
| Construction near power lines | Cleared | 3/11/2025 | RIDWAN HARDY |
| Work Adjacent to Public Way | Cleared | 3/14/2025 | LIAM ODONOVAN |
| Highway dedication | Cleared | 4/7/2025 | KIMBERLY HERNANDEZ |
| Highway dedication | Cleared | 4/7/2025 | KIMBERLY HERNANDEZ |
| Miscellaneous | Cleared | 4/23/2025 | KIMBERLY HERNANDEZ |
| Miscellaneous | Cleared | 4/23/2025 | KIMBERLY HERNANDEZ |
| Trees in Parkway | Cleared | 6/6/2025 | MIGUEL ORNELAS |
| Permit | Cleared | 6/10/2025 | JESUS CISNEROS |
| Frnt yard landscape/Water mgmt | Cleared | 8/21/2025 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 8/21/2025 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 8/21/2025 | JAZMIN ROQUE |
| ZA Case | Cleared | 8/21/2025 | JAZMIN ROQUE |
| DAS Clearance | Cleared | 8/28/2025 | ELIZABETH TOMS |
| Specific Plan | Cleared | 9/4/2025 | RICHARD WOO |
| Green Code | Cleared | 9/18/2025 | MANUEL MONTUFAR |
| Hydrant and Access approval | Cleared | 10/8/2025 | LAVEON RIDER |
| Density Bonus | Cleared | 10/14/2025 | OLIVIA JIN |
| Density Bonus | Cleared | 10/14/2025 | OLIVIA JIN |
| SB8 RUD | Cleared | 10/14/2025 | OLIVIA JIN |
| Miscellaneous | Cleared | 10/20/2025 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 10/20/2025 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 10/20/2025 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 10/20/2025 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 10/20/2025 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 10/20/2025 | JAZMIN ROQUE |
| Zoning Plan Check | Cleared | 10/22/2025 | NICOLE SALEEBA |
| Fire Marshal Fire Life Safety | Cleared | 11/4/2025 | FIRE DEPARTMENT |
| Sewer availability | Cleared | 11/5/2025 | DARIN LAM |
Contact Information
| Architect | , ; Lic. No.: C34124 | , |
| Contractor | Steiner Douglas Construction Inc; Lic. No.: 916002-B | , |
| Engineer | Pukkanasut,, Jirayus; Lic. No.: C73728 | 1424 ROLLING HILLS DR FULLERTON, CA 92835 |
| Engineer | Xia,, Ji; Lic. No.: S7144 | 260 S LOS ROBLES AVE, STE 100 PASADENA, CA 91101 |
Inspector Information
| DERRICK SPENCER, (310) 914-3919 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 2/10/2026 | Partial Approval | VASIL MIHALEV |
| Deputy Reinf. Concrete | 2/13/2026 | Approved | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2026 | Partial Approval | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2026 | Partial Approval | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2026 | Partial Approval | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2026 | Partial Approval | DERRICK SPENCER |
| Deputy Wood Construction | 4/16/2026 | Conditional Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2026 | Partial Approval | DERRICK SPENCER |
| Order to Comply | 4/29/2026 | Not Required | DERRICK SPENCER |
| Order to Comply | 5/21/2026 | Not Required | DERRICK SPENCER |
| Pre-Inspection | 5/26/2026 | Approved | DERRICK SPENCER |
| Deputy Wood Construction | 6/1/2026 | Approved | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2026 | Partial Approval | DERRICK SPENCER |
| Order to Comply | 6/3/2026 | Not Required | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2026 | Partial Approval | DERRICK SPENCER |
| Deputy Wood Construction | 6/16/2026 | Approved | DERRICK SPENCER |
| Insulation | 6/16/2026 | Partial Approval | DERRICK SPENCER |
| Deputy Wood Construction | 6/22/2026 | Approved | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2026 | Partial Approval | DERRICK SPENCER |
| Deputy Wood Construction | 6/26/2026 | Approved | DERRICK SPENCER |
| Insulation | 7/8/2026 | Partial Approval | DERRICK SPENCER |
| Insulation | 7/17/2026 | Partial Approval | DERRICK SPENCER |