18313 W LORNE ST 91335

Certificate Information: 18313 W LORNE ST 91335

Application / Permit
24010-10000-02752
Plan Check / Job No.
B24LA12614
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE WITH ADDITION TO NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
Permit Issued
Issued on 4/9/2025
Issuing Office
Current Status
CofO Issued on 10/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/8/2024 APPLICANT
Assigned to Plan Check Engineer 7/12/2024 ALEC MOUSAKHANIAN
Corrections Issued 7/15/2024 ALEC MOUSAKHANIAN
Applicant returned to address corrections 8/7/2024 PINANK PATEL
Applicant returned to address corrections 8/21/2024 PINANK PATEL
Applicant returned to address corrections 8/29/2024 PINANK PATEL
Plan Check Approved 12/12/2024 PINANK PATEL
Issued 4/9/2025 APPLICANT
CofO in Progress 10/4/2025 ARUTYUN MADATYAN
Permit Finaled 10/28/2025 JOHN JANSON
CofO Issued 10/28/2025 JOHN JANSON
Permit Finaled 10/28/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/9/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 8/9/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 8/20/2024 BIAINA HARITUNIAN
Sewer availability Cleared 9/4/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 11/25/2024 RIDWAN HARDY
Construction within easement Cleared 11/25/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Santos,, Michael; Lic. No.: C77657 16202 ORION AVE      CHINO, CA 91708

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/1/2025 Partial Inspection ARUTYUN MADATYAN
PLUMBING-Rough 5/16/2025 Partial Approval SCOTT SOBEL
Footing/Foundation/Slab 5/29/2025 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 7/15/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Rough 7/16/2025 Approved ARUTYUN MADATYAN
PLUMBING-Rough 7/16/2025 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 7/23/2025 Corrections Issued ARUTYUN MADATYAN
Interior/Exterior Lathing 7/23/2025 Corrections Issued ARUTYUN MADATYAN
BUILDING-Rough-Frame 7/31/2025 Approved ARUTYUN MADATYAN
HVAC-Rough 7/31/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 7/31/2025 Partial Approval ARUTYUN MADATYAN
Insulation 8/8/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 8/8/2025 Partial Approval ARUTYUN MADATYAN
Drywall Nailing 8/13/2025 Approved ARUTYUN MADATYAN
Gas Test 9/11/2025 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Final 9/18/2025 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 9/18/2025 Partial Approval ARUTYUN MADATYAN
Sewer 9/18/2025 Approved ARUTYUN MADATYAN
Final 10/1/2025 Corrections Issued ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 10/1/2025 SGSOV Approved ARUTYUN MADATYAN
Smoke Detectors 10/1/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 10/3/2025 Approved ARUTYUN MADATYAN
Final 10/3/2025 OK to Issue CofO ARUTYUN MADATYAN
HVAC-Final 10/3/2025 Approved ARUTYUN MADATYAN
PLUMBING-Final 10/3/2025 Approved ARUTYUN MADATYAN
Service/Power Release 10/3/2025 Approved ARUTYUN MADATYAN