1223 3/4 N AVENUE 45 90041
Certificate Information: 1223 3/4 N AVENUE 45 90041
- Application / Permit
- 24010-10000-02776
- Plan Check / Job No.
- B24LA12685
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: New TYPE V-A Detached ADU at the rear of the lot per ordinance and engineering design. All electric
- Permit Issued
- Issued on 12/12/2024
- Issuing Office
- Current Status
- CofO Issued on 12/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2024 | WEIJIAN HUANG |
| Corrections Issued | 7/29/2024 | WEIJIAN HUANG |
| Quality Review Completed | 8/15/2024 | DANIEL CHAN |
| Applicant returned to address corrections | 10/10/2024 | WEIJIAN HUANG |
| Applicant returned to address corrections | 11/6/2024 | WEIJIAN HUANG |
| Applicant returned to address corrections | 12/10/2024 | WEIJIAN HUANG |
| Plan Check Approved | 12/11/2024 | WEIJIAN HUANG |
| Issued | 12/12/2024 | APPLICANT |
| CofO in Progress | 12/24/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 12/27/2025 | DEROLD HAUFF |
| CofO Issued | 12/27/2025 | DEROLD HAUFF |
| Permit Finaled | 12/27/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 8/20/2024 | AMBER CAMPBELL |
| BHO/Hillside ordinance | Cleared | 8/20/2024 | AMBER CAMPBELL |
| BHO/Hillside ordinance | Cleared | 8/20/2024 | AMBER CAMPBELL |
| BHO/Hillside ordinance | Cleared | 8/20/2024 | AMBER CAMPBELL |
| BHO/Hillside ordinance | Cleared | 8/20/2024 | AMBER CAMPBELL |
| Grading Pre-Inspection | Cleared | 8/20/2024 | LANNY MERRICK |
| Hold | Cleared | 9/11/2024 | SANDRA SOH |
| Tenant Habitability Plan | Cleared | 9/11/2024 | HUGO GARRIDO GARZA |
| Eng Process Fee Ord 176,300 | Cleared | 9/12/2024 | AMBER CAMPBELL |
| Sewer availability | Cleared | 9/12/2024 | AMBER CAMPBELL |
| Roof/Waste drainage to street | Cleared | 9/13/2024 | AMBER CAMPBELL |
| Hydrant and Access approval | Cleared | 11/12/2024 | JERRY KAO |
| GPI Written Notices | Cleared | 12/5/2024 | WEIJIAN HUANG |
| Address approval | Cleared | 12/9/2024 | AMBER CAMPBELL |
Contact Information
| Architect | Van, Grunsven, Gregory D; Lic. No.: C36145 | 4819 ALGOMA AVENUE LOS ANGELES, CA 90041 |
| Contractor | Owner-Builder | , |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
| Geologist | Robles,, Gustavo; Lic. No.: EG2422 | 981 W. ARROW HIGHWAY #191 SAN DIMAS, CA 91773 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/15/2025 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 1/27/2025 | Partial Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 2/28/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 3/6/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 3/11/2025 | Approved | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2025 | Partial Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 4/9/2025 | Partial Approval | NICHOLAS LOPEZ |
| Sewer | 4/9/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 6/9/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2025 | Corrections Issued | NICHOLAS LOPEZ |
| HVAC-Rough | 6/9/2025 | Corrections Issued | NICHOLAS LOPEZ |
| PLUMBING-Rough | 6/9/2025 | Approved | NICHOLAS LOPEZ |
| Deputy Wood Construction | 6/11/2025 | Conditional Approval | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 6/23/2025 | Approved | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2025 | Approved | DAVID WILLIAMS |
| HVAC-Rough | 6/23/2025 | Approved | DAVID WILLIAMS |
| Insulation | 6/26/2025 | Not Ready for Inspection | REGINA MENDEZ |
| BUILDING-Rough-Frame | 6/30/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 6/30/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 6/30/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 6/30/2025 | Approved | NICHOLAS LOPEZ |
| Verify Sprinkler Sign Off | 6/30/2025 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 7/14/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 7/14/2025 | Approved | REGINA MENDEZ |
| ELECTRICAL-Rough | 9/25/2025 | Partial Approval | NICHOLAS LOPEZ |
| Masonry Wall/Backfill | 10/17/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 10/21/2025 | Corrections Issued | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 10/24/2025 | Approved | NICHOLAS LOPEZ |
| Final | 10/24/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 10/24/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| HVAC-Final | 10/24/2025 | Corrections Issued | NICHOLAS LOPEZ |
| PLUMBING-Final | 10/24/2025 | Corrections Issued | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 10/24/2025 | SGSOV No Gas | NICHOLAS LOPEZ |
| Service/Power Release | 10/24/2025 | Not Required | NICHOLAS LOPEZ |
| Smoke Detectors | 10/24/2025 | Approved | NICHOLAS LOPEZ |
| Final | 12/24/2025 | OK to Issue CofO | NICHOLAS LOPEZ |
| Green Building Final | 12/24/2025 | Approved | NICHOLAS LOPEZ |